Resolution 2019-12 Resolution No. 2019-12
A RESOLUTION OF THE UNITED CITY OF YORKVILLE,KENDALL COUNTY,
ILLINOIS,APPROVING SETTLEMENT AGREEMENT RELATING TO THE
COMPLETION OF PUBLIC IMPROVEMENTS FOR THE BLACKBERRY WOODS
SUBDIVISION
WHEREAS, the United City of Yorkville, Kendall County, Illinois (the "City") is a duly
organized and validly existing non home-rule municipality created in accordance with the
Constitution of the State of Illinois of 1970 and the laws of the State; and,
WHEREAS, Meadowbrook Builders, LLC, an Illinois limited liability company (the
"Developer") is constructing a residential subdivision known as the Blackberry Woods
Subdivision; and,
WHEREAS,pursuant to the Subdivision Control Ordinance of the City, First Community
Bank,now known as Busey Bank, issued letters of credit#159 and#222 (the "Letters of Credit")
securing the completion of the Blackberry Woods Subdivision; and,
WHEREAS, a dispute between the City and Developer has arisen as a result of the City
calling the Letters of Credit due to the Developer's failure to complete certain items as required
by its Subdivision Control Ordinance (the"Dispute"); and,
WHEREAS,the Developer and City have negotiated the terms of a settlement agreement
which provides for the release of letter of credit#159 and the replacement of letter of credit#222
with a new letter of credit to secure the completion by the Developer of the items as set forth in
the settlement agreement(the"Settlement Agreement"); and,
WHEREAS, the Mayor and City Council of the City believe it to be in the best interests
of the City and its residents to settle the Dispute in accordance with the terms of the Settlement
Resolution No.2019-12
Page 1
Agreement;thereby eliminating costs to be incurred in litigating the Dispute and providing for the
completion of the Blackberry Woods Subdivision as originally contemplated.
NOW,THEREFORE,BE IT RESOLVED,by the Mayor and City Council of the United
City of Yorkville, Kendall County, Illinois, as follows:
Section 1. That the Settlement Agreement by and between the City and Developer,
attached hereto and made a part hereof, is hereby approved and the Mayor, City Clerk, and City
Administrator are hereby authorized to executed and deliver said Settlement Agreement and
undertake any and all actions as may be required to implement its terms on behalf of the City.
Section 2. That this Resolution shall be in full force and effect from and after its passage
and approval as provided by law.
Passed by the City Council of the United City of Yorkville, Kendall County, Illinois,
this 26d'day of March,A.D. 2019.
'bET>VTy CITY CLERK
CARLO COLOSIMO Absent KEN KOCH Absent
JACKIE MILSCHEWSKI Ave ARDEN JOE PLOCHER Ave
CHRIS FUNKHOUSER Ave JOEL FRIEDERS Ave
BEAVER TARULIS Aye JASON PETERSON Absent
APPROVED by me, as Mayor of the United City of Yorkville, Kendall County, Illinois,
this 0 day of I L , A.D. 2019.
M Yft//
Resolution No.2019-12
Page 2
Attest:
U4a
E:PU7'y CITY CLERK
Resolution No.2019-12
Page 3
STATE OF ILLINOIS )
COUNTY OF KENDALL )
Revised February 26, 2019(2)
Final Draft
BLACKBERRY WOODS LETTER OF CREDIT PUBLIC WORK IMPROVEMENT AND
SETTLEMENT AGREEMENT
NOW COMES MEADOWBOOK BUILDERS, LLC AN ILLINOIS LIMITED
LIABILITY COMPANY and in agreement with the UNTIED CITY OF YORKVILLE to provide
completion of Public Improvements for Blackberry Woods Subdivision, and further to settle all
matters in dispute between the parties and provide security for completion of said Public
Improvements agree as follows:
I. MEADOWBROOK BUILDERS, LLC hereby agrees to complete all Public
Improvements and final inspections by City Engineers on or before June 1, 2019.
IL Letters of Credit: The parties hereto acknowledge and agree that there are two
outstanding Letters of Credit issued originally by First Community Bank N.K.A
Busey Bank as follows:
a. Letter of Credit#159: Attached hereto and incorporated herein by
reference is a letter dated January 10, 2019 referencing two repair items
that need to be completed by MEADOWBROOK BUILDERS, LLC and
upon completion of such were the last items to be resolved under Letter of
Credit 159.
The parties hereto agree that the UNITED CITY OF YORKVILLE will
furnish a Release letter to Busey Bank releasing all of Letter of Credit
#159.
b. Letter of Credit#222: Attached hereto and incorporated herein by
reference is a copy of a letter dated January 10, 2019 from Engineering
Enterprises in regard to Letter of Credit#222.
Meadowbrook Builders LLC and the UNITED CITY OF YORKVILLE
1
agree that MEADOWBROOK BUILDERS, LLC shall cause a new Letter
of Credit to be issued with a one year fixed date from date of issuance by
Busey Bank in favor of the UNITED CITY OF YORKVILLE in the sum
of$164,500.00 which shall secure completion of the remaining items of
Public Improvements needed to be completed by MEADOWBROOK
BUILDERS, LLC by June 1,2019 plus a one year retention period as to a
10% balance of that Letter of Credit for a one year period of time from
Public Improvement acceptance.
III. Completion of Public Improvement Items or Accounting for Public Improvements
completed pursuant to Letter of Credit#22 and the attached January 10, 2019
Engineering Enterprises Letter:
General
1. Minor street additions are being added to the"AS-BUILT" drawings
previously submitted to the City. The final version shall be submitted to
Engineering Enterprises for review by Meadowbrook Builder, LLC on or
before February 15, 2019.
2. All construction debris has been removed on a continuing basis by
MEADOWBROOK BUILDERS, LLC. They will continue to periodically
inspect the site as homes under construction occasionally have packaging and
other debris blowing out of dumpsters which are located at each house
construction site for proper disposal of debris. There are no construction
items of Developer remaining unpicked up anywhere within the Development.
Stormwater
3. It is believed that all sediment was removed form the stormwater
management facility. This matter not having shown up prior to the November
19, 2018 Punchlist did not permit that planting of the materials called for in
the landscape plan for the Subdivision. It is anticipated that seeding will take
place in Mid-April 2019 or at the latest prior to the overall completion date.
Storm Sewer
4. Items 4,5 ,and 6 are already completed.
7. Will be completed by June 1, 2019.
8. The parties are reviewing the televised drawings and working out a
solution to the repairs on the them. It is anticipated that Aladdin Nasar the
Principal of Meadowbrook Builders LLC and Bradley P. Sanderson the
supervising Engineering Enterprises Engineer will have an agreement in place
exactly as to what repairs will be need and how they will be performed by
March 12, 2019 and repair items completed by June 1, 2019.
2
Roadway
9. & 10. As weather permits the new damaged area of concrete curb and
gutter will be repaired before the overall repair expiration date. Given that we
are in a very severe winter season it is probable that there will be more street
patching and curb repairs either due to snow plow damage or construction on
the last few remaining lots which again will be accomplished we believe by
April 1, 2019 and ready for inspection.
11. Completion of the remaining public sidewalks will be by the June 1, 2019
date although it is anticipated by the parties that the repairs can be completed
earlier in the spring as long as there is dry weather.
12. Thorn Electric has been contracted to do the job they have the fixture
heads and wiring in their possession,they have ordered the light poles that are
in conformity to City Ordinance. It does take a bit of time to get the poles but
as soon as Thorn those they will install the light poles and do the burn
inspection called for item 13.
14. Back filling was done as requested by the UNITED CITY OF
YORKVILLE previously seeding will take place when the detention pond
seeding happens in early spring.
15. Completion of the remaining public sidewalks will be by the June 1, 2019
date although it is anticipated by the parties that the repairs can be completed
earlier in the spring as long as there is dry weather.
16. And 17. Meadowbrook Builders is waiting for confirmation on unusual
sign design and will install as soon as available from the City.
18. Parkway trees that need to be finished have been being installed on a lot by
lot basis with each building permit. There are currently some homes finished
that were set for occupancy during winter months that would not permit
planting of parkway trees and there is individual bonds in place for each of
those situations again there is a small number of lots that the Developer still
has to put the trees in without homes which will be done by the overall June 1,
2019 date.
We respectfully submit this written agreement to resolve all matters. We are requesting Busey
Bank to issue the new Letter of Credit; the hope of both the City Attorney and myself is that they
will issue a totally new Letter of Credit rather than jus reduce the existing Letter of Credit#222.
As soon as we hear back form the Bank we will advise the City Attorney of the methodology to
be used in that fashion.
Respectfully Submitted by:
3
Daniel J. Kramer,
Attorney at Law
This agreement is approved by:
MEADOWBROOK B ILDERS, LLC UNITED CIT YORKVILLE
0,04t
iirleasd, Nfanager Authorized Representative
Date: Date: 0
4
YEARS
Engineering Enterprises,Inc.
January 10, 2019
Ms. Krysti Barksdale-Noble
Community Development Director
United City of Yorkville
800 Game Farm Road
Yorkville, IL 60560
Re: Blackberry Woods(Phase B)-LOC No. 159
United City of Yorkville
Kendall County, Illinois
Krysti:
A representative from Engineering Enterprises, Inc. performed an onsite punch list inspection for the above
referenced project and noted the following:
Sanitary Sewer
1. The following structure has an incorrect lid and should be replaced with a lid reading "City of Yorkville -
Sanitary"with concealed pick holes: S-6.
Water Main
2. The following structure has an incorrect lid and should be replaced with a lid reading "City of Yorkville -
Water"with concealed pick holes: VV-9.
The contractor shall contact us once the items have been completed for a re-inspection. If you have any
questions or require any additional information, please contact our office.
Very truly yours,
ENGINEERING ENTERPRISES, INC.
�BradleY P. Sanderson, P.E.
Vice President
BPS/nls
PC: Mr. Bart Olson, City Administrator(Via e-mail)
Ms. Erin Willrett, Assistant City Administrator(Via e-mail)
Mr. Eric Dhuse, Director of Public Works(Via e-mail)
Ms. Lisa Pickering, Deputy Clerk(Via e-mail)
Ms. Kathy Field-Orr, City Attorney(Via e-mail)
Mr. Aladdin Nassar, Meadowbrook Builders (Via e-mail)
JAM, NLS- EEI (Via e-mail)
YEARS
Engineering Enterprises,Inc.
January 10, 2019
Ms. Krysti Barksdale-Noble
Community Development Director
United City of Yorkville
800 Game Farm Road
Yorkville, IL 60560
Re: Blackberry Woods(Phase B)- LOC No. 222
United City of Yorkville
Kendall County, Illinois
Krysti:
A representative from Engineering Enterprises, Inc. performed an onsite punch list inspection for the
above referenced project and noted the following:
General
1. Updated record drawings reflecting the new roadway and curb should be submitted for review.
I
2. All construction debris should be removed from the site.
Storm Water Martacomerd Facility
3. Appropriate vegetation and seeding should be planted around the southwest detention basin in
the areas where excessive sediment was removed.
Storm Sewer
4. The following structures have debris and should be cleaned: MH 117, INL 125, INL 132 and INL
140.
5. The following structure has a broken frame and should be replaced along with a new lid: MH 129.
6. The following structure has an offset frame and rings and should be reset: INL 96
7. Sump pump line for Lot 121 should be connected to structure MH 113 and the connection
mortared.
8. We have reviewed the televising video of the existing storm and sanitary sewer dated February
2017 as prepared by Cam-Vac. The following comments should be addressed and repaired.
• Pipe segment 113 to 112 has two misaligned storm sump taps located 57.4' and 56.1' from the
upstream manhole.
52�%Iheeler Road, Sugar Grove, IL 60554 - 1 1 •
Ms. Krysti Barksdale-Noble
January 10, 2019
Page 2
• Pipe segment 113 to 112 the pipe is cracked at two joints located 39.0' and 95.5' from the
upstream manhole.
• Pipe segment 139 to 136 has a misaligned storm sump tap located 47.8' from the upstream
manhole.
• Pipe segment 139 to 136 the pipe is cracked at the joint located 117.7' from the upstream
manhole.
• Pipe segment 98 to 94 the pipe is cracked at the joint located 78.8' from the upstream
manhole.
• Pipe segment 103 to 102 the pipe has cracking throughout the pipe located 41.4', 58.6', 66.2',
83.1' and 152.6' from the upstream manhole.
Pipe segment 125 to 106 has debris in the storm sump tap located 59.3' from the upstream
manhole.
• Pipe segment 142 to 141 the pipe is cracked at the joint located 154.7' from the upstream
manhole.
• Pipe segment 97 to 96 has wall shadowing of the reinforcement bars located 37.6' from the
upstream manhole.
• Pipe segment 117 to 111 the pipe is cracked at two joints located 92.7' and 108.6' from the
upstream manhole.
• Pipe segment 119 to 118 has wall shadowing of the reinforcement bars located 57.7' from the
upstream manhole.
• Pipe segment 126 to 105 has debris in the storm sump tap located 41.7' from the upstream
manhole.
• Pipe segment 127 to 126 the pipe is cracked at the joint located 13.3' from the upstream
manhole.
• Pipe segment 152 to 127 has wall shadowing of the reinforcement bars located 18.1' from the
upstream manhole.
The developer should contact our office to review the methods of repair prior to completing the
work.
Roadway
The developer should contact our office to review the methods of repair prior to
completing items 9-11.
9. There are several locations where the concrete curb and gutter has been damaged and should be
repaired.
10. There are several locations where the HMA surface has been damaged and should be repaired.
11. There are several locations where the concrete sidewalk has been damaged and should be
repaired.
12. Street lights should be installed through the Unit per plan.
Ms. Krysti Barksdale-Noble
January 10, 2019
Page 3
13. A 48 hour burn test of the street lights should be completed prior to acceptance.
14. The sidewalk at Carly Drive and Purcell Street should be backfilled with topsoil and topped with
seed, fertilizer and hydraulic mulch.
15. Sidewalk should be completed for all undeveloped lots throughout the Unit per plan.
16. Install Future Roadway Connection sign at the west dead end of Purcell Drive.
17. Install End of Roadway Reflectorized Red signs at the west dead end of Purcell Drive.
Landwming
18. Parkway trees in front of undeveloped lots should be installed at 50-foot intervals per the
landscape plan.
The contractor shall contact us once the items have been completed for a re-inspection. If you have
any questions or require any additional information, please contact our office.
Very truly yours,
ENGINEERING ENTERPRISES, INC.
radley P. 5nderson, P.E.
Vice President
BPS/nls
PC: Mr. Bart Olson, City Administrator(Via e-mail)
Ms. Erin Willrett, Assistant City Administrator(Via e-mail)
Mr. Eric Dhuse, Director of Public Works (Via e-mail)
Ms. Lisa Pickering, Deputy Clerk (Via e-mail)
Ms. Kathy Field-Orr, City Attorney (Via e-mail)
Mr. Aladdin Nassar, Meadowbrook Builders (Via e-mail)
JAM, NLS - EEI (Via e-mail)
\\Milkyway\EEI Storage\Docs\Public\Yorkville\2016\Y01627-DG Blackberry Woods-Phase B\Docs\Punchlist 05—LOC 222.doc
Engineering Enterprises, Inc.
Punchlist05 LOC222
DAMAGED HMA PAVEMENT
A �
t
DAMAGED . PAVEMENT AND
x
CONCRETE
52 Wheeler Road,Sugar Grove,IL 60554— (630)466-6700 tel— (630)466-6701 fax—www.eeiweb.com
Engineering Enterprises,Inc.
PunchfistOS_LUt222
DAMAGED HMA PAVEMENT AND
p. CONCRETE
At
n
,q
DAMHMA PAVEMENT AND
AGED
CONCRETE
52 Wheeler Road,Sugar Grove, IL 60554— (630)466-6700 tel —(630)466-6701 fax—www.eeiweb.com
Engineering Enterprises, Inc,
Punchlist05 LOC222
77
DAMAGED HMA PAVEMENT
won=
BMs
.. " y (�.. DAMAGED HMA PAVEMENT AND
CONCRETE CURB
av
52 Wheeler Road,Sugar Grove,IL 60554- (630)466-6700 tel - (630) 466-6701 fax-www.eeiweb.com
Engineering Enterprises,Inc.
PunchlistOS LOC222
+ _. .
ca
DAMAGED HMA PAVEMENT
Ik—
DRIVEWAY TO BE REPLACED
�•i
$ s;f
52 Wheeler Road, Sugar Grove, IL 60554 – (630) 466-6700 tel – (630} 466-6701 fax –www.eeiweb.com
Engineering Enterprises,Inc.
Punchlist05 LOC222
SIDEWALK TO BE BACKFILLED AND
.� a
m� RESTORED
r
AREA TO BE • D TO BETTER
CONDITIONS
52 Wheeler Road, Sugar Grove, IL 60554- (630)466-6700 tel - (630)466-6701 fax -www.eeiweb.com
Engineering Enterprises, Inc.
PunchIM05 JOC222
151
AREA
a�
y. • BE RESTORED • BETTER
CONDITIONS
f
INL 140
• BE CLEANED •
�t
a
a.
l�x
Y`$
52 Wheeler Road,Sugar Grove, IL 60554— (630)466-6700 tel (630) 466-6701 fax —www.eeiweb.com
Engineering Enterprises,Inc.
Punchlist05 1OC222
r ,
j
BROKEN -AON D
4SHOULD
NEW LIDax-' »
r
„
„6 a
v
h ..
BE RESET AT MH
4 sn OFFSET FRAME TO
96
A
tp -.
52 Wheeler Road,Sugar Grove, IL 60554— (630)466-6700 tel — (630)466-6701 fax — www.eeiweb.com