Resolution 2023-12Resolution No. 2023-12
A RESOLUTION APPROVING CHANGE ORDERS RELATING TO
651 PRAIRIE POINTE DRIVE, YORKVILLE, ILLINOIS
(Twelfth Set of Change Orders)
WHEREAS, the United City of Yorkville, Kendall County, Illinois (the "City") is a duly
organized and validly existing non -home rule municipality created in accordance with the
Constitution of the State of Illinois of 1970 and the laws of the State; and,
WHEREAS, the City has acquired the building and property commonly known as 651
Prairie Pointe Drive (the "New City Hall") for the purpose of rehabilitating the building and
repurposing it as the new Yorkville City Hall and the headquarters of the Yorkville Police
Department (the "Project"); and,
WHEREAS, the City issued a Request for Proposals to construct the Project and after
review and evaluation of submittals from several firms, the City entered into a contract with Lite
Construction of Montgomery, Illinois (the "Contract"); and,
WHEREAS, the Contract, as approved by the City with Lite Construction, provided a line
item for unforeseen contingencies due to the fact that the New City Hall was constructed in 2007
and change orders were guaranteed to come as demolition of existing walls and ceilings occurred;
and,
WHEREAS, Lite Construction has submitted two (2) change orders to the original
Contract, as itemized on the list attached hereto, modifications to the original work design as
mandated to conform to current code standards resulting in an additional costs totaling $13,465;
and,
WHEREAS, the City has reviewed the change orders as submitted by Lite Construction
and acknowledges that the work covered by these change orders was unforeseen but is necessary
Resolution No. 2023-12
Page 1
and in the best interest of the City; therefore, the City is prepared to approve the Change Order as
hereinafter provided.
NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of the United
City of Yorkville, Kendall County, Illinois, as follows:
1.
Section 1. The foregoing preambles are hereby adopted as if fully restated in this Section
Section 2. That the change orders as itemized on the list attached hereto as submitted by
Lite Construction resulting in total additional costs of $13,465 are hereby approved.
Section 3. That this Resolution shall be in full force and effect upon its passage and
approval as provided by law.
Passed by the City Council of the United City of Yorkville, Kendall County, Illinois this
251" day of April, A.D. 2023.
KEN KOCH AYE
ARDEN JOE PLOCHER AYE
CHRIS FUNKHOUSER AYE
SEAVER TARULIS AYE
ITV CLERK
DAN TRANSIER AYE
CRAIG SOLING AYE
MATT MAREK AYE
RUSTY CORNEILS AYE
APPROVED by me, as Mayor of the United City of Yorkville,, endall County, Illinois
this 01 day of 1 , A.D. 2023. �-
MAYOR
Attest:
C TY CLERK
Resolution No. 2023-12
Page 2
LITE CONSTRUCTION
L
711 South Lake Street
P.O. Box 135
54
MONTGOMERY, IL 60538
Number
(630) 896-7220
PHONE
1
DA012/23
Fax (630) 896-1304
TO Cordogan Clark & Associates
JOB NV40EIIfVCI r 11101ti
e ty Hall Police Facility
960 Ridgeway..Ave ...........................................................
Aurora, IL 60506
21-364
....... . .....
JOB NUMBER
JOB PHONE
EXISTING CONTRACT NO.
DATE OF EXISTING CONTRACT
We hereby agree to mate the change(s) specified below:
... .......
.. ........
PR 043 for exit signs
Valley, Electric
- ..........
$1,538.00
LCI Mark up
$154.00
Total..._
.......... ....
.... .. .... -
...... ....
...... .-S.I.J.692I 0-0
...... ........ .. ... .. .................
. ......... .
.................
.... ..... .. ... ... .... ..........
..........
. ...........
....... .......... ...........
.......... .. - ................
. .. ... .. ..... .. .... .... .....
.................... ................
. ......
............ .. ..............................
. .. ....
........ ... . -
NOTE; This Change Order becomes part of and in conformance with the existing contract
WEE AQPar--E hereby to make the change(s) specified above at this price 0
$
DATE
PREVIOUS CONTRACT AMOUNT $
AUTHORIZED SIGNAT E 11::� A7 I
r !�_ A I ) I REVISED CONTRACT TOTAL $
ACCEPTED — TlYe above prices and specifications of Date of acceptance
this Change Order are satisfactory and are hereby
accepted. All work to be performed under same terms
and conditions as specified in original contract unless Signature
otherwise stipulated.
PROPOSED CHANGE ORDER
Valley Electrical Contractors CCN # 10179-42
Po Box 461 CCN Date 4/11/2023
Oswego, IL 60543 Date: 4/11/2023
Telephone: 630-554-6200 Project Name: Yorkville City Hall and Police Station
Fax: 630-554-5543 Project Number: 10179
Page Number: 1
Client Address:
Lite Construction
Contact: Tim Campbell
711 S. Lake St
Montgomery, IL 60538
Telephone: 630-896-7220
Contact: Tim Campbell
Work Description
We reserve the right to correct this quote for errors and omissions.
This change order is for demoing an existing exit sign then furnishing
and
installing 2 new ones per PR043.
Itemized Breakdown
Description
Qty
EX1 - Single Face
1
EX1 - Double Face
1
1/2" EMT
20
1/2" EMT DC SS CONN
4
1/2" EMT DC SS CPLG
4
1/2" MINRLAC W/BOLT 0-B
4
#12 THHN
70
42-1/8" SQ BOX 3/4" KO
2
4" SQ BLANK COVER
2
3/C #14 6' FIXTURE WHIP
2
Totals
110
Summary
General Materials
113.67
LIGHTING FIXTURES
663.32
Material Overhead (@ 10.000 %)
77.70
Material Markup (@ 5.000 %)
42.73
Material Total
897.42
JOURNEYMAN (4.68 Hrs @ $137.00)
641.16
Final Adjustment
-0.58
Final Amount $1,538.00
ORIGINAL
Document G709 - 20 1 8
Proposal Request
PROJECT: (name and address)
City Hall & Police Facility Renovation
651 Prairie Point Dr. Yorkville, IL
OWNER: (name and address)
United City of Yorkville
800 Game Farm Rd. Yorkville, IL
CONTRACT INFORMATION:
Contract For: General Construction
Date: March 8, 2022
ARCHITECT: (name and address)
Cordogan Clark & Associates
960 Ridgeway Ave. Aurora, IL
Architect's Project Number: 21-364
Proposal Request Number: 043
Proposal Request Date: 04/10/2023
CONTRACTOR: (name and address)
Lite Construction, Inc.
711 S. Lake St. Montgomery, IL
The Owner requests an itemized proposal for changes to the Contract Sum and Contract Time for proposed modifications to
the Contract Documents described herein. The Contractor shall submit this proposal within Five (5) days or notify the
Architect in writing of the anticipated date of submission.
(Insert a detailed description of the proposed modifications to the Contract Documents and, if applicable, attach or reference
specific exhibits)
The following items were requested by City of Yorkville building inspector per email 03/13/2023.
In Open Office 332 near door 329, remove existing electrical sign and replace with EX1 type directional arrow exit sign, pointing toward
door 326. In Break -Out 325, provide EX1 type directional arrow exit sign, visible from adjacent corridors and pointing toward door S301.
Refer to attached sketch for locations. Provide all wiring and conduit required to complete scope of work.
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO PROCEED WITH THE WORK
DESCRIBED IN THE PROPOSED MODIFICATIONS.
REQUESTED BY THE ARCHITECT:
Lauren Kiley Architectural Designer
PRINTED NAME AND TITLE
AIA Document G709 — 2018. Copyright 01993, 2001 and 2018. All rights reserved. "The American Institute of Architects," "American Institute of Architects,"
"AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 09:15:08 CT on
04/10/2023 under Order No.3104237387 which expires on 09/10/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance
with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (3B9ADA51)
L00 )ISV £ti0 ad ANS 00EL'646'ZL6 9L96'969'069
OL909 SIONI-III `OJHOIHO 90909 SIONIIINHoand NOILOOHl5N00 • SNIMNISN3 • 3801O311HOUV
£ZOZ/06/60 31V(l 133211S 9113M H12iON 9LL 3nN3AH l.VM3E)"' 096 N"`jV+�YJJ fl: Nty/'JdOA AOG
trK-2 a39vynN103rONd NOliVAON36l ll-IlOdd 3OMd (INV �1VH Ail3 u' J �
0
R O
N CLL LL Yf
\ CJ
o
L
Aso
LITE CONSTRUCTION
U 2- t �
711 South Lake Street
P.O. Box 135
55
MONTGOMERY, IL 60538
Number
(630) 896-7220
PHONE
DA4tl2 23
Fax (630) 896.1304
TO Cordogan Clark & Associates
EOC
JOB N �o/r`kvt� e10
ity Hall Police
Facility
960...Ridgeway..A.ve... ..... .
Aurora, IL 60506
21-364
JOB NUMBER
JOB PHONE
EXISTING CONTRACT NO.
DATE OF EXISTING CONTRACT
We hereby agree to make the change(s) specified below:
_. _.
.........
.....
............ .. ................ ................
...,......._
Temporary AV system for the Council Chambers
_..... _._ ............. ....... .
......... ....................
................. _.._................... ........ ......_...
.......__ .................. .__..............
Val.ley_Electric .__ . _
$...I0,702 00 ...........................
LCI Mark up
$1,071.00
Total._._ __ . _.._.. __ ......._..........
_ _....... _
_. __ _. ............
_.__ ......_....__..__..........
$11;773.00.1._.__ .......... __ .._ ......
_... __... _......... _. ................ _ ...........
.......
........... _... ...
._ .............
..........
._. _..... .......... _ _ .._ ..._ ..
.._._ .........
..... ....... ....._ __.... ..__ .._... _ _..._............. ......... .. __ ......._. _
............. __..__ .... ................... ... .........._........
NOTE: This Change Order becomes part of and in conformance with the existing contract.
CE AGIPRE hereby io make ihe changes) specified above at This price
DATE
.' Z PREVIOUS CONTRACT AMOUNT $
AUTHORIZED SIGNATURE I T R)
REVISED CONTRACT TOTAL $
i
ACCEPTED — The above prices and specifications of 2
this Change Order are satisfactory and are hereby Date of acceptance t 2-�-
accepted. Ali work to be performed under same terns
and conditions as specified in original contract unless Signature
othennvise stipulated. (OWNER) ��
PROPOSED CHANGE ORDER
Valley Electrical Contractors CCN # 10179-43
Po Box 461 CCN Date 4/12/2023
Oswego, IL 60543 Date: 4/12/2023
Telephone: 630-554-6200 Project Name: Yorkville City Hall and Police Station
Fax: 630-554-5543 Project Number: 10179
Page Number: 1
Client Address:
Lite Construction
Contact: Tim Campbell
711 S. Lake St
Montgomery, IL 60538
Telephone: 630-896-7220
Contact: Tim Campbell
Work Description
We reserve the right to correct this quote for errors and omissions.
This change order is the cost for the temporary AV system in the council
chambers and multiple rooms.
Itemized Breakdown
Summary
AV Rack - ACG ($9,266.30 + 0.000 % + 10.000 % + 5.000 %) 10,702.58
Subtotal 10,702.58
Final Amount $10,702.58
ORIGINAL