Resolution 2023-15Resolution No. 2023-15
A RESOLUTION APPROVING CHANGE ORDERS RELATING TO
651 PRAIRIE POINTE DRIVE, YORKVILLE, ILLINOIS
(Thirteenth Set of Change Orders)
WHEREAS, the United City of Yorkville, Kendall County, Illinois (the "City") is a duly
organized and validly existing non -home rule municipality created in accordance with the
Constitution of the State of Illinois of 1970 and the laws of the State; and,
WHEREAS, the City has acquired the building and property commonly known as 651
Prairie Pointe Drive (the "New City Hall") for the purpose of rehabilitating the building and
repurposing it as the new Yorkville City Hall and the headquarters of the Yorkville Police
Department (the "Project"); and,
WHEREAS, the City issued a Request for Proposals to construct the Project and after
review and evaluation of submittals from several firms, the City entered into a contract with Lite
Construction of Montgomery, Illinois (the "Contract"); and,
WHEREAS, the Contract, as approved by the City with Lite Construction, provided a line
item for unforeseen contingencies due to the fact that the New City Hall was constructed in 2007
and change orders were guaranteed to come as demolition of existing walls and ceilings occurred;
and,
WHEREAS, Lite Construction has submitted one (1) change order to the original
Contract, as itemized on the list attached hereto, modifications to the original work design as
mandated to conform to current code standards resulting in an additional costs totaling $1,952;
and,
WHEREAS, the City has reviewed the change order as submitted by Lite Construction
and acknowledges that the work covered by the change order was unforeseen but is necessary and
Resolution No. 2023-15
Page 1
in the best interest of the City; therefore, the City is prepared to approve the Change Order as
hereinafter provided.
NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of the United
City of Yorkville, Kendall County, Illinois, as follows:
1.
Section 1. The foregoing preambles are hereby adopted as if fully restated in this Section
Section 2. That the change order as itemized on the list attached hereto as submitted by
Lite Construction resulting in total additional costs of $1,952 are hereby approved.
Section 3. That this Resolution shall be in full force and effect upon its passage and
approval as provided by law.
Passed by the City Council of the United City of Yorkville, Kendall County, Illinois this
9th day of May, A.D. 2023.
KEN KOCH
ARDEN JOE PLOCHER
CHRIS FUNKHOUSER
SEAVER TARULIS
AYE
AYE
AYE
AYE
k bUPUJ
C Y CLERK
DAN TRANSIER
CRAIG SOLING
MATT MAREK
RUSTY CORNEILS
APPROVED by me, as Mayor of the United City of Yorkvi e,
this � �t�day of , A.D. 2023.
t1
Attest:
CIT CLERK
Q(
MAYOR
AYE
AYE
AYE
AYE
County, Illinois
Resolution No. 2023-15
Page 2
LITE CONSTRUCTION
711 South Lake Street
P.O. Box 135
MONTGOMERY, IL 60539
(630) 895-7220
Fax (630) 896.1304
TO Cordogan Clark & Associates
_..960. Ridgeway .Ave...._._.........._.....
Aurora, IL 60506
.................................................................................................................................
We hereby agree to make the change(s) specified below:
Add 2 additional exit lights per PR044
i
56
Number
PHONE D
JOB NITOr%Vi1Tfetity Hall Police Facility
21-364
JOB NUMBER JOB PHONE
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT
...........Valley. E.I. ectri.c............................ .......................... ....._$.1.,7_7.5:.0............
LCI Mark up $177.00
Total................................................................................................._..... .... ................ ............
.............. $.1.952: 00.......................................__.
... .......... ....... ....... .......................... ..._.................-.................. .... .... ......... ............................................_............. .... ....... .......... .............. .... ...-..............................._.......... .....
.....................................................
NOTE: This Change Order becomes part of and in conformance with the existing contract.
WE AGREE hereby io make the change cy specigied above at this price E:� $ ' 9%:52
DATE
PREVIOUS CONTRACT AMOUNT $
AUTHORIZC-D SIGNATURE (CONY R)
/f REVISED CONTRACT 7(54I-A $
ACCEPTED — The above prices and specifications of }
this Change Order are satisfactory and are hereby /-7 Date of acceptance
accepted. All work to be performed under same terns
and conditions as specified in original contract unless Signature
otherwise stipulated. I I (OWNER)
PROPOSED
Valley Electrical Contractors CCN # 10179-44
Po Box 461 CCN Date 411112023
Oswego, IL 60543 Date: 4/19/2023
Telephone: 630-554-6200 Project Name: Yorkville City Hall and Police Station
Fax: 630-554-5543 Project Number: 10179
Page Number: 1
Client Address:
Lite Construction
Contact: Tim Campbell
711 S. Lake St
Montgomery, IL 60538
Telephone: 630-896-7220
Contact: Tim Campbell
Work Description
We reserve the right to correct this ctuote for errors and omissions.
This change order is for installing 2 additional exit signs per PR044.
Itemized Breakdown
Description
Qty
EX1 - Single Face
1
EX1 - Double Face
1
1/2" EMT
40
1/2" EMT DC SS CONN
4
1/2" EMT DC SS CPLG
4
1/2" MINRLAC W/BOLT 0-B
4
#12 THHN
140
42-1/8" SQ BOX 3/4" KO
2
4" SQ BLANK COVER
2
3/C #14 6' FIXTURE WHIP
2
Totals
200
Summary
General Materials
161.32
LIGHTING FIXTURES
663.32
Material Overhead (@ 10.000 %)
82.46
Material Markup (@ 5.000 %)
45.36
Material Total
952.46
JOURNEYMAN (6.01 Hrs @ $137.00)
823.37
Final Adjustment
-0.83
Final Amount $1,775.00
IsT:TI;e OMA �
Proposal Request
PROJECT: (name and address)
City Hall & Police Facility Renovation
651 Prairie Point Dr. Yorkville, IL
OWNER: (name and address)
United City oCYorkville
800 Game Farm Rd. Yorkville, IL
CONTRACT INFORMATION:
Contract For: General Construction
Date: March 8, 2022
ARCHITECT: (name and address)
Cordogan Clark & Associates
960 Ridgeway Ave. Aurora, IL
Architect's Project Number: 21-364
Proposal Request Number: 044
Proposal Request Date: 04/19/2023
CONTRACTOR: (name and address)
Lite Construction, Inc.
711 S. Lake St. Montgomery, IL
The Owner requests an itemized proposal for changes to the Contract Sum and Contract Time for proposed modifications to
the Contract Documents described herein. The Contractor shall submit this proposal within Five (5) days or notify the
Architect in writing of the anticipated date of submission.
(Insert a detailed description of the proposed modifications to the Contract Documents and, if applicable, attach o)• reference
specific exhibits.)
The following items were requested by City of Yorkville Fire Marshall per email 04/13/2023.
In Open Office 222 at door 222, provide EX type double sided directional arrow exit sign, pointing towards Major Case/ Work Area 227. In
Council Chambers 340 B, provide EXI type directional arrow exit sign, pointing toward door 340D. Refer to attached sketch for locations.
Provide all wiring and conduit required to complete scope of work.
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO PROCEED WITH THE WORK
DESCRIBED IN THE PROPOSED MODIFICATIONS.
REQUESTED BY THE ARCHITECT:
Lauren Kiley Architectural Designer
PRINTED NAME AND TITLE
AIA Document G709 — 2018. Copyright ® 1993, 2001 and 2018. All rights reserved. "The American Institute of Architects," "American Institute of Architects,"
"AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 11:13:47 CT on
04119/2023 under Order No.3104237387 which expires on 09/10/2023, Is not for resale, is licensed for one-time use only, and may only be used in accordance
with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfc@alacontracts.com.
User Notes: (3B9ADA54)
--- - - - - -- ( os$ osS os$ OS$
13 FJ� 1J (E) 7� 7i� 7I EXI 7I� Z21
SI� 5II/ SI= FI� 7 7 7� i
5I� SI� II� 5I� �= )� 1I= 7'�
N) F1 FI Po F�I� 7 7 7
5N 5N 5N IF7 g
FII����\\..--\\\\-,,IIII ft Fi F4 F17
� F1� F1
57® �
51�J 5 5 ).
F4 F1 FI FI F
5 7= 7= 7- 7
N 5I� 5I� 5I� 6 FI F���j F1 F
1271GJ 7F,�-j 7t�]
E) : EXI
H "F1� Ft� H� FI� Ft�IGJ
F
13 (EI 7 7 7 7 7 7 7
SOS SOS SOS $OS
FIF-,-;;;i FI F� FI
CITY HALL AND POLICE FACILITY RENOVATION
D�
S Fl
3N
i
F2
F
7�
i
F2
F1 7
Fl
iEXI
g )
F1�7
FI�FS 7
3I�;IrII�A
SOS
CORDUGAN CLARK PROJECT NUMBER 21-364
960 RIDGEWAY AVENUE 716 NORTH WELLS STREET DATE
ARCHITECTURE • ENGINEERING - CONSTRUCTION AURORA,JLLINOIS 60506 CHICAGO, ILLINOIS 60610
630.896..4678 312.943.7300 SHEET
04119/2023
PR 044 ASK 001