Public Works Packet 2019 03-19-19
AGENDA
PUBLIC WORKS COMMITTEE MEETING
Tuesday, March 19, 2019
6:00 p.m.
City Hall Conference Room
800 Game Farm Road, Yorkville, IL
Citizen Comments:
Minutes for Correction/Approval: February 19, 2019
New Business:
1. PW 2019-13 Snow Operations Report
2. PW 2019-14 Fox Highlands – Raintree Village Water Main Interconnect – Change Order No. 1
3. PW 2019-15 Church Street Sanitary Sewer Improvements – Engineering Agreement
4. PW 2019-16 2019 Road to Better Roads Program – Contract Award
5. PW 2019-17 Fox Hill Unit 7 – Easement Abrogation
6. PW 2019-18 Wyland National Mayors Challenge for Conservation
7. PW 2019-19 Hanging Baskets
8. PW 2019-20 Utility Box Art
9. PW 2019-21 Speed Sign Update
Old Business:
1. PW 2018-102 East Alley and Van Emmon
Additional Business:
2018/2019 City Council Goals – Public Works Committee
Goal Priority Staff
“Road to Better Roads Funding” 5 Bart Olson, Eric Dhuse & Rob Fredrickson
“Water Planning” 6 Eric Dhuse & Brad Sanderson
“Municipal Building Needs & Planning” 7 Bart Olson, Eric Dhuse, Rob Fredrickson,
Tim Evans & Erin Willrett
“Traffic Patrol” 9 Eric Dhuse & Rich Hart
“Whispering Meadows” 10 Bart Olson & Brad Sanderson
“Vehicle Replacement” 12 Bart Olson, Eric Dhuse, Rob Fredrickson,
Rich Hart & Tim Evans
“Water Conservation Plan” 14 Eric Dhuse & Brad Sanderson
“Capital Improvement Plan” 16 Eric Dhuse, Rob Fredrickson &
Brad Sanderson
United City of Yorkville
800 Game Farm Road
Yorkville, Illinois 60560
Telephone: 630-553-4350
www.yorkville.il.us
UNITED CITY OF YORKVILLE
WORKSHEET
PUBLIC WORKS COMMITTEE
Tuesday, March 19, 2019
6:00 PM
CITY HALL CONFERENCE ROOM
---------------------------------------------------------------------------------------------------------------------------------------
CITIZEN COMMENTS:
---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------
MINUTES FOR CORRECTION/APPROVAL:
---------------------------------------------------------------------------------------------------------------------------------------
1. February 19, 2019
□ Approved __________
□ As presented
□ With corrections
---------------------------------------------------------------------------------------------------------------------------------------
NEW BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
1. PW 2019-13 Snow Operations Report
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
2. PW 2019-14 Fox Highlands – Raintree Village Water Main Interconnect – Change Order No. 1
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
3. PW 2019-15 Church Street Sanitary Sewer Improvements – Engineering Agreement
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
4. PW 2019-16 2019 Road to Better Roads Program – Contract Award
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
5. PW 2019-17 Fox Hill Unit 7 – Easement Abrogation
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
6. PW 2019-18 Wyland National Mayors Challenge for Conservation
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
7. PW 2019-19 Hanging Baskets
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
8. PW 2019-20 Utility Box Art
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
9. PW 2019-21 Speed Sign Update
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
OLD BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
1. PW 2018-102 East Alley and Van Emmon
□ Moved forward to CC __________ consent agenda? Y N
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
ADDITIONAL BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
Minutes
Tracking Number
Minutes of the Public Works Committee – February 19, 2019
Public Works Committee – March 19, 2019
Majority
Committee Approval
Minute Taker
Name Department
Page 1 of 2
DRAFT
UNITED CITY OF YORKVILLE
PUBLIC WORKS COMMITTEE
Tuesday, February 19, 2019, 6:00pm
Yorkville City Hall, Conference Room
800 Game Farm Road
IN ATTENDANCE:
Committee Members
Chairman Joel Frieders Alderman Seaver Tarulis
Alderman Jackie Milschewski Alderman Ken Koch
Other City Officials
City Administrator Bart Olson Engineer Brad Sanderson, EEI
Assistant City Administrator Erin Willrett Public Works Director Eric Dhuse
Other Guests:
Mark Lewan, Rowdy's Dan Thatcher, Rowdy's
The meeting was called to order at 6:00pm by Chairman Joel Frieders.
Citizen Comments: None
At this time, Chairman Frieders paid tribute to those who were killed in the recent shooting in Aurora.
Previous Meeting Minutes: January 15, 2019
The minutes were approved as presented.
New Business:
1. PW 2019-09 Snow Operations Report
Mr. Dhuse said salt usage was almost 1,200 tons and a total of about 10,000 miles were driven by each
the big trucks and smaller trucks. Additional salt was recently ordered and the state allocation has now
been met. Mr. Olson noted that 40 tons of salt were sold to the school district at cost since they
depleted their supply. Four trucks are in various stages of repair/operation. He said there are 9 plow
routes and one truck is needed as a backup. The fleet of trucks will be considered as part of the budget
proposals.
2. PW 2019-10 Water Department Reports for October, November, December 2018
Director Dhuse said there was nothing outstanding in the reports and Public Works continues to comply
with EPA rules. Only two breaks were noted so far this year. These reports move to the Council
consent agenda.
Page 2 of 2
3. PW 2019-11 Downtown Train Track Gates
Mr. Olson said there was no repair or replacement update from the railroad following two high profile
incidents in the last month including a gate malfunction and train malfunction. Alderman Milschewski
asked about fines when the crossings are blocked and Mr. Olson said there is a fee structure, but he is
unaware of the amounts. Chairman Frieders noted other traffic problems in general, on Rt. 47 and
construction on Rt. 34 and said he had attended a Sugar Grove planning meeting last month. Mr.
Olson noted that funding for Rt. 47 from Galena to Cross St. has been approved.
4. PW 2019-12 Windett Ridge Bond Release.
Developers have completed all the items except a shared use path repair for which they will pay cash to
the city in lieu of repair. The repair is a short patch at a cost of $3,200. Staff is OK with that decision
and when the check is received, Mr. Sanderson recommended release of the maintenance bond. The
HOA has been notified and a letter was also sent notifying them that they need to assume the trail
maintenance this year. This moves to the Council consent agenda.
Old Business: None
1. PW 2018-102 East Alley and Van Emmon
The traffic issues resulting from drop-offs/pick-ups of students at YPAC was discussed at least month's
meeting and this was brought back for further consideration. Mr. Olson said 4 options have been
drafted stating the pros and cons, with the staff recommendation being option #3. After committee
discussion, option #2 was determined to the best solution with proper signage, repairs, striping, etc.
Mr. Olson said a recommended light is not included in the cost estimate and that information will be
brought to the next meeting. Another option is to place a light on the back of the Farm Bureau
building. The construction will also be subject to an agreement with the owner of Imperial
Investments.
Additional Business:
Ms. Milschewski noted a light burned out on the bridge.
There was no further business and the meeting was adjourned at 6:25pm.
Minutes respectfully transcribed by
Marlys Young, Minute Taker
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #1
Tracking Number
PW 2019-13
Snow Operations Report March 2019
Public Works Committee – March 19, 2019
None
Informational only
Snow operations report from Feb 16th – March 11th
Eric Dhuse Public Works
Name Department
Summary
Below please find the monthly report for snow removal operations. I have also included
salt and brine data that we have gathered from our trucks.
Background
The PW and Parks Departments performed snow removal operations on February 17th
and February 20th. These snow events were nothing out of the ordinary and were dealt with
easily. Below, please find the spreadsheet which details the totals for the month.
2/14‐3/11
3/11/2019
Recorder ED
Total Miles Average Lbs of Tons of Lbs of Gallons of Gal Brine/ Salt Brine
Route Truck ID Driven MPH Salt Used Salt Used Salt/Mi. Brine Used Ton Salt Miles Miles
1 9 179.40 15.00 42292.00 21.15 458.00 325.00 15.37 107.00 107.00
2 27 134.40 7.20 29956.00 14.98 370.00 449.00 29.98 81.00 73.00
3 13 148.70 7.00 35533.00 17.77 395.00 405.00 22.80 90.00 90.00
4 23 189.40 8.00 44592.00 22.30 402.00 168.00 7.53 111.00 83.00
5 10 Shop 0.00 0.00 0.00
6 28 115.30 5.00 39128.00 19.56 398.00 479.00 24.48 98.00 98.00
7 22 0.00 0.00
8 11 189.00 11.00 35047.00 17.52 381.00 510.00 29.10 92.00 92.00
956 6.65 226548 113 343.43 2336 21.54 579 543
Avg. Avg. Avg.
Additional tons of salt estimated to be used by truck 22 20
Additional tons of salt estimated to be used by one ton trucks 18
TOTAL ESTIMATED SALT USAGE 151
Snow Event Date MONTHLY TOTALS
Date of Recording
EVENT TOTALS
Fleet Status
Y10- was repaired, but not in time to plow. The cost was originally estimated at $3500, came in
at a little over $5000. Needed more parts which took longer to replace.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, Administrator
Date: March 11, 2019
Subject: March Snow Operations Report
Y 28 – Still have not taken to get repaired. Using as a salt truck until winter is over.
Y22 – Still trying to get all the parts needed to complete this truck. Did receive a few more, but
not the main harness.
Y19 – Bent plow frame. Replaced damaged part, operational once more.
Recommendation
I would ask that this be placed on the March 19, 2019 Public Works Committee meeting
as an informational item. If you have any questions or need further information, please let me
know.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/gov_officials.php
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #2
Tracking Number
PW 2019-14
Fox Highlands-Raintree Village Water Main Interconnect
Public Works Committee – March 19, 2019
Majority
Consideration of Approval
Consideration of Change Order No. 1
Brad Sanderson Engineering
Name Department
The purpose of this memo is to present Change Order No. 1 for the above referenced project.
A Change Order, as defined by in the General Conditions of the Contract Documents, is a written order to
the Contractor authorizing an addition, deletion or revision in the work within the general scope of the
Contract Documents, or authorizing an adjustment in the Contract Price or Contract Time.
Background:
The United City of Yorkville and Innovative Underground, LLC entered into an agreement for a contract
value of $292,304.00 for the above referenced project.
Questions Presented:
Should the City approve Change Order No. 1 which would decrease the contract amount by $49,859.32.
Discussion:
Changes are per as-built quantities measured in the field. Please see the attached summary spreadsheet.
We are recommending approval of the change order.
Action Required:
Consideration of approval of Change Order No. 1 in the amount of $49,859.32
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Erin Willrett, Assistant City Administrator
Krysti Barksdale-Noble, Community Dev. Dir.
Lisa Pickering, Deputy City Clerk
Date: March 19, 2019
Subject: Fox Highlands Water Main Interconnect
CHANGE ORDER
Order No. 1 (Balancing)
Date: March 4, 2019
Agreement Date: May 10, 2018
NAME OF PROJECT: Fox Highlands-Raintree Village Water Main Interconnect
OWNER: United City of Yorkville
CONTRACTOR: Vian Construction Co., Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. SEE ATTACHED
Change of CONTRACT PRICE:
Original CONTRACT PRICE: $292,304.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $292,304.00
The CONTRACT PRICE due to this CHANGE ORDER will be (increased) (decreased)
by: $49,859.32
The new CONTRACT PRICE including this CHANGE ORDER will be: $242,444.68
Change to CONTRACT TIME:
The CONTRACT TIME will be (increased) (decreased) by 0 calendar days.
The date for completion of all work will be November 15, 2018
Justification
1-24) Changes per as-built quantities measured in the field.
Approvals Required
Requested by: Vian Construction Co., Inc.
Recommended by: Engineering Enterprises, Inc.
Accepted by: United City of Yorkville
CHANGE ORDER NO. 1 (BALANCE)
FOX HIGHLANDS-RAINTREE VILLAGE WATER MAIN INTERCONNECT
UNITED CITY OF YORKVILLE
QUANTITY COST QUANTITY COST
1 FOOT 1,010 108.00$ 0 -$ 85.5 9,234.00$
2 FOOT 188 40.00$ 0 -$ 48 1,920.00$
3 LB 740 5.00$ 0 -$ 172 860.00$
4 EACH 1 1,200.00$ 0 -$ 1 1,200.00$
5 FOOT 25 56.00$ 0 -$ 25 1,400.00$
6 CUYD 250 22.00$ 0 -$ 250 5,500.00$
7 EACH 4 300.00$ 0 -$ 1 300.00$
8 LB 3812 2.00$ 0 -$ 3197 6,394.00$
9 SQYD 1,540 4.00$ 11 44.00$ 0 -$
10 TON 230 126.00$ 0 -$ 9.7 1,222.20$
11 TON 140 88.00$ 15.37 1,352.56$ 0 -$
12 FOOT 2000 2.00$ 53.5 107.00$ 0 -$
13 SQFT 225 10.00$ 0 -$ 225 2,250.00$
14 FOOT 55 48.00$ 0 -$ 27 1,296.00$
15 SQYD 30 88.00$ 0 -$ 30 2,640.00$
16 EACH 2 400.00$ 0 -$ 2 800.00$
17 FOOT 60 65.00$ 0 -$ 60 3,900.00$
18 FOOT 10 70.00$ 0 -$ 10 700.00$
19 FOOT 10 375.00$ 0 -$ 10 3,750.00$
20 SQYD 90 45.00$ 85.2 3,834.00$ 0 -$
21 TON 50 50.00$ 0 -$ 50 2,500.00$
22 TON 50 50.00$ 0 -$ 50 2,500.00$
23 FOOT 200 4.00$ 0 -$ 200 800.00$
24 UNIT 10000 1.00$ 0 -$ 6030.68 6,030.68$
5,337.56$
(55,196.88)$
292,304.00$
292,304.00$
($49,859.32)
242,444.68$
COMBINATION CURB AND GUTTER REMOVAL AND REPLACEMENT
PCC DRIVEWAY REMOVAL AND REPLACEMENT
STORM SEWER REPAIR, RCP, 12-INCH
HOT-MIX ASPHALT PAVEMENT REMOVAL
HOT-MIX ASPHALT BINDER COURSE, IL-19.0, N50
HOT-MIX ASPHALT SURFACE COURSE, MIX "D", N50
ROADWAY EDGE CRACK SEALING
SIDEWALK REMOVAL AND REPLACEMENT
RESTORATION
PERIMETER EROSION BARRIER
STORM SEWER REPAIR, RCP, 15-INCH
STORM SEWER REPAIR, RCP, 30-INCH
NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL, TYPE 1
NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL, TYPE 2
NEW CONTRACT PRICE:
ALLOWANCE - ITEMS ORDERED BY THE ENGINEER
TOTAL ADDITIONS =
TOTAL DEDUCTIONS =
ORIGINAL CONTRACT PRICE:
CURRENT CONTRACT PRICE ADJUSTED BY PREVIOUS CHANGE ORDERS:
AMOUNT OF CURRENT CHANGE ORDER:
DEDUCTIONSITEMS
SANITARY SERVICE REPAIR, PVC SDR-26, D-2241, 6-INCH
ITEM NO.UNIT CONTRACT
QUANTITY UNIT PRICE ADDITIONS
WATER MAIN, 8-INCH D.I.P, CLASS 52, WITH POLYETHYLENE WRAP
WATER MAIN PROTECTION, PVC, C-900, 12-INCH
DUCTILE IRON FITTINGS
WATER SERVICE CONNECTION, 1-INCH
WATER SERVICE PIPE, 1-INCH TYPE K COPPER
FOUNDATION MATERIAL
EXPLORATORY EXCAVATION
BITUMINOIS MATERIALS (TACK COAT)
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #3
Tracking Number
PW 2019-15
Church Street Sanitary Sewer Improvements – Engineering Agreement
Public Works Committee – March 19, 2019
Majority
Approval
Please see attached.
Bart Olson Administration
Name Department
Church Street Sanitary Sewer Improvements
United City of Yorkville, Kendall County, IL
Professional Services Agreement - Design and Construction Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter referred
to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter referred to as
the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
ENGINEER agrees to furnish to the City the following services: The ENGINEER shall
provide any and all necessary engineering services to the City as indicated on the
included exhibits. Design and Construction engineering will be provided for sanitary
sewer rehabilitation and lining on Church Street (see Exhibit 5 for project limits).
Engineering will be in accordance with all City, Standard Specifications for Water and
Sewer Construction in Illinois, Illinois Department of Transportation, and Illinois
Environmental Protection Agency requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the ENGINEER
shall be compensated for all work performed for the City prior to termination.
C. Compensation and maximum amounts due to ENGINEER:
ENGINEER shall receive as compensation for all work and services to be performed
herein, an amount based on the Estimate of Level of Effort and Associated Cost included
in Exhibit 3. Design Engineering will be paid for as a Fixed Fee (FF) in the amount of
$13,215 and Construction Engineering will be paid for Hourly (HR) at the actual rates for
services to be performed, currently estimated at $15,999. The hourly rates for this project
are shown in the attached 2018 Standard Schedule of Charges (Exhibit 6). All payments
will be made according to the Illinois State Prompt Payment Act and not less than once
every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing Contract,
ENGINEER, on or before February 1st of any given year, shall provide written notice of
any change in the rates specified in Section C hereof (or on any attachments hereto) and
said changes shall only be effective on and after May 1st of that same year.
Church Street Sanitary Sewer Improvements
United City of Yorkville
Professional Services Agreement
Design and Construction Engineering
E. Ownership of Records and Documents:
ENGINEER agrees that all books and records and other recorded information developed
specifically in connection with this agreement shall remain the property of the City.
ENGINEER agrees to keep such information confidential and not to disclose or
disseminate the information to third parties without the consent of the City. This
confidentiality shall not apply to material or information, which would otherwise be
subject to public disclosure through the freedom of information act or if already
previously disclosed by a third party. Upon termination of this agreement, ENGINEER
agrees to return all such materials to the City. The City agrees not to modify any original
documents produced by ENGINEER without contractors consent. Modifications of any
signed duplicate original document not authorized by ENGINEER will be at OWNER’s
sole risk and without legal liability to the ENGINEER. Use of any incomplete, unsigned
document will, likewise, be at the OWNER’s sole risk and without legal liability to the
ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the State of
Illinois. Venue shall be in Kendall County, Illinois.
G. Independent Contractor:
ENGINEER shall have sole control over the manner and means of providing the work
and services performed under this agreement. The City’s relationship to the ENGINEER
under this agreement shall be that of an independent contractor. ENGINEER will not be
considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The Contractor certifies that if any of its personnel are an employee
of the State of Illinois, they have permission from their employer to perform the service.
Anti-Bribery : The Contractor certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or admission of
bribery or attempted bribery of an officer or employee of the State of Illinois or any
other state.
Loan Default: If the Contractor is an individual, the Contractor certifies that he/she is not
in default for a period of six months or more in an amount of $600 or more on the
repayment of any educational loan guaranteed by the Illinois State Scholarship
Commission made by an Illinois institution of higher education or any other loan made
from public funds for the purpose of financing higher education (5 ILCS 385/3).
Church Street Sanitary Sewer Improvements
United City of Yorkville
Professional Services Agreement
Design and Construction Engineering
Felony Certification: The Contractor certifies that it is not barred pursuant to 30 Illinois
Compiled Statutes 500/50-10 from conducting business with the State of Illinois or any
agency as a result of being convicted of a felony.
Barred from Contracting : The Contractor certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720 Illinois
Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The Contractor certifies that it is in compliance with the Drug
Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective date of this
contract. The Drug Free Workplace Act requires, in part, that Contractors, with 25 or
more employees certify and agree to take steps to ensure a drug free workplace by
informing employees of the dangers of drug abuse, of the availability of any treatment or
assistance program, of prohibited activities and of sanctions that will be imposed for
violations; and that individuals with contracts certify that they will not engage in the
manufacture, distribution, dispensation, possession, or use of a controlled substance in
the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity : The Contractor
agrees to comply with applicable provisions of the Illinois Human Rights Act (775
Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the Americans with Disabilities
Act, Section 504 of the U.S. Rehabilitation Act and the rules applicable to each. The
equal opportunity clause of Section 750.10 of the Illinois Department of Human Rights
Rules is specifically incorporated herein. The Contractor shall comply with Executive
Order 11246, entitled Equal Employment Opportunity, as amended by Executive Order
11375, and as supplemented by U.S. Department of Labor regulations (41 C.F.R. Chapter
60). The Contractor agrees to incorporate this clause into all subcontracts under this
Contract.
International Boycott: The Contractor certifies that neither it nor any substantially owned
affiliated company is participating or shall participate in an international boycott in
violation of the provisions of the U.S. Export Administration Act of 1979 or the
regulations of the U.S. Department of Commerce promulgated under that Act (30 ILCS
582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires the
Contractor (and any subcontractors) to maintain, for a period of 3 years after the later of
the date of completion of this Contract or the date of final payment under the Contract, all
books and records relating to the performance of the Contract and necessary to support
amounts charged to the City under the Contract. The Contract and all books and records
related to the Contract shall be available for review and audit by the City and the Illinois
Auditor General. If this Contract is funded from contract/grant funds provided by the
U.S. Government, the Contract, books, and records shall be available for review and
audit by the Comptroller General of the U.S. and/or the Inspector General of the federal
Church Street Sanitary Sewer Improvements
United City of Yorkville
Professional Services Agreement
Design and Construction Engineering
sponsoring agency. The Contractor agrees to cooperate fully with any audit and to
provide full access to all relevant materials.
United States Resident Certification: (This certification must be included in all contracts
involving personal services by non-resident aliens and foreign entities in accordance with
requirements imposed by the Internal Revenue Services for withholding and reporting
federal income taxes.) The Contractor certifies that he/she is a: x United States Citizen
___ Resident Alien ___ Non-Resident Alien The Internal Revenue Service requires that
taxes be withheld on payments made to non resident aliens for the performance of
personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the Contractor certifies that its
Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real Estate
Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership ___ Tax
Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit Corporation
___ Trust or Estate ___ Medical and Health Care Services Provider Corp.
I. Indemnification:
ENGINEER shall indemnify and hold harmless the City and City’s agents, servants, and
employees against all loss, damage, and expense which it may sustain or for which it will
become liable on account of injury to or death of persons, or on account of damage to or
destruction of property resulting from the performance of work under this agreement by
ENGINEER or its Subcontractors, or due to or arising in any manner from the wrongful
act or negligence of ENGINEER or its Subcontractors of any employee of any of them.
In the event that the either party shall bring any suit, cause of action or counterclaim
against the other party, the non-prevailing party shall pay to the prevailing party the cost
and expenses incurred to answer and/or defend such action, including reasonable attorney
fees and court costs. In no event shall the either party indemnify any other party for the
consequences of that party’s negligence, including failure to follow the ENGINEER’s
recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of the types
of services rendered hereunder. (Not applicable as having been previously supplied)
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attachments.
Except for those terms included on the attachments, no additional terms are included as a
part of this agreement. All prior understandings and agreements between the parties are
merged into this agreement, and this agreement may not be modified orally or in any
Church Street Sanitary Sewer Improvements
United City of Yorkville
Professional Services Agreement
Design and Construction Engineering
manner other than by an agreement in writing signed by both parties. In the event that
any provisions of this agreement shall be held to be invalid or unenforceable, the
remaining provisions shall be valid and binding on the parties. The list of exhibits is as
follows:
Exhibit 1: Professional Engineering Services
Exhibit 2: Limitation of Authority, Duties and Responsibilities of the
Resident Construction Observer
Exhibit 3: Estimate of Level of Effort and Associated Cost
Exhibit 4: Anticipated Project Schedule
Exhibit 5: Location Map
Exhibit 6: 2018 Standard Schedule of Charges
L. Notices:
All notices required to be given under the terms of this agreement shall be given mail,
addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
800 Game Farm Road Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time to time substitute addresses or
persons in connection with required notices.
Agreed to this _____day of __________________, 2019.
United City of Yorkville: Engineering Enterprises, Inc.:
_________________________________ ________________________________
Gary Golinski Brad Sanderson, P.E.
Mayor Vice President
_________________________________ ________________________________
Beth Warren Angie Smith
City Clerk Executive Assistant
1
EXHIBIT 1
SECTION A - PROFESSIONAL DESIGN ENGINEERING SERVICES
For purposes of this Exhibit 1 and all attachments hereto, the term “contractor” shall not
refer to Engineering Enterprises, Inc., but shall instead refer to individuals or companies
contracted with, to construct or otherwise manage the project described herein. The
ENGINEER shall furnish professional design engineering services as follows:
1. The ENGINEER will attend conferences with the OWNER, or other interested
parties as may be reasonably necessary.
2. The ENGINEER will perform the necessary design surveys, accomplish the
detailed design of the project, prepare construction drawings, specifications and
contract documents, and prepare a final cost estimate based on final design for the
entire system. It is also understood that if subsurface explorations (such as
borings, soil tests, rock soundings and the like) are required, the ENGINEER will
furnish coordination of said explorations without additional charge, but the costs
incident to such e xplorations shall be paid for by the OWNER as set out in
Section D hereof.
3. The contract documents furnished by the ENGINEER under Section A-2 shall
utilize IEPA endorsed construction contract documents, including Supplemental
General Conditions, Contract Change Orders, and partial payment estimates.
4. Prior to the advertisement for bids, the ENGINEER will provide for each
construction contract, not to exceed 10 copies of detailed drawings, specifications,
and contract documents for use by the OWNER, appropriate Federal, State, and
local agencies from whom approval of the project must be obtained. The cost of
such drawings, specifications, and contract documents shall be included in the
basic compensation paid to the ENGINEER.
2
5. The ENGINEER will furnish add itional copies of the drawings, specifications and
contract documents as required by prospective bidders, material suppliers, and
other interested parties, but may charge them for the reasonable cost of such
copies. Upon award of each contract, the ENGINEER will furnish to the
OWNER five sets of the drawings, specifications and contract documents for
execution. The cost of these sets shall be included in the basic compensation paid
to the ENGINEER. Original documents, survey notes, tracings, and the like ,
except those furnished to the ENGINEER by the OWNER, are and shall remain
the property of the ENGINEER.
6. The drawings prepared by the ENGINEER under the provisions of Section A -2
above shall be in sufficient detail to permit the actual location of the proposed
improvements on the ground. The ENGINEER shall prepare and furnish to the
OWNER without any additional compensation, three copies of map(s) showing
the general location of needed construction easements and permanent easements
and the land to be acquired. Property surveys, property plats, property
descriptions, abstracting and negotiations for land rights shall be accomplished by
the OWNER, unless the OWNER requests, and the ENGINEER agrees to provide
those services. In the event the ENGINEER is requested to provide such services,
the ENGINEER shall be additionally compensated as set out in Section D hereof.
7. The ENGINEER will attend the bid opening and tabulate the bid proposal, make
an analysis of the bids, and make recommendations for awarding contracts for
construction.
8. The ENGINEER further agrees to obtain and maintain, at the ENGINEER’s
expense, such insurance as will protect the ENGINEER from claims under the
Workman’s Compensation Act and such comprehensive general liability
insurance as will protect the OWNER and the ENGINEER from all claims for
bodily injury, death, or property damage which may arise from the performance
by the ENGINEER or by the ENGINEER’s employees of the ENGINEER’s
functions and services required under this Agreement.
3
9. The ENGINEER will complete the final plans, specifications and contract
documents and submit for approval of the OWNER, and all State regulatory
agencies to meet the project schedule(s) as summarized in Exhibit 4:
“Anticipated Project Schedule – Church Str eet Sanitary Sewer Improvements”
dated February 19, 2019.
SECTION B - PROFESSIONAL CONSTRUCTION ENGINEERING SERVICES
The ENGINEER shall furnish professional construction engineering services as follows:
1. The ENGINEER will review, for conformance with the design concept, shop and
working drawings required by the construction Contract Documents and indicate
on the drawings the action taken. Such action shall be taken with reasonable
promptness.
2. The ENGINEER will interpret the intent of the drawings a nd specifications to
protect the OWNER against defects and deficiencies in construction on the part of
the contractors. The ENGINEER will not, however, guarantee the performance
by any contractor.
3. The ENGINEER will evaluate and determine acceptability of substitute materials
and equipment proposed by Contractor(s).
4. The ENGINEER will establish baselines for locating the work together with a
suitable number of bench marks adjacent to the work as shown in the contract
documents.
4
5. The ENGINEER will provid e general engineering review of the work of the
contractor(s) as construction progresses to ascertain that the contactor is
conforming to the design concept.
(a) ENGINEER shall have authority, as the OWNER’s representative, to
require special inspection of or testing of the work, and shall receive and
review all certificates of inspections, testing and approvals required by
laws, rules, regulations, ordinances, codes, orders or the Contract
Documents (but only to determine generally that their content comp lies
with requirements of, and the results certified indicate compliance with,
the Contract Documents).
(b) During such engineering review, ENGINEER shall have the authority, as
the OWNER’s representative, to disapprove of or reject contractor(s)’
work while it is in progress if ENGINEER believes that such work will
not produce a completed Project that conforms generally to the Contract
Documents or that it will prejudice the integrity of the design concept of
the Project as reflected in the Contract Documents.
6. The ENGINEER will provide resident construction observation. Resident
construction observation shall consist of visual inspection of materials,
equipment, or construction work for the purpose of ascertaining that the work is in
substantial confo rmance with the contract documents and with the design intent.
Such observation shall not be relied upon by others as acceptance of the work.
The ENGINEER’s undertaking hereunder shall not relieve the contractor of
contractor’s obligation to perform the work in conformity with the drawings and
specifications and in a workmanlike manner; shall not make the ENGINEER an
insurer of the contractor’s performance; and shall not impose upon the
ENGINEER any obligation to see that the work is performed in a safe manner.
Exhibit 2 - The Limitations of Authority, Duties and Responsibilities of the
Resident Construction Observer is attached to this Agreement.
5
7. The ENGINEER will cooperate and work closely with representatives of the
OWNER.
8. Based on the ENGINEER’s on-site observations as an experienced and qualified
design professional, on information provided by the Resident Construction
Observer, and upon review of applications for payment with the accompanying
data and schedules by the contractor, the ENGINEER:
(a) Shall determine the amounts owing to contractor(s) and recommend in
writing payments to contractor(s) in such amounts. Such
recommendations of payment will constitute a representation to OWNER,
based on such observations and review, that the work has progressed to
the point indicated, and that, to the best of the ENGINEER’s knowledge,
information and belief, the quality of such work is generally in accordance
with the Contract Documents (subject to an evaluation of such work as a
functioning whole prior to or upon substantial completion, to the results of
any subsequent tests called for in the Contract Documents, and to any
other qualifications stated in the recommendation).
(b) By recommending any payment, ENGINEER will not hereby be deemed
to have represented that exhaustive, continuous or detailed reviews or
examinations have been made by ENGINEER to check the quality or
quantity of contractor(s)’ work as it is furnished and performed beyond the
responsibilities specifically assigned to ENGINEER in the Agree ment and
the Contract Documents. ENGINEER’s review of contractor(s)’ work for
the purposes of recommending payments will not impose on Engineer
responsibility to supervise, direct or control such work or for the means,
methods, techniques, sequences, or procedures of construction or safety
precautions or programs incident thereto or contractor(s) compliance with
laws, rules, regulations, ordinances, codes or orders applicable to their
furnishing and performing the work. It will also not impose responsibility
on ENGINEER to make any examination to ascertain how or for what
6
purposes any contractor has used the moneys paid on account of the
Contract Price, or to determine that title to any of the work, materials
equipment has passed to OWNER free and clear of any lien, claims,
security interests, or encumbrances, or that there may not be other matters
at issue between OWNER and contractor that might affect the amount that
should be paid.
9. The ENGINEER will prepare necessary contract change orders for approval of
the OWNER, and others on a timely basis.
10. The ENGINEER will make a final review prior to the issuance of the statement of
substantial completion of all construction and submit a written report to the
OWNER. Prior to submitting the final pay estimate, the ENGINEER shall submit
the statement of completion to and obtain the written acceptance of the facility
from the OWNER.
11. The ENGINEER will provide the OWNER with one set of reproducible record
(as-built) drawings, and two sets of prints at no additional cost to the OWNER.
Such drawings will be based upon construction records provided by the contractor
during construction and reviewed by the resident construction observer and from
the resident construction observer’s construction data.
12. If State Statutes require notices and advertisements of final payment, the
ENGINEER shall assist in their preparation.
13. The ENGINEER will be available to furnish engineering services and
consultations necessary to correct unforeseen project operation difficulties for a
period of one year after the date of statement of substantial completion of the
facility. This service will include instruction of the OWNER in initial project
operation and maintenance but will not include supervision of normal operation of
the sys tem. Such consultation and advice shall be at the hourly rates as described
in the attached Exhibit 6: Standard Schedule of Charges dated January 1, 2018.
7
The ENGINEER will assist the OWNER in performing a review of the project
during the 11th month afte r the date of the certificate of substantial completion.
14. The ENGINEER further agrees to obtain and maintain, at the ENGINEER’s
expense, such insurance as will protect the ENGINEER from claims under the
Workman’s Compensation Act and such comprehensive general liability
insurance as will protect the OWNER and the ENGINEER from all claims for
bodily injury, death, or property damage which may arise from the performance
by the ENGINEER or by the ENGINEER’s employees of the ENGINEER’s
functions and services required under this Agreement.
15. The ENGINEER will provide construction engineering services in accordance
with the periods summarized in Exhibit 4: “Anticipated Project Schedule –
Church Street Sanitary Sewer Improvements” dated February 19, 2019.
If the above is not accomplished within the time period specified, this Agreement may be
terminated by the OWNER. The time for completion may be extended by the OWNER
for a reasonable time if completion is delayed due to unforeseeable cases beyond the
control and without the fault or negligence of the ENGINEER. Pursuant to Paragraph D
“Changes in Rates of Compensation”, the contract shall be designated on-going
consistent with the project schedule.
8
SECTION C – COMPENSATION FOR ENGINEERING SERVICES
1. The OWNER shall compensate the ENGINEER for professional design
engineering services in the amount of $13,215 (FF) as summarized on Exhibit 3:
“Estimate of Level of Effort and Associated Cost for Professional Engineering
Services for Church Street Sanitary Sewer Improvements” dated February 19,
2019.
(a) The compensation for the professional design engineering services shall
be payable as follows:
(1) A sum which does not exceed ninety percent (90%) of the total
comp ensation payable under Section C -1 shall be paid in monthly
in crements for work actually completed and invoiced, for grant
administration and for the preparation and submission to the
OWNER and/or IEPA of the construction drawings, specifications,
cost estimates and contract documents.
(2) A sum which, together with the compensation paid pursuant to
Section C-1(a)(1) above, equals one hundred percent (100%) of the
total compensation due and payable in accord with Section C -1
above, shall be due immediately after the award of construction
contract(s) is approved by the corporate authorities.
2. The OWNER shall compensate the ENGINEER for the construction
administration, construction staking, construction observation (including the
Resident Construction Observer), and any additional consultation and surveying
services on the basis of Hourly Rates (HR) as described on the attached Exhibit 6:
Standard Schedule of Charges dated January 1, 2018. The estimated values are
included in Exhibit 3: “Estimate of Level of Effort and Associated Cost for
Professional Engineering Services for Church Street Sanitary Sewer
9
Improvements” dated February 19, 2019 and are estimated at $15,999 Hourly
(HR).
(a) The compensation for the construction administration, construction
staking, construction observation (including the Resident Construction
Observer), and any additional consultation and surveying services shall be
payable as follows:
(1) A sum which equals any charges for work actually completed and
invoiced shall be paid at least once per month.
3. The OWNER shall compensate the ENGINEER for direct expenses as identified
in the contract and as noted on Exhib it 3 at the actual cost or hourly cost for the
work completed.
(1) A sum which equals any charges for work actually completed and
invoiced shall be paid at least once per month.
4. The compensation for any additional engineering services authorized by the
OWNER pursuant to Section D shall be payable as follows:
(a) A sum which equals any charges for work actually completed and
invoiced shall be paid at least once per month.
10
SECTION D – ADDITIONAL ENGINEERING SERVICES
In addition to the foregoing being performed, the following services may be provided
UPON PRIOR WRITTEN AUTHORIZATION OF THE OWNER.
1. Site surveys outside of the project limits and other similar special surveys as may
be required.
2. Laboratory tests, well tests, borings, specialized geological soils hydraulic, or
other studies recommended by the ENGINEER.
3. Property surveys, detailed description of sites, maps, drawings, or estimates
related thereto; assistance in negotiating for land and easement rights.
4. Necessary data and filing maps for litigation, such as condemnation.
5. Redesigns ordered by the OWNER after final plans have been accepted by the
OWNER and IEPA.
6. Appearances before courts or boards on matters of litigation or hearings related to
the project.
7. Preparation of environmental impact assessments or environmental impact
statements.
8. Making drawings from field measurements of existing facilities when required for
planning additions or alterations thereto.
9. Services due to changes in the scope of the Project or its design, including but not
limited to, changes in size, complexity, schedule or character of construction.
11
10. Revising studies or reports which have previously been approved by the OWNER,
or when revisions are due to cases beyond the control of the ENGINEER.
11. Preparation of design documents for alternate bids where major changes require
additional documents.
12. Preparation of detailed renderings, exhibits or scale models for the Project.
13. Providing special analysis of the OWNER’s needs such as owning and operating
analysis, plan for operation and maintenance, OWNER’s special operating
drawings or charts, and any other similar analysis.
14. The preparation of feasibility studies, appraisals and evaluations, detailed quantity
surveys of material and labor, and material audits or inventories by the OWNER.
15. Additional or extended services during construction made necessary by (1) work
damaged by fire or other cause during construction, (2) defective or incomplete
work of the contractor, and/or (3) the contractor’s default on the Construction
Contract due to delinquency or insolvency.
16. Providing design services relating to future facilities, systems and equipment
which are not intended to be constructed or operated as a part of the Project.
17. Providing other services not otherwise provided for in this Agreement, including
services normally furnished by the OWNER as described in Section E –
SPECIAL PROVISIONS – Owner’s Responsibilities.
Payment for the services specified in this Section E shall be as agreed in writing between
the OWNER and the ENGINEER prior to commencement of the work. The ENGINEER
will render to OWNER for such services an itemized bill, separate from any other billing,
once each month, for compensation for services performed hereunder during such period,
12
the same to be due and payable by OWNER to the ENGINEER on or before the 10th day
of the following period. Payment for services noted in D shall be at Actual Cost (AC),
Fixed Fee (FF) or Hourly (HR).
SECTION E - SPECIAL PROVISIONS
1. OWNER’S RESPONSIBILITIES
(a) Provide to the ENGINEER all criteria, design and construction standards
and full information as to the OWNER’s requirements for the Project.
(b) Designate a person authorized to act as the OWNER’s representative. The
OWNER or his representative shall receive and examine documents
submitted by the ENGINEER, interpret and define the OWNER’s policies
and render decisions and authorizations in writing promptly to prevent
unreasonable delay in the progress of the ENGINEER’s services.
(c) Furnish laboratory tests, air and water pollution tests, reports and
inspections of samples, materials or other items required by law or by
governmental authorities having jurisdiction over this Project, or as
recommended by the ENGINEER.
(d) Provide legal, accounting, right-of-way acquisition and insurance
counseling services necessary for the Project, legal review of the
construction Contract Documents, and such auditing services as the
OWNER may require to account for expenditures of sums paid to the
contractor.
13
(e) Furnish above services at the OWNER’s expense and in such manner that
the ENGINEER may rely upon them in the performance of his services
under this Agreement and in accordance with the Project timetable.
(f) Guarantee full and free access for the ENGINEER to enter upon all
property required for the performance of the ENGINEER’s services under
this Agreement.
(g) Give prompt written notice to the ENGINEER whenever the OWNER
observes or otherwise becomes aware of any defect in the Project or other
event which may substantially affect the ENGINEER’s performance of
services under this Agreement.
(h) Protect and preserve all survey stakes and markers placed at the project
site prior to the assumption of this responsibility by the contractor and
bear all costs of replacing stakes or markers damaged or removed during
said time interval.
2. Delegation of Duties - Neither the OWNER nor the ENGINEER shall delegate his
duties under this Agreement without the written consent of the other.
3. The ENGINEER has not been retained or compensated to provide design services
relating to the contractor’s safety precautions or to means, methods, techniques,
sequences, or procedures required by the contractor to perform his work but not
relating to the final or completed structure. Omitted services include but are not
limited to shoring, scaffolding, underpinning, temporary retainment of
excavations and any erection methods and temporary bracing.
4. The ENGINEER intends to render his services under this Agreement in
accordance with generally accepted professional practices for the intended use of
the Project.
14
5. Since the ENGINEER has no control over the cost of labor, materials, equipment
or services furnished by others, or over the contractor(s) methods of determining
prices, or over competitive bidding or market conditions, his opinions of probable
Project Costs and Construction Costs provided for herein are to be made on the
basis of his experience and qualifications and represent his best judgment as an
experienced and qualified professional engineer, familiar with the construction
industry. The ENGINEER cannot and does not guarantee that proposals, bids or
actual project or construction cost will not vary from opinions of probable cost
prepared by him. If prior to the bidding or negotiating phase OWNER wishes
greater assurance as to project or construction costs he shall employ an
independent cost-estimator.
6. Access to Records:
(a) The ENGINEER agrees to include subsections E-6(b) through E-6(e)
below in all cont racts and all subcontracts directly related to project
services which are in excess of $25,000.
(b) The ENGINEER shall maintain books, records, documents and other
evidence directly pertinent to performance of Agency loan work under this
Agreement consistent with generally accepted accounting standards in
accordance with the American Institute of Certified Public Accountants
Professional Standards (666 Fifth Avenue, New York, New York 10019;
June 1, 1987). The Agency or any of its duly authorized representatives
shall have access to such books, records, documents and other evidence
for the purpose of inspection, audit and copying. The ENGINEER will
provide facilities for such access and inspection.
(c) Audits conducted pursuant to this provision shall be in accordance with
generally accepted auditing standards.
15
(d) The ENGINEER agrees to the disclosure of all information and reports
resulting from access to records pursuant to subsection E-6(b) above, to
the Agency. Where the audit concerns the ENGINEER, the auditing
agency shall afford the ENGINEER an opportunity for an audit exit
conference and an opportunity to comment on the pertinent portions of the
draft audit report. The final audit report will include the written
comments, if any, of the audited parties.
(e) Records under subsection E-6(b) above shall be maintained and made
available during performance on Agency loan work under this agreement
and until three years from date of final Agency loan audit for the project.
In addition, those records which relate to any “dispute” appeal under an
Agency loan agreement, or litigation, or the settlement of claims arising
out of such performance, costs or items to which an audit exception has
been taken, shall be maintained and made available until three years after
the date of resolution of such appeal, litigation, claim or exception.
7. Covenant Against Contingent Fees - The ENGINEER warrants that no person or
selling agency has been employed or retained to solicit or secure this contract
upon an agreement or understanding for a commission, percentage, brokerage, or
contingent fee, excepting bonafide employees. For breach or violation of this
warranty, the loan recipient shall have the right to annul this agreement without
liability or in its discretion to deduct from the contract price or consideration or
otherwise recover, the full amount of such commission, percentage, brokerage, or
contingent fee.
8. Covenant Against Contingent Fees - The loan recipient warrants that no person or
agency has been employed or retained to solicit or secure a PWSLP loan upon an
agreement or understanding for a commission, percentage, brokerage, or
contingent fee. For breach or violation of this warranty, the Agency shall have
the right to annul the loan or to deduct from the loan or otherwise recover, the full
amount of such commission, percentage, brokerage, or contingent fee.
16
9. Certification Regarding Debarment – The ENGINEER certifies that the services
of anyone that has been debarred or suspended under Federal Executive Order
12549 has not, and will not, be used for work under this Agreement.
10. Affirmative Action – The ENGINEER agrees to take affirmative steps to assure
that disadvantaged business enterprises are utilized when possible as sources of
supplies, equipment, construction and services in accordance with the Clean
Water Loan Program rules. As required by the award conditions of USEPA's
Assistance Agreement with IEPA, the ENGINEER acknowledges that the fair
share percentages are 5% for MBEs and 12% for WBEs.
11. The ENGINEER shall not discriminate on the basis of race, color, national origin
or sex in the performance of this contract. The contractor shall carry out
applicable requirements of 40 CFR Part 33 in the award and administration of
contracts awarded under EPA financial assistance agreements. Failure by the
contractor to carry out these requirements is a material breach of this contract
which may result in the termination of this contract or other legally available
remedies.
17
EXHIBIT 2
THE LIMITATIONS OF AUTHORI TY, DUTIES AND RESPONSIBILITIES OF THE
RESIDENT CONSTRUCTION OBSERVER ARE AS FOLLOWS:
1. The Resident Construction Observer shall act under the direct supervision of the
ENGINEER, shall be the ENGINEER’s agent in all matters relating to on-site
construction review of the contractor’s work, shall communicate only with the
ENGINEER and the contractor (or contractor’s), and shall communicate with
sub contractors only through the contractor or his authorized superintendent. The
OWNER shall communicate with the Resident Construction Observer only
through the ENGINEER.
2. The Resident Construction Observer shall review and inspect on-site construction
activities of the contractor relating to portions of the Project designed and
specified by the Engineer as contained in the Construction Contract Documents.
3. Specifically omitted from the Resident Construction Observer’s duties is any
review of the contractor’s safety precautions, or the means, methods, sequences,
or procedures required for the contractor to perform the work but not relating to
the final or completed Project. Omitted design or review services include but are
not limited to shoring, scaffolding, underpinning, temporary retainment of
excavations and any erection methods and temporary bracing.
4. The specific duties and responsibilities of the Resident Construction Observer are
enumerated as follows:
(a) Schedules: Review the progress schedule, schedule of Shop Drawing
submissions and schedule of values prepared by contractor and consult
with ENGIN EER concerning their acceptability.
18
(b) Conferences: Attend preconstruction conferences. Arrange a schedule of
progress meetings and other job conferences as required in consultation
with ENGINEER and notify those expected to attend in advance. Attend
meetings and maintain and circulate copies of minutes thereof.
(c) Liaison:
(1) Serve as ENGINEER’s liaison with contractor, working principally
through contractor’s superintendent and assist him in
understanding the intent of the Contract Documents.
(2) Assist ENGINEER in serving as OWNER’s liaison with contractor
when contractor’s operations affect OWNER’s on-site operations.
(3) As requested by ENGINEER, assist in obtaining from OWNER
additional details or information, when required at the job site for
proper erection of the work.
(d) Shop Drawings and Samples:
(2) Receive and record date of receipt of Shop Drawings and samples.
(3) Receive samples which are furnished at the site by contrctor, and
notify ENGINEER of their availability for examination.
(3) Advise EN GINEER and contractor or its superintendent
immediately of the commencement of any work requiring a Shop
Drawing or sample submission if the submission has not been
approved by ENGINEER.
(e) Review of Work, Rejection of Defective Work, Inspections and Tests:
19
(1) Conduct on-site inspection of the work in progress to assist
ENGINEER in determining if the work is proceeding in
accordance with the Contract Documents and that completed work
will conform to the Contract Documents.
(2) Report to ENGINEER whenever he believes that any work is
unsatisfactory, faulty or defective or does not conform to the
Contract Documents, or does not meet the requirements of any
inspections, test or approval required to be made or has been
damaged prior to final payment; and advise ENGINEER when he
believes work should be corrected or rejected or should be
uncovered for inspection, or requires special testing, inspection or
approval.
(3) Verify that tests, equipment and systems start-ups, and operating
and maintenance instructions are conducted as required by the
Contract Documents and in presence of the required personnel, and
that contractor maintains adequate records thereof; observe, record
and report to ENGINEER appropriate details relative to the test
procedures and start-ups.
(4) Accompany visiting inspectors representing public or other
agencies having jurisdiction over the Project, record the outcome
of these inspections and report to ENGINEER.
(f) Interpretation of Contract Documents: Transmit to contractor
ENGINEER’s clarifications and interpretations of the Contract
Documents.
(g) Modifications: Consider and evaluate contractor’s suggestions for
modifications in Drawings or Specifications and report them with
recommendations to ENGINEER.
20
(h) Records:
(1) Maintain at the job site orderly files for correspondence, reports of
job conferences, Shop Drawings and samples submissions,
reproductions of original Contract Documents including all
addenda, change orders, field orders, additional drawings issued
subsequent to the execution of the Contract, ENGINEER’s
clarifications and interpretations of the Contract Documents,
progress reports, and other Project related documents.
(2) Keep a diary or log book, recording hours on the job site, weather
conditions, data relative to questions of extras or deductions, list of
visiting officials and representatives of manufacturers, fabricators,
suppliers and distributors, daily activities, decisions, observations
in general and specific observations in more detail as in the case of
observing test procedures. Send copies to ENGINEER.
(4) Record names, addresses and telephone numbers of all
contractor’s, sub contractors and major suppliers of materials and
equipment.
(i) Reports:
(1) Furnish ENGINEER periodic reports as required of progress of the
work and contractor’s compliance with the approved progress
schedule and schedule of Shop Drawing submissions.
(2) Consult with ENGINEER in advance of schedule major tests,
inspections or start of important phases of the work.
21
(3) Report immediately to ENGINEER upon the occurrence of any
accident.
(j) Payment Requisitions: Review applications for payment with contractor
for compliance with the established procedure for their submission and
forward them with recommendations to ENGINEER, noting particularly
their relation to the schedule of values, work completed and materials and
equipment delivered at the site but not incorporated in the work.
(k) Certificates, Maintenance and Operating Manuals: During the course of
the work, verify that certificates, maintenance and operation manuals and
other data required to be assembled and furnished by contractor are
applicable to the items actually installed; and deliver this material to
ENGINEER for his review and forwarding to OWNER prior to final
acceptance of the work.
(l) Completion:
(1) Before ENGINEER issues a Statement of Substantial Completion,
submit to contractor a list of observed items requiring completion
or correction.
(2) Conduct final review in the company of ENGINEER, OWNER
and contr actor and prepare a final list of items to be completed or
corrected.
(3) Verify that all items on final list have been completed or corrected
and make recommendations to ENGINEER concerning
acceptance.
ENTITY:ADMIN.WORK
PRINCIPAL SENIOR SENIOR SENIOR SENIOR ITEM COST
WORK IN PROJECT PROJECT PROJECT PROJECT PROJECT PROJECT CAD PROJECT GIS HOUR PER
ITEM CHARGE MANAGER ENGINEER I ENGINEER MANAGER SURVEYOR II TECHNICIAN MANAGER TECHNICIAN I TECHNICIAN ADMIN.SUMM.ITEM
NO.WORK ITEM HOURLY RATE:$197 $191 $149 $137 $173 $160 $149 $149 $137 $72 $70
FINAL ENGINEERING
2.1 Project Management and Administration 1 4 3 8 1,408$
2.2 Project Meetings 1 3 4 8 1,366$
2.3 Bid Package, Specifications and Estimates - 4 40 6 - 50 7,618$
2.4 Bidding and Contracting - 4 11 6 21 2,823$
Final Engineering Subtotal:2 15 58 - - - - 6 - - 6 87 13,215$
CONSTRUCTION ENGINEERING
3.1 Contract Administration - 12 14 26 4,378$
3.2 Construction Layout and Record Drawings - 1 3 4 15 23 3,565$
3.3 Observation and Documentation - 4 48 2 54 8,056$
Construction Engineering Subtotal:- 17 65 - 4 - 15 - - 2 103 15,999$
PROJECT TOTAL:2 32 123 - 4 - 15 6 - - 8 190 29,214
Printing =-$ 24,833$
Mileage =-$ 2,927$
Material Testing = -$ 894$
-$ 560$
DIRECT EXPENSES =-$ 29,214$
29,214$
G:\Public\Yorkville\2019\YO1903-P Church Street Sanitary Sewer Improvements\PSA\[03.Exhibit 3 - Level of Effort.xlsx]Fee Summary
February 13, 2019
EXHIBIT 3
ESTIMATE OF LEVEL OF EFFORT AND ASSOCIATED COST FOR
PROFESSIONAL ENGINEERING SERVICES FOR
CHURCH STREET SANITARY SEWER IMPROVEMENTS
United City of Yorkville, IL
SURVEYING
PROJECT ROLE:
DIRECT EXPENSES LABOR SUMMARY
DRAFTINGENGINEERING
TOTAL EXPENSES =
Engineering Expenses =
Surveying Expenses =
Drafting Expenses =
Environmental Assessment =Administrative Expenses =
TOTAL LABOR EXPENSES =
WORKYear:ITEMMonth:NO. WORK ITEM Week Starting:1234123412341234123412341234123412341234FINAL DESIGN ENGINEERING2.1 Project Management and Administration2.2 Project Meetings2.3 Bid Package, Specifications and Estimates2.4 Bidding and ContractingCONSTRUCTION ENGINEERING3.1 Contract Administration3.2 Construction Layout and Record Drawings3.3 Observation and DocumentationG:\Public\Yorkville\2019\YO1903-P Church Street Sanitary Sewer Improvements\PSA\[4. Exhibit 4 - Schedule.xls]ScheduleProject Management & QC/QA PermittingMeeting(s) Bidding and ContractingDesign ConstructionApril August SeptemberMay JuneMarch July October2019LegendEXHIBIT 4ANTICIPATED PROJECT SCHEDULECHURCH STREET SANITARY SEWER IMPROVEMENTSUNITED CITY OF YORKVILLE, ILFebruary 19, 2019January February
!.!.
!.
!.
!.
!.
!.
!.!.
!.
!.
!.
!.
!.
!.
!.!.
!.
!.
!.
!.!.
!.!.
!.!.
!.
!.
!.!.
!.
!.
!.
!.
!.
!.
!.
!.
!.
!.
!.
!.
!.!.!.!.
!.!.
W Somonauk St
S Bridge StN Bridge StTower LnGameFarm Rd
Church StE Somonauk St
E Spring St
E Center St
E Main St
W Main St
W Spring St
W Center St
King StW River StWest StEngineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
Legend
!.SANITARY MANHOLE
UNKNOWN SANITARY SEWER
4" SANITARY SEWER
6" SANITARY SEWER
8" SANITARY SEWER
10" SANITARY SEWER
12" SANITARY SEWER
14" SANITARY SEWER
15" SANITARY SEWER
16" SANITARY SEWER
SANITARY SEWER IMPROVEMENTS
LOCATION MAP
www.eeiweb.com
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
FEBRUARY 2019
YO1903
YO1903_Church St. PSA.MXD
H:\GIS\PUBLIC\YORKVILLE\2019\
MJT ³
200 0 200100 Feet
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #4
Tracking Number
PW 2019-16
2019 Road to Better Roads Program
Public Works Committee – March 19, 2019
Majority
Consideration of Contract Award
2019 Roads to Better Roads - Recommendation to Award
Brad Sanderson Engineering
Name Department
Bids were received, opened and tabulated for work to be done on the 2019 Roads to Better Roads
Program at 11:30 a.m., March 11, 2019. Representatives of contractors bidding the project, the
City, and our firm were in attendance. A tabulation of the bids and the engineer’s estimate is
attached for your information and record. The low bid was $624,997.07 of which $587,224.15 is
the City share and $37,772.92 is the Bristol Township share. Breakdowns for the City share and
Township share of the project are attached for your information and record. The low bid was
14.1% below our engineer’s estimate and within the FY2020 budget.
We recommend the acceptance of the bid and approval of award be made to the low bidder, D
Construction, Co., 1488 S Broadway Street, Coal City, IL 60416 in the amount of $624,997.07.
If you have any questions or require additional information, please let us know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Lisa Pickering, Deputy City Clerk
Date: March 11, 2019
Subject: 2019 Roads to Better Roads Program
BIDS RECD 3/11/2019ITEMUNIT UNIT UNIT UNIT UNITNO.DESCRIPTIONUNIT QUANTITY PRICE AMOUNT PRICE AMOUNTPRICE AMOUNT PRICE AMOUNT PRICE AMOUNT40600290 BITUMINOUS MATERIALS (TACK COAT) POUND 3015.0 0.01$ 30.15$ 5.00$ 15,075.00$ 0.75$ 2,261.25$ 0.01$ 30.15$ $0.20603.00$ 40600982HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINTSQ YD 615.0 10.00$ 6,150.00$ 20.00$ 12,300.00$ 5.00$ 3,075.00$ 12.50$ 7,687.50$ $10.006,150.00$ 40600625LEVELING BINDER (MACHINE METHOD), N50TON 2,253.0 63.00$ 141,939.00$ 68.00$ 153,204.00$ 69.50$ 156,583.50$ 73.00$ 164,469.00$ $65.00146,445.00$ 40603335HOT-MIX ASPHALT SURFACE COURSE, MIX "D", N50TON 3,378.0 63.00$ 212,814.00$ 65.00$ 219,570.00$ 70.00$ 236,460.00$ 73.00$ 246,594.00$ $65.00219,570.00$ 42400200PORTLAND CEMENT CONCRETE SIDEWALK 5 INCHSQ FT 2,567.0 6.25$ 16,043.75$ 6.15$ 15,787.05$ 6.90$ 17,712.30$ 6.15$ 15,787.05$ $7.0017,969.00$ 42400800DETECTABLE WARNINGSSQ FT 168.0 25.00$ 4,200.00$ 30.00$ 5,040.00$ 25.00$ 4,200.00$ 30.00$ 5,040.00$ $25.004,200.00$ X4401198HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTHSQ YD 40,175.0 1.45$ 58,253.75$ 1.44$ 57,852.00$ 1.75$ 70,306.25$ 1.70$ 68,297.50$ $2.50100,437.50$ 44000600SIDEWALK REMOVALSQ FT 2,937.0 2.00$ 5,874.00$ 2.10$ 6,167.70$ 1.10$ 3,230.70$ 2.10$ 6,167.70$ $2.005,874.00$ 44201670CLASS D PATCHES, TYPE I, 2 INCHSQ YD 875.0 25.00$ 21,875.00$ 20.00$ 17,500.00$ 24.00$ 21,000.00$ 35.50$ 31,062.50$ $20.0017,500.00$ 44201672CLASS D PATCHES, TYPE II, 2 INCHSQ YD 875.0 23.00$ 20,125.00$ 18.50$ 16,187.50$ 22.00$ 19,250.00$ 31.00$ 27,125.00$ $20.0017,500.00$ 44201674CLASS D PATCHES, TYPE III, 2 INCHSQ YD 875.0 22.00$ 19,250.00$ 17.00$ 14,875.00$ 18.00$ 15,750.00$ 27.00$ 23,625.00$ $20.0017,500.00$ 44201676CLASS D PATCHES, TYPE IV, 2 INCHSQ YD 1,744.0 20.00$ 34,880.00$ 15.50$ 27,032.00$ 17.00$ 29,648.00$ 23.00$ 40,112.00$ $20.0034,880.00$ 60255500MANHOLES TO BE ADJUSTEDEACH 3.0 400.00$ 1,200.00$ 510.00$ 1,530.00$ 450.00$ 1,350.00$ 950.00$ 2,850.00$ $500.001,500.00$ 60255800MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, CLOSED LIDEACH 10.0 550.00$ 5,500.00$ 770.00$ 7,700.00$ 800.00$ 8,000.00$ 1,200.00$ 12,000.00$ $800.008,000.00$ X6026050SANITARY MANHOLES TO BE ADJUSTEDEACH 1.0 550.00$ 550.00$ 990.00$ 990.00$ 750.00$ 750.00$ 1,200.00$ 1,200.00$ $900.00900.00$ X6026056SANITARY MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, CLOSED LIDEACH 1.0 700.00$ 700.00$ 1,261.75$ 1,261.75$ 1,100.00$ 1,100.00$ 1,500.00$ 1,500.00$ $1,200.001,200.00$ 60260100INLETS TO BE ADJUSTEDEACH 29.0 350.00$ 10,150.00$ 250.00$ 7,250.00$ 300.00$ 8,700.00$ 225.00$ 6,525.00$ $400.0011,600.00$ 78000100THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLSSQ FT 464.0 4.95$ 2,296.80$ 4.00$ 1,856.00$ 4.00$ 1,856.00$ 4.50$ 2,088.00$ $4.502,088.00$ 78000200THERMOPLASTIC PAVEMENT MARKING - LINE 4"FOOT 20,527.0 0.52$ 10,674.04$ 0.57$ 11,700.39$ 0.57$ 11,700.39$ 0.48$ 9,852.96$ $0.8016,421.60$ 78000400THERMOPLASTIC PAVEMENT MARKING - LINE 6"FOOT 452.0 1.37$ 619.24$ 0.75$ 339.00$ 0.75$ 339.00$ 1.25$ 565.00$ $1.20542.40$ 78000600THERMOPLASTIC PAVEMENT MARKING - LINE 12"FOOT 960.0 2.75$ 2,640.00$ 2.00$ 1,920.00$ 2.00$ 1,920.00$ 2.50$ 2,400.00$ $2.402,304.00$ D CONSTRUCTION1488 S. BroadwayCoal City, IL 60416 GENEVA CONSTRUCTIONP.O. Box 998Aurora, IL 60507 CURRAN CONTRACTING286 Memorial Ct.Crystal Lake, IL 60014BID TABULATION4413 Roosevelt Road, Suite 108Hillside, IL 60162BUILDERS PAVING, LLCSugar Grove, IL 60554ENGINEER'S ESTIMATE BID TABULATION 2019 ROAD PROGRAMUNITED CITY OF YORKVILLE52 Wheeler RoadENGINEERING ENTERPRISES, INC.52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
BIDS RECD 3/11/2019ITEMUNIT UNIT UNIT UNIT UNITNO.DESCRIPTIONUNIT QUANTITY PRICE AMOUNT PRICE AMOUNTPRICE AMOUNT PRICE AMOUNT PRICE AMOUNTD CONSTRUCTION1488 S. BroadwayCoal City, IL 60416 GENEVA CONSTRUCTIONP.O. Box 998Aurora, IL 60507 CURRAN CONTRACTING286 Memorial Ct.Crystal Lake, IL 60014BID TABULATION4413 Roosevelt Road, Suite 108Hillside, IL 60162BUILDERS PAVING, LLCSugar Grove, IL 60554ENGINEER'S ESTIMATE BID TABULATION 2019 ROAD PROGRAMUNITED CITY OF YORKVILLE52 Wheeler Road78000650THERMOPLASTIC PAVEMENT MARKING - LINE 24"FOOT 98.0 5.50$ 539.00$ 4.00$ 392.00$ 4.00$ 392.00$ 5.00$ 490.00$ $4.50441.00$ 78300200RAISED REFLECTIVE PAVEMENT MARKER REMOVALEACH 210.0 7.00$ 1,470.00$ 6.70$ 1,407.00$ 4.35$ 913.50$ 10.00$ 2,100.00$ $15.003,150.00$ X2520700SODDING, SPECIALSQ YD 462.0 15.00$ 6,930.00$ 17.16$ 7,927.92$ 15.16$ 7,003.92$ 26.70$ 12,335.40$ $20.009,240.00$ 20101700SUPPLEMENTAL WATERINGUNIT 10.0 1.00$ 10.00$ 20.00$ 200.00$ 20.00$ 200.00$ 125.00$ 1,250.00$ $300.003,000.00$ XX006172ROUTING AND SEALING CRACKSFOOT 18,438.0 0.43$ 7,928.34$ 0.39$ 7,190.82$ 0.39$ 7,190.82$ 0.88$ 16,225.44$ $2.5046,095.00$ XX004774BRICK DRIVEWAY REMOVAL AND REPLACEMENTSQ FT 36.0 50.00$ 1,800.00$ 14.00$ 504.00$ 14.00$ 504.00$ 55.00$ 1,980.00$ $50.001,800.00$ Z0004562COMBINATION CONCRETE CURB AND GUTTER REMOVAL AND REPLACEMENTFOOT 873.0 35.00$ 30,555.00$ 35.75$ 31,209.75$ 33.00$ 28,809.00$ 34.75$ 30,336.75$ $35.0030,555.00$ TOTAL BASE BID (Items 1 - 28) 624,997.07 643,968.88 660,205.63 739,695.95 727,465.50$ % BELOW/ABOVE ENGINEER'S ESTIMATE-14.09% -11.48% -9.25% 1.68%ENGINEERING ENTERPRISES, INC.52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
()-()-()-
()-()-()-()-(-)()-()-()-
()-()-()-()-()-()-(()-()-(-)()-()-()-
()-()-()-()-()-()-()-)-()-()-()-()-()-()-()-()-()-()-()-()-()-
()-()-()-()-()-()-()-
()-()-()-()-(-)()-()-()-
()-()-()-()-()-()-(()-()-(-)()-()-()-
()-()-()-()-()-()-()-)-()-()-()-()-()-()-()-()-()-()-()-()-()-
()-()-()-()-McHughGame FarmTumaTuma
BruellOakwoodD ickso n BoomerWackerAndersonWellsPrairie
Clo
v
er
Wheat
l
andHaley
H eartlan d
TausChurchHeritage
C
e
n
t
e
r
Alice
MartinBlackber
r
yLandmark Pr
ai
r
i
eMeadowsBridgeBridgeQ u i n s e yPowersMcHughStillwaterK
e
n
d
all
Kendall
ColtonB
l
u
e
j
a
y
Pleasure
OmahaFreemontB lu e s te m
P a r kHayden
MarieSunset
Main
Appletree VictoriaPrairieSumac
Center
KingRiver BristolClearwater
LibertyConcordTowerNaden
Mu l h e r n
Fa
r
ms
t
e
a
dSpring
SpringMistwoodStrawberry Menard
Carpenter
JohnsonB la c k b e rry
WestPalmerQuinseyCrimsonMarketplaceBehrensSandersPark DakotaS o m on au k
Arrowhead
RedwoodConeflower
AuburnBirchwoodC
h
ris
t
y
DaltonConover
Hillcrest
O
liv
e
E Kendal
l
Dr
Jackson
Homestead
S w a n s o n
M idnghtKendall CirMcHughWalnut
WoodworthCannonballSwi
t
chgr
assK e n n e d y
Prairie Pointe
K a teMarketview
Elm Prairie RoseDe
e
r
pa
t
h
Georgeanna
W K e n d a l l D r
Leisure
Countryside
Countryside Wild IndigoPrairieGrassGr
a
c
e
L e x i n g t o n
TeriVeterans V eteran sLegend
2019 RTBR PROGRAM
2019 RTBR PROGRAM (TOWNSHIP).WalshEngineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
PROPOSED 2019 RTBR PROGRAM
LOCATION MAP
www.eeiweb.com
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
JANUARY 2019
YO1842
YO1842_2018 Road Program .MXD
H:\GIS\PUBLIC\YORKVILLE\2018\
MJT
United City of Yorkville
800 Game Farm Road
Yorkville, IL 60560
630-553-4350 ³
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Agenda Item Number
New Business #5
Tracking Number
PW 2019-17
Fox Hill Unit 7 – Easement Abrogation
Public Works Committee – March 19, 2019
Majority
Consideration of Acceptance
Consideration of Easement Abrogation Acceptance
Brad Sanderson Engineering
Name Department
An easement abrogation (vacation) from the drainage and utility easements are needed within the
Fox Hill Unit 7 development. There are two areas where this affects.
A small portion of the building on lot 5 encroaches onto the easement. The City does not have
any utilities in this easement nor should it in the future. Staff supports and recommends
acceptance of the easement abrogation.
Abrogating a small portion of the easement on lot 12 will allow for the owner to construct a short
retaining wall to reduce the slope between lot 12 and the stormwater management facility. The
City does not have any utilities in this easement nor should it in the future. Staff supports and
recommends acceptance of the easement abrogation.
A draft of the easement abrogation is attached.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Kathy Field-Orr, City Attorney
Lisa Pickering, Deputy City Clerk
Date: March 7, 2019
Subject: Fox Hill Unit 7 – Plat of Easement Abrogation
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #6
Tracking Number
PW 2019-18
Discussion of Wyland National Mayors Challenge for Conservation
Public Works Committee - March 19, 2019
N/A
Approval
Majority
Consideration of Support for the Wyland National Mayors Challenge for
Conservation
Erin Willrett Administration
Name Department
Summary
Continue participation in a national program to challenge the residents to conserve water, energy
and other natural resources, in alignment with City Council Goal #6 – Water Planning.
Background
Once again, the Wyland Foundation, in partnership with the National League of Cities and the
U.S. Environmental Protection Agency, invited the United City of Yorkville to participate in the 9th
annual National Mayor’s Challenge for Water Conservation. The commitment from the City to
participate is as simple as drafting the statement of support below. There is no cost to the City. There
were several items that were sent out to market this program in 2018. After the results were tallied, in
2018, Yorkville placed 5th in the 5,000-29,999 population category nation-wide!
Residents who are interested in conservation efforts and who would like to accept the
challenge can go online (www.mywaterpledge.com) and make a pledge to conserve water, energy, and
other natural resources over the next year by selecting from different pledge options. Some options are
as easy as wasting less food and recycling. When the resident enters their location, the drop-down menu
for pledges will contain our draft statement about water conservation. Our draft statement will read as:
“A sustainable water source for the City’s future water supply is a main focus for our community and its
residents. Yorkville currently obtains its water from the deep sandstone aquifer, which is being steadily
drawn down as it is being pumped beyond its long-term sustainable yield due to increasing water
demands and growth of the region. The City is committed to building strong, collaborative relationships
regionally for sustainable water use. We hope to partner with our neighboring communities and our
actual neighbors to promote water conservation efforts in the home. By taking the water pledge, you
can help extend the capacity of the City’s water supply.”
When a resident goes online to accept the challenge, they will search for “Yorkville, IL”, the
website will then walk the resident through the process to pledge to make thoughtful conservation
choices at home. There are several check boxes that the residents can choose from depending on the
changes they are pledging to make. At the end of the “choices” portion of the pledge, an email address
is required and the option for the resident to be entered into the prize drawing is made as a check box.
After the resident enters their email address the pledge process is complete. Additionally, the website
has several informational items for the resident to read through and learn about. City standings in the
challenge are on the website and the residents can check back and see how their “choices” positively
affect the community. This program is designed to get residents to think about how their choices impact
the natural environment and if changes are made, no matter how small, benefits add up quickly. There
is no further commitment and no additional information that is needed from the residents other than
those listed above.
Memorandum
To: Public Works Committee
From: Erin Willrett, Assistant City Administrator
CC: Bart Olson, City Administrator
Date: March 2019
Subject: Wyland National Mayors Challenge for Conservation
The City will also be posting several items on social media and on our website to promote this
challenge. The City’s main goal by promoting this program is to help residents be aware of the
importance of the natural resources that are used on a daily basis and the pressing need to protect those
precious resources.
Recommendation
While not a requirement to participate in the program, staff recommends an acknowledgment by
the City Council in the attached Resolution for support of the statement above and participation in
marketing the program. This initiative aligns with the City Council Goal #6 – Water Planning.
Resolution No. 2019-____
Page 1
Resolution No. 2019-_____
A RESOLUTION OF THE UNITED CITY OF YORKVILLE, ILLINOIS
IN SUPPORT OF THE “WYLAND MAYOR’S CHALLENGE FOR WATER CONSERVATION”
WHEREAS, the United City of Yorkville (the “City”) is a duly organized and validly existing
non home-rule municipality created in accordance with the Constitution of the State of Illinois of 1970
and the laws of the State; and,
WHEREAS, the City continue to explore ways to manage residential consumption of water and
power, and to inspire its residents to care for our natural resources; and
WHEREAS, cities can engage in efforts to inspire their own communities, as well as their
neighboring cities, to become better environmental stewards; and
WHEREAS, the eighth annual National Mayor’s Challenge for Water Conservation presented
by the Wyland Foundation and Toyota, with support from the U.S EPA WaterSense, The Toro
Company, National League of Cities, Conserva Irrigation, and Earth Friendly Products (makers of
ECOS), is a healthy, non-profit competition for cleaner communities and a water use and pollution
reduction competition between our cities; and
WHEREAS, with the encouragement of their Mayors, residents may register their participation
in their city's Challenge, online, by making simple pledges to decrease their water use and to reduce
pollution for the period of one year, thereby assisting their cities to apply State and Federal water
conservation strategies and to target mandated reductions; and
WHEREAS, from April 1- 30, 2019, the City of (X) wishes to inspire its residents and its
neighboring communities to take the "Wyland Mayor's Challenge for Water Conservation" by making a
series of online pledges at mywaterpledge.com to reduce their impact on the environment and to see
immediate savings in their water, trash, and electricity bills;
NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of the United City
of Yorkville, Kendall County, Illinois, as follows:
Section 1: That the City agrees and supports the "Wyland Mayor's Challenge for Water
Conservation" emphasis.
Section 2: That the program is to be implemented from April 1- 30, 2019, through a series of
communication and outreach strategies, whether new or existing, to encourage Yorkville residents to
take the conservation "Challenge."
Section 3: This Resolution shall be in full force and effect upon its passage and approval as
provided by law.
Resolution No. 2019-____
Page 2
Passed by the City Council of the United City of Yorkville, Kendall County, Illinois this
________ day of ____________________, 2019.
__________________________________
City Clerk
CARLO COLOSIMO ________ KEN KOCH ________
JACKIE MILSCHEWSKI ________ ARDEN JOE PLOCHER ________
CHRIS FUNKHOUSER ________ JOEL FRIEDERS ________
SEAVER TARULIS ________ JASON PETERSON ________
Approved by me, as Mayor of the United City of Yorkville, Kendall County, Illinois, this
________ day of ____________________, 2019.
__________________________________
Mayor
United City of Yorkville Press Release, March 1, 2019
CONTACT:
Erin Willrett, Assistant City Administrator
630-553-8574
ewillrett@yorkville.il.us
8th National Mayor’s Challenge for Water Conservation, April 1 – 30
Yorkville joins nationwide challenge to be most “water wise”
Mayor Golinski is joining mayors across the country in asking residents to make a long-term commitment
to manage water resources more wisely by taking part in the annual Wyland National Mayor’s Challenge
for Water Conservation — and in return residents can win $5,000 toward their utility payments, water
saving fixtures, and hundreds of other prizes. Plus, one lucky charity from a winning city will receive a
2019 Toyota Highlander Hybrid to serve the community.
The annual challenge, April 1- 30, is a non-profit national community service campaign to see which
leaders can best inspire their residents to make a series of informative and easy-to-do online pledges at
mywaterpledge.com to use water more efficiently, reduce pollution, and save energy. “This challenge is a
great way for cities large and small to do our part for the planet – and reward our residents for doing the
right thing.” said Mayor Golinski.
Last year, residents from over 3,800 cities in all 50 U.S. states pledged to reduce their annual
consumption of freshwater by 3 billion gallons, reduce waste sent to landfills by 79.9 million pounds, and
prevent more than 177,000 pounds of hazardous waste from entering our watersheds. The challenge
goes beyond recent drought issues and looks at the ways our water use will affect the future of our
communities — from how we grow food to reducing polluted runoff.
To participate, residents enter online at mywaterpledge.com, and then make a series of online pledges to
conserve water on behalf of Yorkville, IL. Cities compete in the following population categories: (5,000-
29,999 residents, 30,000-99,999 residents, 100,000-299,999 residents, 300,000-599,999 residents, and
600,000+ residents). Cities with the highest percentage of residents who take the challenge in their
population category are entered into drawings for hundreds of eco-friendly prizes, including home
improvement gift cards, home irrigation equipment, and the Grand Prize $5,000 home utility bill payment.
The Challenge also gives residents a chance to nominate a deserving charity that would benefit from
receiving a 2019 Toyota Highlander Hybrid and features additional resources for residents to take their
commitment of conservation even further, from regional water and energy resource issues to cost-saving
tips at home.
The 8th National Mayor’s Challenge for Water Conservation is presented by the Wyland Foundation and
Toyota, with support from the U.S EPA WaterSense, The Toro Company, National League of Cities,
Conserva Irrigation, and Earth Friendly Products (makers of ECOS).
About the Wyland Foundation
Founded in 1993 by environmental artist Wyland (best known for his series of 100 monumental marine
life murals), the Wyland Foundation, a 501c3 non-profit organization dedicated to promoting, protecting,
and preserving the world’s ocean, waterways, and marine life. The foundation encourages environmental
awareness through community events, education programs, and public art projects.
www.wylandfoundation.org
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #7
Tracking Number
PW 2019-19
Hanging Baskets
Public Works Committee - March 19, 2019
Positive
Approval
Proposal for hanging baskets in the downtown area.
Eric Dhuse Public Works
Name Department
Summary
Discussion of possible locations for hanging flower baskets in the downtown area. This
would be the rebirth of this project on a small scale. If the project goes well, we can expand it to
include more area.
Background
Years ago, the city partnered with the garden club to place hanging flower baskets
throughout the downtown and in town square park. In this program, businesses or individuals
were able to sponsor a basket for X dollars and have it placed near their business or in the park.
The project was successful for a few years but was severely hampered by the recession and the
construction on Rt. 47. Since that time, the sidewalk downtown on Rt. 47 has been rebuilt, but at
a much narrower width. This new width will not allow hanging baskets to be placed in front of
the businesses without interfering with pedestrians. Instead, I would propose that we place most
of the baskets along Van Emmon St. and mount them directly onto buildings. To do this, we will
need the permission of the owners, and agree on placement. If the owners are agreeable, I think
this will be a viable option to restart this program. I have attached a map with potential locations
for your review. The cost for the 8 baskets and brackets is approximately $1625-$1785
depending on the price of the flowers. A complete breakdown is below:
Building Mount - $97.00 Lamp Post Bracket - $90.00
Hanging Basket 18” - $40.00 Hanging Basket 18” - $40.00
Basket Liner - $17.00 Basket Liner - $17.00
Flowers - $50-$70 Flowers - $50-$70
Total $204 – 224 Total $197 – 217
I have also attached pictures of the basket, liner, and the different mounting brackets for
your review and comment. There are some other choices, but these were made for municipal use
and can take the weight of large baskets. In addition, these baskets are not too trendy, they are
very subtle which let the flowers stand out. For the flowers I have been in contact with Winding
Creek Nursery. They have assured me that if we got them the baskets soon, they would be able
to get them ready to go for the season. I had suggested red, wave petunias for the flower. I
chose them for their tolerance to different conditions, their rapid growth, and red for Yorkville. I
also chose this variety knowing that the nursery has many flats of this type of flower started
already in their greenhouse. If this program is a success and we would like to continue it next
year, we can always change the flower color, variety or even an entirely different set of plants if
we are so inclined.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, Administrator
Date: March 13, 2019
Subject: Hanging baskets
Recommendation
I recommend that this be placed on the March 19, 2019 Public Works Committee for
discussion and direction for staff.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #8
Tracking Number
PW 2019-20
Utility Box Art
Public Works Committee – March 19, 2019
A discussion will take place at the meeting.
Bart Olson Administration
Name Department
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #9
Tracking Number
PW 2019-21
Speed Sign Update
Public Works Committee – March 19, 2019
A verbal update will be given at the meeting.
Bart Olson Administration
Name Department
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Human Resources
Community Development
Police
Public Works
Parks and Recreation
Agenda Item Number
Old Business #1
Tracking Number
PW 2018-102
East Alley and Van Emmon
Public Works Committee – March 19, 2019
Please see attached.
Brad Sanderson Engineering
Name Department
As directed by the Committee, we have provided greater detail as to the anticipated costs for the
preferred improvement option. Please refer to the attached preliminary cost estimate and
exhibits. The costs also include additional striping on Van Emmon to block out the exit only
driveway.
As to the timing of the improvements, we would recommend utilizing the RTBR contractor to
perform the work. That work is anticipated be in the May to mid-July timeframe. The work
specific to this improvement should be completed with 2-3 weeks.
We would propose to “design in the field” and would estimate our construction engineering fees
to be in the $2,000 range.
If you have any questions or require additional information, please let us know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Lisa Pickering, Deputy City Clerk
Date: March 12, 2019
Subject: East Alley