library4-28-05 Page 1 of 3
Yorkville Public Library
Building Committee
April 28,2005
7:00 pm.
The meeting was called to order at 7:00 pm. by Jo Ann Gryder
Present
Carol La Chance, Library Board Gail Gaebler,Library Board
Michelle Pfister, Library Director Jo Ann Gryder, Library Board
Russ Walter, Library Board Marianne Wilkinson, Library Board
Sandy Lindblom,Library Board Joe Gruber,Library Board
Reco¢nition of Visitors
Art Prochaska,Mayor Tracy Pleckham,Finance Director
Rick M'Carthy, BCA Gary Williams, Building Department
Matthew Falco,BCA
Gary Williams spoke on behalf of the City of Yorkville's Building Department. He
requested 5 sets of copies of the paperwork for the building permits so there is no waiting
for the paperwork to go from department to department.
The building is 40,000 square feet including the existing building.
The fire alarm permit should be filed separately.
The review process should take approximately 3 weeks.
A question was raised if the city would waive the permit fees. Gary does not know the
answer but can find out and let the library know by Monday.
The building codes the Building Department uses are the IBC 2000 unamended.
Construction Bond interest
The actual amount of Bond interest available will not be available until the Bonds are
sold and the money is put into the bank. At least %i of the Bonds are expected to be sold
in June. Tracy conservatively estimated the interest to be $90,000. She said that is about
3%interest. The local Banks will bid on the Bonds so the library can acquire the best
rate.
Additional Funding from the City
Art has gotten an agreement from 2 of the builders for the development fees. They will
pay $250 of the$500 per home at the time of the final plat. The Bristol Bay development
has about 2100 homes and he is not sure how many Prestwick has.
Enerav Grant
There was paperwork in the packet BCA provided with information about 2 different
grants the library could apply for. The only drawback to qualifying for the grants is that
the library would have to put more money into the plan for lighting and energy efficiency.
Page 2 of 3
Budget Shortfall
This was discussed. There is a shortfall because of the inflation of building materials.
This was unexpected. Generally a 3 '/2%inflation rate is expected,but this year costs
have gone up about 20 %. Rick and Matt explained that putting some of their suggestions
in as alternate bids would free up the money the library is short, and if money becomes
available they would be added back into the project. Omit means they would no longer
discuss the option to leave the item out or change it.
Value Engineering—Existing Library Renovation
This will become an Alternate Bid item.
Value Engineering—Square Foot Reduction
It was decided that this would be omitted. The way Yorkville is growing,there is no way
the Board members want a smaller Library.
Storm water Detention
After further evaluation,this does not look to be as complicated as was originally
thought. The estimated cost is about$20,000.
Water Main Location
There was a sketch passed out to the Board members. The City Engineer would like to
see a 20 foot setback from the water main. The way the plans are currently laid out there
is only a 10 foot setback. The reason the setback needs to be so far is because of all the
running sand in the area. Different options will be considered before anything is final.
Revised Police Route
Art disliked BCA's current plan for remodeling the parking lots. He would like to see the
police have more than one exit form the parking lot. Matt had spoken to a police officer
and felt the police liked the new plan. Perhaps the proposed revision could add a second
exit from the police parking lot.
Technology Scope
Rich suggested that the Library should write a new contract with KJW W to be contracted
under BCA. KJW W will still do exactly what it is doing,but the technology bid will go
out at the same time as BCA's bid, and everything will be covered under the same
insurance.
Owner's Roresentative
Rick handed out some information and forms to fill out with what he believes this project
will require as far as an Owner's Rep, and what the people applying for the job will need
to know about the job specifications.
Pape 3 of 3
Project Schedule
Due to the value engineering research, and the need to write up all the alternate bids,
BCA will need additional time to prepare the construction documents for bidding. They
end of July is when the bidding process is expected to be finished.
There was further discussion about selecting an Owner's Rep. The board members
decided that in order to choose the best qualified person for the job, each applicant should
fill out the same paperwork and RFQ(Request for Qualification). The city attorney will
be asked to review the paperwork provided by BCA and also will be asked if it is
necessary to post an ad for the position, or if the selected people can be given the forms
without posting the ad.
Adiournment
Jo Ann Gryder adjourned the meeting at 8:20 pm.
Minutes submitted by Laura Leppert.