Resolution 2023-09Resolution No. 2023-09 A RESOLUTION APPROVING CHANGE ORDERS RELATING TO 651 PRAIRIE POINTE DRIVE, YORKVILLE, ILLINOIS (Eleventh Set of Change Orders) WHEREAS, the United City of Yorkville, Kendall County, Illinois (the "City") is a duly organized and validly existing non -home rule municipality created in accordance with the Constitution of the State of Illinois of 1970 and the laws of the State; and, WHEREAS, the City has acquired the building and property commonly known as 651 Prairie Pointe Drive (the "New City Hall") for the purpose of rehabilitating the building and repurposing it as the new Yorkville City Hall and the headquarters of the Yorkville Police Department (the "Project"); and, WHEREAS, the City issued a Request for Proposals to construct the Project and after review and evaluation of submittals from several firms, the City entered into a contract with Lite Construction of Montgomery, Illinois (the "Contract"); and, WHEREAS, the Contract, as approved by the City with Lite Construction, provided a line item for unforeseen contingencies due to the fact that the New City Hall was constructed in 2007 and change orders were guaranteed to come as demolition of existing walls and ceilings occurred; and, WHEREAS, Lite Construction has submitted five (5) change orders to the original Contract, as itemized on the list attached hereto, modifications to the original work design as mandated to conform to current code standards resulting in an additional costs totaling $12,607; and, WHEREAS, the City has reviewed the change orders as submitted by Lite Construction and acknowledges that the work covered by these change orders was unforeseen but is necessary Resolution No. 2023-09 Page 1 and in the best interest of the City; therefore, the City is prepared to approve the Change Order as hereinafter provided. NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of the United City of Yorkville, Kendall County, Illinois, as follows: 1. Section 1. The foregoing preambles are hereby adopted as if fully restated in this Section Section 2. That the change orders as itemized on the list attached hereto as submitted by Lite Construction resulting in total additional costs of $12,607 are hereby approved. Section 3. That this Resolution shall be in full force and effect upon its passage and approval as provided by law. Passed by the City Council of the United City of Yorkville, Kendall County, Illinois this 11 to day of April, A.D. 2023. CI CLERK KEN KOCH AYE DAN TRANSIER AYE ARDEN JOE PLOCHER AYE CRAIG SOLING AYE CHRIS FUNKHOUSER AYE MATT MAREK AYE SEAVER TARULIS AYE RUSTY CORNEILS AYE APPROVED by me, as Mayor of the United City of Yorkville, Kendall County, Illinois this �'--' day of A'I�� I , A.D. 2023. MAYOR - Attest: Resolution No. 2023-09 Page 2 LITE CONSTRUCTION 711 South Lake Street P.O. Box 135 MONTGOMERY, IL 60535 (630) 896-7220 Fax (630) 896-1304 TO Cordogan Clark & Associates 960..Ridgeway....Ave ...._ .................... Aurora, IL, 60506 ....._..... .................. ..... ..... _.........._......:.__.................__...... _. ......._....................................................................................... _..... _........ _.... _... _.... _........ _. We hereby agree to make the change(s) specified below: ................... ................................................................ PR 40 Fire Strobe =1--=J . "l 49R 1 Number PHONE DAY 24 23 JOBN 1 OI INO City Hall Police Facility 21-364 JOB NUMBER JOB PHONE EXISTING CONTRACT NO. DATE OF EYISTING CONTRACT ...... ....... ........__........... _..._................_........................_ I .._.._..................................................... ................................_............................................... NOTE: This Change Order becomes part of and in conformance with the existing contract. ar2�f� AI I- KEE hereby to make the change(s) specified above at this price b $ DATE PREVIOUS CONTRACT AMOUNT $ —IV J AUTHORIZED SIGNATURE (CONY OR) REVISED CONTRACT TOTAL $ ACCEPT ED — The above prices and specifications of this Change Order are satisfactory and are hereby Date of acceptance accepted. All wort: to be performed under same terms and conditions as specified in original contract unless Signature otherwise stipulated. rowNeal PROPOSED CHANGE ORDER Valley Electrical Contractors CCN # 10179-37 Po Box 461 CCN Date 1/3012023 Oswego, IL 60543 Date: 3/24/2023 Telephone: 630-554-6200 Project Name: Yorkville City Hall and Police Station Fax: 630-554-5543 Project Number: 10179 Page Number: 1 Client Address: Lite Construction Contact: Tim Campbell 711 S.Lake St Montgomery, IL 60538 Telephone: 630-896-7220 Contact: Tim Campbell Work Description We reserve the right to correct this quote for errors and omissions. This Change Order is for the new exterior strobe per PR 040. To include: Coring into the wall for conduit Weatherproof horn/strobe 15/75cd, Red Weatherproof box, Cast, Red Control Module Required LV Cable for install Itemized Breakdown Description Qty VALLEY ELECTRICIAN 1 Totals 1 Summary JOURNEYMAN (2.00 Hrs @ $137.00) 274.00 New Exterior Strobe ($2,178.00 + 0.000 % + 0.000 % + 10.000 %) 2,395.80 Subtotal 2,669.80 Final Adjustment -0.80 Final Amount $2,669.00 ORIGINAL LITE CONSTRUCTION 711 South Lake Street P.O. Box 135 MONTGOMERY, IL 60535 (630) 896-7220 Fax (630) 896-1304 TO Cordogan Clark & Associates 960...Ridgeway..Ave _ .......... Aurora, EL 60506 ........................................................................................................................................... ............................................................................................................................................ k 50 Number PHONE DA JOB N 1 Ori°cVI le City Hall Police Facility 21-3 64 JOB NUMBER JOB PHONE EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT .................................... $50.00 .............................................................................._.._.... MOTE: This Change Order becomes part of and in conformance with the existing contract C'i91:i-E AIG uEE hereby to make i:he s) specified above at this price b DATE PREVIOUS CONTRACT AMOUNT AUTHORIZED SIGNAT ,ON RACTOR) REVISED CONTRACT TOTAL $ ACCEPTED — The above prices and specifications of t±3 a�j this Change Order are satisfactory and are hereby Date of acceptance _ accepted. All work to be performed under same terms and conditions as specified in original contract unless Signature otherwise stipulated. (OWNER) Document G709- - 2018 Proposal Request PROJECT: (name and address) City Hall & Police Facility Renovation 651 Prairie Point Dr. Yorkville, IL OWNER: (name and address) United City of Yorkville 800 Game Farm Rd. Yorkville, IL CONTRACT INFORMATION: Contract For: General Construction Date: March 8, 2022 ARCHITECT: (name and address) Cordogan Clark & Associates 960 Ridgeway Ave. Aurora, IL Architect's Prgject Number: 21-364 Proposal Request Number: 041 Proposal Request Date: 03/08/2023 CONTRACTOR: (name and address) Lite Construction, Inc. 711 S. Lake St. Montgomery, IL The Owner requests an itemized proposal for changes to the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. The Contractor shall submit this proposal within Five (5) days or notify the Architect in writing of the anticipated date of submission. (Insert a detailed description of the proposed modifications to the Contract Documents and, if applicable, attach or reference specific exhibits) In Evidence Processing Lab 120 and Bag & Tag 124, provide a 3-way control wall switch with indicator light connected to exhaust fan EF-1-2 for each of the two exhaust arms. The control switches are intended to operate the exhaust fan individually or simultaneously while the exhaust arms are in use. Final location of wall switches to be verified in field by owner. Refer to attached sketch ASK-001 for preliminary locations. Include all wiring and conduit as required for complete operating system and provide standard device labeling on control switches. THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. REQUESTED BY THE ARCHITECT: Lauren Kiley Architectural Designer PRINTED NAME AND TITLE AIA Document G709 — 2018. Copyright O 1993, 2001 and 2018. All rights reserved. "The American Institute of Architects," "American Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 12:25:18 CT on 03/08/2023 under Order No.3104237387 which expires on 09/10/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documente Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (389ADA53) PROPOSED CHANGE ORDER Valley Electrical Contractors CCN # 10179-41 Po Box 461 CCN Date 3/15/2023 Oswego, IL 60543 Date: 3/15/2023 Telephone: 630-554-6200 Project Name: Yorkville City Hall and Police Station Fax: 630-554-5543 Project Number: 10179 Page Number: 1 Client Address: Lite Construction Contact: Tim Campbell 711 S. Lake St Montgomery, IL 60538 Telephone: 630-896-7220 Contact: Tim Campbell Work Description We reserve the right to correct this quote for errors and omissions. This change order is for the additional 2 light switches requested in PR041. Itemized Breakdown Description Qty 1/2" EMT 20 1/2" EMT DC SS CONN 2 1/2" EMT DC SS CPLG 2 1/2" EMT 1-H STEEL STRAP 3 #12 THHN 68 41-1/2" SQ BOX COMB KO 1 4" SQ 1G PL-RING 1/2" RISE 1 20A 120-277V S/P SW (SG) 1 I S/S SWITCH PLATE 1 #10x1" S-TAP SCREW P/H 5 Totals 104 Summary General Materials 33.27 Material Overhead (@ 10.000 %) 3.33 Material Markup (@ 5.000 %) 1.83 Material Total 38.43 JOURNEYMAN (2.22 Hrs @ $137.00) 304.14 PROJECT MANAGER (1.00 Hrs @ $155,00) 155.00 Final Adjustment -0.57 Final Amount $497.00 ORIGINAL LITE CONSTRUCTION 711 South Lake Street P.O. Box 135 MONTGOMERY, IL 60538 (630) 896-7220 Fax (630) 896-1304 TO Cordogan Clark & Associates .......... ....960...Ridgeway...Ave._ ............_ ............... Aurora, IL 60506 We hereby agree to make the change(s) specified below: ......................................................................_._....._........._._..........__.... . PR 42 Evidence lab 120 exhaust connection di.p ..... ... ....... . LCI Mark up Total....................._...__............................ _. _ _ ._$870.00 ... _...... _ . . $87.00 _$957.00.. _ .. 51 Number NOTE: This Change Order becomes part of and in conformance with the existing contract. Wra- AuGHEE7 hereby to make the changes) peci;ied above at this price DATE - t PREVIOUS CONTRACT AMOUNT AUTHORIZED SIGNATURE (CONTRACTt)i L4", V V REVISED CONTRACT TOTAL $ i ACCEPTG0 — The above rices and specific ati its of Date of acceptance 13 a3 this Change Order are satisfactory and are hereby accepted. All wort: to be performed under same terms and conditions as specified in original contract unless Signature otherwise stipulated. �own,er�i AIA Document G709_ - 2018 Proposal Request PROJECT: (name and address) CONTRACT INFORMATION: Architect's Project Number: 21-364 City Hall & Police Facility Renovation Contract For: General Construction Proposal Request Number: 042 651 Prairie Point Dr. Yorkville, IL Date: March 8. 2022 Proposal Request Date: 03/10/2023 OWNER: (name and address) ARCHITECT: (mune and address) CONTRACTOR: (name and address) United City of Yorkville Cordogan Clark & Associates Lite Construction. Inc. 800 Game Farm Rd. Yorkville. 11, 960 Ridgeway Ave. Aurora, IL 711 S. Lake St. Montgomery, IL The Owner requests an itemized proposal for changes to the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. The Contractor shall submit this proposal within Five (5) days or notify the Architect in writing of the anticipated date of submission. (insert a detailed description of the proposed modifications to the Contract Documents and,, if applicable, attach or• reference specific exhibits.) In Evidence Processing Lab 120. provide exhaust connection from owner provided Fuming Chamber Cabinet to exhaust air duct for EF-1-2. For the connection at the Fuming Chamber Cabinet, increase from 1.5" PVC to 2" at the outlet. Route the 2" PVC to the 4" E/A duct and connect to side of duct at 45 degrees. Duct connection to be sealed in compliance with standard mechanical specifications. Verify installation and operation controls in field with current conditions. The cut sheet for Fuming Chamber Cabinet is attached for reference. Modify acoustical ceiling the as required for pipe run. Any cutting to be clean and held tight to pipe. Contingent on approval of PR41 to add the wall switch control- provide label to indicate control is for Fuming Chamber Cabinet and/or Exhaust Arm. confirm terminology with owner prior to finalizing. THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. REQUESTED BY THE ARCHITECT: Lauren Kiley Architectural Designer PRINTED NAME AND TITLE AIA Document G709 — 2018. Copyright 01993, 2001 and 2018. All rights reserved.' The American Institute of Architects," 'American Institute of Architects,' "AIA; the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 12:3BAS CT on 03/16/2023 under Order No.3104237387 which expires on 09/10/2023. is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents-", Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. User Notes: (3B9ADA50) M(K�ffl MANUFACTURING Counter Top Unit Item Number Capacity Exhaust Volume Exhaust Outlet Diameter 56F0030W 13 Cubic Feet 14 CFM 1.5" I.D. QUALITY BY DESIGN CU. FT. 8.31 CU. FT. 2.25 CU. FT. I , 15 3/4" 71 rt 'FT CU. . C t I 19.93 CU, FT 4� } t 693 { CU. FT. I P61 0 ARTLII' and SONS, Inc. 230 South Broa(lway � aurora, Illinois 60505 (630)896-IS60 ��' Fax (630) 896-1198 ,�'wrce 7,969 �n�r�ur.artlipandsons.com .Cr9'N: Dawn Kantorski and/or Tim PROPOSAL, 5013M IT I' - D TO Lite Construction i71'Rlil:•I' CITY. S'IA'ITr AND 711'CODE FTIONP. PROPOSAL SPECIFICATIONS AND ESTIMATE NO 1;- 28267-1 PAGE. NO. 1 01: 1 PACES rAx IDAre 1 03/13/23 for, NIXIME PR 042 - Ventilation of Mott Forensic Cabinet _ JOB LOC:\fYtN Citv of Yorkville Pro'cct We hereby propose to furnish materials rend Tabor necessary for the completion of: We will provide and install exhaust ducting from the 1-1/,' exhaust duct for EF-1-2. Labor $760.00 Materials $110.00 Total $870.00 WE PROPOSE hercbv to furnish material and labor --- cnngilctc ill accordance with the atxrvc specifications. for lice sum of - Eight -Hundred Seventy and 00/100----------- —------------------------------------- ------------------------ — - - _ I'an'ment tc be utade as lbllotvs: N/30 dollars 6 870.00 1. Ant• amount doe under this agreement which is not paid whert due shrill bear interest of the rate of I-1 '2 percent per month f•om the date such muounf Ncus due until paid npotl nceeplancc of this proposal. In ilia case ot'deftult i❑ meeting anwunt due upon acceptance of Iltis proposal. terms of pa}'ntent. onrner agr ecs to pm nil costs and rensunnhic auorncn's li if action is brought to collect the All matet'ial is euaranlced to Ix as specified. All tvork to be completed in a substantial Atithorized workmanlike manner according to the spccilicatirntssubmitted- per slattdard practices. Sirilature Ann' alteration or doviatiun from above sliccilicalimis involving extra costs will be executed Hank Artllp only upon ts•riticu orders. and will hecome tilt cxun charge Derr and above the estimate. All aerccmcttls contingent ulloo strikes. accidents or deli}'8 bcyond our control. Owner to carry Nnte This prnlxisal 111:11. be fire. tornado and other necessary insurnoce. Onr nrnrkers are lidhv covered by Wm-knmtix %, ifhdnnn b% its Wool accepted within NO Compensation Insurance. :\C:Cti!''f:\\CIS OT I'It01'05:11, 'fhe above prices. slucil anoll and conditinns are satistactory and are hereby accc pled. You arc authorized to do the nork as specified. Payment kill be made as omlincd abmyc. _-- Signuurre-- Sicuatura -..-_ n ART'LIP and SONS, Inc. 230 South Broadway Aurora, Illinois 60505 (630) 896-1560 Fax (630) 896-1198 f ,$uzce 1 y6�i www.artltpandsons.conl At I N Ud fn KantorSW ano. I'ROI'OSAL SUf3)rtl'(-fL'D'1'O Lite Construction STI(liP: l' --- CITY. STAfE. AND 7.IP CODE rU(CI I rrI-.C'17ENGINEER PHONE. PROPOSAL SPECIFICATIONS AND ESTUNrE PAGI? NO. 1 OF 1 I)AGGS FAX JOB NAME PR 042 - Ventilation of Mott Forensic Cabinet JOB LOCA110N _ City of Yorkville Project DAIT 03/13/23 1011 PHONE We will provide and install exhaust ducting from the 1-1/2" PVC connection at the top of the Mott Forensic Cabinet to the existing exhaust duct for EF-1-2. Labor $760.00 Materials $110.00 Total $870.00 AYE PROPOSE hereby to furnish material and labor — complete in accordance With Via above specifications, for the suns of: Eight -Hundred Seventy and 00/100------------------- ------------------------------------------------------------------- dollars (� 870.00 ). Payment to be made as follows: N/30 An)' amount due under this agreement which is not paid when due shall bear interest at ilia rate of 1-l.2 percent per month front the date such :unounl teas duc until paid upon acceptance of this proposal. lit t}te case of default in utceting terms of payniont. owner agrees to pay all costs and reasonable atlorncv's foes if action is brought to collect the amuunt due upon acceptance of this proposal. All material is guaranteed to be as specified. All work to be completed in a substantial Authorized workmanlike nnanner according to the specifications submitted, per standard practices. Signature e A — Any alteration or deviation front above specifications involving extra costs will be esec i(ed Hank Artlip only upon ivritlen orders. and will become an extra charge over curd above ilia estimate. All alycullentl Contingent upoll strikes. aceidents or delays bcYond our control. Owner to carry Note: This pmlxlsal may be fire. tornado and othet nccessarY insuratcc. Our workers arc full• covered by Workmani s withdrawn by its if not accepted within 30 de}s. Compensation Insurance. �CCL'P'I;��CIi Oh l'RUI'US:\I "Ilicaboyc prices. specilication and conditim s are satisfactory and arc hereby accepted. You are :mtborized to do ilia Siguauvc work as specified. Payment will be made as ottiiacd above. Date of Acceptance: signature _ LITE CONSTRUCTION 711 South Lake Street P.O. Box 135 MONTGOMERY, IL 60538 (630) 896-7220 Eau (630) 896-1304 TO Cordogan Clark & Associates ._960 _Ridgeway..Ave .......... __ ...._....... ..........._ Aurora, IL 60506 ................. .............................. ...__..........._._._............._..._._.._ ...... We hereby agree to make the change(s) specified below: ............... ....._................ ,............... ............................. ...... I.... .......... ........_..._............ 52 Number PHONE I DA JOB "Tor`1°Cv (e0' ity Hall Police Facility 21-364 JOB NUMBER JOB PHONE EXISTING CONTRACT NO. DATE Or EXISTING CONTRACT ............................................................................................................................................................... _.. ................ ...... .. ..... .......... .. ...._..._ ....... ........_ .... .........__....,.......................... ......... .......... _............ .. ........... ....__................................,. ... _......... ..... .. _....... ....... _. _ ... _........... .. NOTE: This Change Order becomes part of and in conformance with the eristing contract Wre- AGIEUE hereby to make the change) specified above at Phis price C� $ DATE PREVIOUS CONTRACT AMOUNT $ AUTHORIZED SIGNATURE (CONTRAI& OR) i ) REVISED CONTRACT TOTAL $ I ACCEPTED — The aboA prices and specifications of U this Change Order are satisfactory and are hereby Date of acceptance accepted. All work to be performed under same terms { J� and conditions as specified in original contract unless Signature othenuise stipulated. i " " �P • r� G R O U P 7 An Employee Owned Company ESTABLISHED IN 1985 To: Lite Construction, Inc. 711 S Lake St Montgomery, IL 60538 Phone (630) 896-7220 Change Request Date 02/28/23 Ship To: Job Site 651 Prairie Pointe Dr. Yorkville, IL Attention : Tim Campbell Project Id :2022-2-11BH Project Desc. Yorkville City Hall Ship Via : Our Truck Terms n/a P.O. Number n/a Architect n/a Salesperson : Brian Hedburg Architectural Qty UOM Description Reference Change Request CR8 Quartz Repair 1 lot Quartz Repair 1 CR8 Quartz Repair TOTAL $ 720.00 If the above itemsand pricing are satisfactory, please sign, date, and returnthisform as soon as possible. Lead time forchange orders will not begin until The Horizon Group, Inc. has received written approval. By signing this Change Order, you authorize The Horizon Group, Inc. to collect paymentforthese items. ACCEPTED BY: (PdntNa (Signature www.thehorizongroupinc.com 806 West 76th Street Davenport IA 52806 (563) 391-1891 Fax (563) 391-9079 LIFE CONSTRUCTION 711 South Lake Street P.O. Box 135 MONTGOMERY, IL 60538 (630) 896-7220 Fax (630) 896-1304 TO Cordogan Clark & Associates 960 Ridgeway.. Ave. ......_........................ Aurora, IL 60506 ......_.......................................................................................................................... _....... We hereby agree to make the change(s) specified below: 53 Number PHONE D-2014/23 JOB N 1 OErCVilNOtity Hall Police Facility 21-364 JOB NUMBER JOB PHONE EXISTING CONTRACT NO. DATE- OF EXISTING CONTRACT $12703 7.00........................._........ (-$7,500.00) $.1..3.1.6010.0..................... _..........._..... $855.00 ..........................................._...................._......_...................-. NOTE_ This Change Order becomes part of and in conformance with the existing contract 119L AG nIEEE-7 hereby to make the change sj peci9ied above at this price L�> DATE t PREVIOUS CONTRACT AMOUNT AUTHORIZED SIGNATURE (CONTRA O 1 ZZ — REVISED CONTRACT TOTAL $ n ACCEPT" — The above p ices and specifications of Date of acceptance this Change Order are satisfactory and are hereby accepted. All wort; to be performed under same terms and conditions as specified in original contract unless Signature otherwise stipulated. " Direct Sign Systems I NAMEIADDRESS I Lite Constriction 711 S Lake Street PO Box 135 Montgomery, IL 60538-0135 129 C'unin?ermd Urine, Unit (i "Vorl-willo, lllinoi.z; 6,01i60 Fax: 6 0-55:1- i •': •19 Ship To Yorkville Police Station Tint Campbell DATE QUOTE NO. 2/2312023 5883 Rep P.O. No. JOB TTK DESCRIPTION QTY COST TOTAL 5" x 8" ADA Pliotopolyntcr Sign 102 76.00 7,752.00 2 Custom Paint Colors (Background and Copy) 8" x 6" ADA Pltotopolymer Sign 3 85.00 255.00 2 Custom Paint Colors (Background and Copy) 9" x 6" ADA Photopolymer Sign 13 95.00 1,235.00 2 Custom Paint Colors (Background and Copy) Iel! y gtt�nti . i believe 10" x 6" ADA Plrotopolymer Sign tllefe cal"e 10 2 Custom Paint Colors (Background and Copy) offal 9 105.00 945.00 5" x 8" Painted Acrylic Backers for Signs on Glass �" `------•-y 9 50.00 450.00 8" Cast Aluminum Letters Painted Font Itclvetica 1 875.00 875.00 CITY SERVICES 8" Cast Aluminum Letters Painted Font: Hclvetica 1 475.00 475.00 POLICE Delivery (Installation to be done by Lite Construction) 50.00 50.00 Approval Required to Start Production TOTAL Page 1 Direct Sign Systems NAME/ADDRESS Lite Construction 711 S Lake Street PO Boa 135 Montgomery, IL 60538-0135 129 Commercial Di•>>-c. unit 6 York%'010, Illinoix 605(10 E-mail:signz.;�a irect`�i n.nct. Ship To Yorkville Police Station Tim Campbell DATE QUOTE NO. 2/23/2023 5883 Rep P.O. No. JOB TTK DESCRIPTION QTY COST TOTAL Any changes to the sizes or quantities of signs will change the 0.00 0.00 pricing accordingly. Cancellation of an order after drawings are submitted may result in a cancellation fee. LAYOUTS NEED TO BE SIGNED B. EMAILED BACK TO BEGIN PRODUCTION. AFTER APPROVAL HAS BEEN GIVEN, ANY ADDITIONAL CHANGES WILL, BE BILLED ACCORDINGLY. Shipping costs are additional. This quote is valid for 90 days. Lead-time is approx. 8 weeks from all approvals. Please call with anv questions, 630-553-7446. Approval Required to Start Production TOTAL S 12,037.00 Page 2