Public Works Packet 2024 04-16-24
AGENDA
PUBLIC WORKS COMMITTEE MEETING
Tuesday, April 16, 2024
6:00 p.m.
East Conference Room #337
651 Prairie Pointe Drive, Yorkville, IL
Citizen Comments:
Minutes for Correction/Approval: March 19, 2024
New Business:
1. PW 2024-31 Water Reports for July 2023 – March 2024
2. PW 2024-32 Capital Improvement Projects Update
3. PW 2024-33 Quarterly Bond and Letter of Credit Reduction Summary
4. PW 2024-34 Leak Detection Contract with M.E. Simpson
5. PW 2024-35 Pavement Management Program Update – Preliminary Engineering Agreement
6. PW 2024-36 Kennedy Road and Freedom Place Intersection Improvements – Contract Award
7. PW 2024-37 Kennedy Road and Freedom Place Intersection Improvements – Construction
Engineering Agreement
8. PW 2024-38 Supplemental MFT Resolution for Bulk Rock Salt
9. PW 2024-39 Oak Street Parking Restriction
10. PW 2024-40 Tuscany Trail Parking Restriction
Old Business:
1. PW 2023-84 Route 47 Expansion and Improvements – Update and Overview – Follow-Up
Additional Business:
United City of Yorkville
651 Prairie Pointe Drive
Yorkville, Illinois 60560
Telephone: 630-553-4350
www.yorkville.il.us
UNITED CITY OF YORKVILLE
WORKSHEET
PUBLIC WORKS COMMITTEE
Tuesday, April 16, 2024
6:00 PM
CITY HALL CONFERENCE ROOM
---------------------------------------------------------------------------------------------------------------------------------------
CITIZEN COMMENTS:
---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------
MINUTES FOR CORRECTION/APPROVAL:
---------------------------------------------------------------------------------------------------------------------------------------
1. March 19, 2024
□ Approved __________
□ As presented
□ With corrections
---------------------------------------------------------------------------------------------------------------------------------------
NEW BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
1. PW 2024-31 Water Reports for July 2023 – March 2024
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
2. PW 2024-32 Capital Improvement Projects Update
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
3. PW 2024-33 Quarterly Bond and Letter of Credit Reduction Summary
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
4. PW 2024-34 Leak Detection Contract with M.E. Simpson
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
5. PW 2024-35 Pavement Management Program Update – Preliminary Engineering Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
6. PW 2024-36 Kennedy Road and Freedom Place Intersection Improvements – Contract Award
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
7. PW 2024-37 Kennedy Road and Freedom Place Intersection Improvements – Construction Engineering
Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
8. PW 2024-38 Supplemental MFT Resolution for Bulk Rock Salt
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
9. PW 2024-39 Oak Street Parking Restriction
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
10. PW 2024-40 Tuscany Trail Parking Restriction
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
OLD BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
1. PW 2023-84 Route 47 Expansion and Improvements – Update and Overview – Follow-Up
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
ADDITIONAL BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
Minutes
Tracking Number
Minutes of the Public Works Committee – March 19, 2024
Public Works Committee – April 16, 2024
Majority
Committee Approval
Minute Taker
Name Department
DRAFT
Page 1 of 3
UNITED CITY OF YORKVILLE
PUBLIC WORKS COMMITTEE
Tuesday, March 19, 2024, 6:00pm
Yorkville City Hall, East Conference Room #337
651 Prairie Pointe Drive, Yorkville, IL
IN ATTENDANCE:
Committee Members
Chairman Ken Koch Alderman Rusty Corneils
Alderman Craig Soling Alderman Matt Marek
Other City Officials
City Administrator Bart Olson Assistant City Administrator Erin Willrett
Engineer Brad Sanderson, EEI Public Works Director Eric Dhuse
Alderman Chris Funkhouser
Other Guests:
Richard Vinyard, Cannonball Estates
The meeting was called to order at 6:00pm by Chairman Ken Koch.
Citizen Comments: None
Previous Meeting Minutes: February 20, 2024
The minutes were approved as presented.
New Business:
1. PW 2024-22 2024 Road to Better Roads – Contract Award
Mr. Sanderson reported 3 bids were received late February for the base road program. All bids were about the
same and he recommended D Construction be awarded the work for $1,382,442.77. This moves to the regular
agenda.
2. PW 2024-23 2024 Road to Better Roads – Construction Engineering Agreement
This agreement pertains to the contract discussed above. It is with EEI in the amount of $112,791 and is
included in the budget. This moves to the consent agenda.
3. PW 2024-24 2024 Asphalt Rejuvenation – Contract Award
Engineer Sanderson said this year the rejuvenating program was separated out from the Road to Better Roads
since it was found a higher amount is being paid by combining them. Mr. Marek noted that the price difference
was 30-40%. Only 2 contractors in this area do rejuvenating work and CAM (Corrective Asphalt Materials) was
the only bidder, in the amount of $82,748.25 and they are being recommended. The rejuvenation is being done
to extend the life of the asphalt. This moves forward to the City Council regular agenda.
4. PW 2024-25 2024 Water Main Replacement Contract A – Contract Award
Bids were taken on March 7th and Mr. Sanderson said they were substantially below the estimate. He
recommended awarding the contract to Conley Excavating at $2,312,286.15 and work is expected to start mid-
summer through fall. He said Conley has been very good to work with in the past. Alderman Funkhouser asked
if penalties are added into contracts for delays not outside their control. Mr. Sanderson said there are clauses in
every contract allowing the city to recoup costs. To avoid any problems, EEI will work with Ms. Willrett and
Page 2 of 3
Mr. Dhuse to post information and weekly meetings can be conducted to stay on track. This moves to the
regular agenda.
5. PW 2024-26 2024 Water Main Replacement Contract A – Construction Engineering Agreement
Mr. Olson said this item goes hand in hand with the above contract. This contract is with EEI and is $191,659
which is budgeted this year and next year. This moves to the consent agenda.
6. PW 2024-27 Resolution Authorizing the Execution of Certain Contracts (Certificate of Authority for Rock
Salt Purchases)
Mr. Dhuse said this is a new procedure and in order to file for salt purchases, this contract must be approved by
the City Council. Approval will give Mr. Dhuse and Mr. Olson authority to enter these contracts with the state
and to bid on and purchase the salt. This moves forward to the consent agenda.
7. PW 2024-28 Road Resurfacing Intergovernmental Agreement with Bristol Township
Mr. Dhuse said the city and Bristol Township will trade some paving that needs to be done. Bristol Township
will do paving in the Conover Subdivision and the city will do paving near McHugh and Walnut. The specs are
the same and no money will change hands. The agreement holds each party harmless and EEI will oversee the
McHugh paving and the county engineer will monitor the Conover paving. Alderman Soling noted a water
drainage problem on Sunset which will be corrected. This moves to the Council consent agenda.
8. PW 2024-29 2024 EEI Hourly Rates
Mr. Olson said EEI has requested an hourly rate change. He said it impacts the city in 3 ways 1) base contracts,
2) hourly rates get incorporated into supplemental agreements and 3) developer work. The rate increase request
is approximately 3.89%. Alderman Soling asked if this is in line with other rate increases. Mr. Olson gave a few
examples and compared previous EEI requests which he said were inflationary. If approved, these rates will be
effective for 2024. Alderman Funkhouser asked for some numbers for some of the EEI classifications. This
moves forward to the regular agenda with committee approval.
9. PW 2024-30 Rob Roy Drainage District – Additional Work
This work is being done as part of an agreement between the city and the Drainage District at the request of the
area farmers. Mr. Dhuse said some work remains and there are many trees on the downslope side of the ditch.
Alderman Funkhouser said if the stumps are cleared, 18-19 acres of land could be gained as tillable land. He
said he had issue with spending money on this, however, he noted this had been agreed upon. He believes the
farmers should be responsible. Alderman Corneils asked why the city is overseeing this since it seems like a
county project. and Mr. Dhuse replied that the city is involved since the Drainage District lacks funds and
personnel. Mr. Olson added that in a court hearing, it was determined the city would manage the contract and
the work as long as the District got the funds from the county. All work must be done by December 31st this year
or unspent money will be returned to Kendall County. Alderman Koch asked what would happen if the costs
are more than the $500,000 allotted. The Drainage District can then levy a tax, but staff thought that was
doubtful. This moves to the regular agenda.
Old Business:
1. PW 2023-83 Kylyns Ridge Subdivision Traffic Sign Analysis
Mr. Sanderson reported the traffic study was done last fall and presented to the committee then with several
discussion points. Striping was requested to slow the traffic. He said the locations for striping are limited but
one was found on High Ridge between Faxon and Blackberry Shore. It is expected this would slow the traffic
by 1-7 mph, but is less effective on a low-speed road. He said the average speed on High Ridge Rd. is 28-29
mph in the posted 30-mph zone. Alderman Funkhouser also suggested clustered trees to help create a tunnel
effect. He would like a solution for Northland also. He said there is a lot of cut-through traffic from Whispering
Meadows.
Thermoplastic striping plus signs would be installed. These type of stripes have not been done before. Mr.
Dhuse commented that snowplows will basically destroy the stripes after a couple years and paint would be used
Page 3 of 3
then. Alderman Marek asked how results would be measured--another analysis would be done afterward.
Repaving will be done this year and the stripes would be applied afterward. Alderman Funkhouser said the PD
could also monitor speeds as part of a program they are putting in place to monitor traffic. Signs mounted on
trees are also collecting data.
Mr. Richard Vinyard of Northland Lane provided input as well. He said Northland Lane and Blackberry Shore
did not connect previously and speeding was not an issue until it opened to through traffic. He said residents in
the area have been parking cars on both sides in an effort to narrow the street and slow traffic. The townhomes
being built will also increase traffic and there is limited parking already. He suggested contacting Home Depot
to install “No Trespassing” signs to eliminate using the area as a cut-through since it is private property. He said
drivers cannot see kids there and cars have to yield to one another. Mr. Olson said any discussion with Home
Depot must be reviewed by the attorney first and must be discussed with engineering Mr. Marek added that
Home Depot gets upset with people driving through there. Mr. Vinyard noted that in his town of employment,
the police have entered into agreements with retailers to be able to police their parking lots to reduce issues.
The striping will go forward and Mr. Sanderson will include the work in the bid package. This moves to the
consent agenda with committee approval.
Additional Business:
There was discussion about the proposed new Public Works facility. Committee members brought forth
suggestions and ideas for the new building as well as the shape of the building and salt dome. Mr. Olson
encouraged all ideas to be forwarded to city administrators. Input from Public Works and Parks employees is
being provided and Mr. Olson will discuss with the architect. The committee also talked about the new
facilities at South Elgin and Montgomery and some of the features they thought useful.
In another matter, Alderman Soling asked to revisit the Adams St. and Van Emmon area where the residents have
asked to have the stumps removed and a steep bank remediated. Mr. Dhuse has been working with the
Conservation Association who advised the stumps should remain to keep the bank intact. Public Works will be
doing work there.
There was no further business and the meeting adjourned at 7:16pm.
Minutes respectfully transcribed by
Marlys Young, Minute Taker
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #1
Tracking Number
PW 2024-31
Water Reports for July 2023 – March 2024
Public Works Committee – April 16, 2024
Majority
Approval
Acceptance of the monthly water reports per IEPA regulations.
Eric Dhuse Public Works
Name Department
Summary
Monthly water reports need to be approved by the City Council per IEPA regulations.
Background
Each month the Water Department provides a monthly report to the IEPA on each of our
wells. This report is summarized in the attached monthly sheets. The IEPA mandates that the
governing body approve the water reports as a check to make sure the governing body is given
an opportunity to review the data.
Recommendation
Staff recommends approval of the monthly water reports as presented.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: April 9, 2024
Subject: Water Reports
United City of Yorkville
WATER DEPARTMENT REPORT
July
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 392 23,376,000
7 1527 1125 520 15,517,600
8 1384 840 303 16,344,000
9 1368 861 370 15,437,000
TOTAL PUMPED 70,674,600
CURRENT MONTH’S PUMPAGE IS 11,769,000 GALLONS LESS THAN LAST MONTH
4,441,600 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 2,279,826 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,716 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 92.55 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1698 LBS. FED CALCULATED CONCENTRATION: ___3.09__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.75 __ MG/L
POLYPHOSPHATE: 1678 _ LBS. FED CALCULATED CONCENTRATION: ___1.07___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.75 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __4 NUMBER OF LEAKS OR BREAKS REPAIRED: __ ___
MXU’S: _ BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __35 COMMERCIAL: ___0_ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
August
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 393 29,546,000
7 1527 1125 510 13,028,000
8 1384 840 301 16,750,000
9 1368 861 374 15,042,000
TOTAL PUMPED 74,366,000
CURRENT MONTH’S PUMPAGE IS 3,691,400 GALLONS LESS THAN LAST MONTH
12,153,300 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 2,398,903 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,970 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 100.23 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1733 LBS. FED CALCULATED CONCENTRATION: ___2.91__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.75 __ MG/L
POLYPHOSPHATE: 1643 _ LBS. FED CALCULATED CONCENTRATION: ___0.96___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.75 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __1 NUMBER OF LEAKS OR BREAKS REPAIRED: __ _1__
MXU’S: _ 1 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __44 COMMERCIAL: ___0_ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
September
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 393 7,076,000
7 1527 1125 510 20,475,000
8 1384 840 300 19,864,000
9 1368 861 370 17,557,000
TOTAL PUMPED 64,972,000
CURRENT MONTH’S PUMPAGE IS 9,394,000 GALLONS LESS THAN LAST MONTH
2,987,000 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 2,165,733 ___GALLONS
DAILY MAXIMUM PUMPED: __ 3,080 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 88.57 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1425 LBS. FED CALCULATED CONCENTRATION: ___2.80__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.77 __ MG/L
POLYPHOSPHATE: 1643 _ LBS. FED CALCULATED CONCENTRATION: ___0.84___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.75 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __12 NUMBER OF LEAKS OR BREAKS REPAIRED: __ ___
MXU’S: _ 1 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __30 COMMERCIAL: ___1_ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
October
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 392 340,000
7 1527 1125 571 21,932,500
8 1384 840 300 17,199,000
9 1368 861 388 18,279,000
TOTAL PUMPED 57,750,500
CURRENT MONTH’S PUMPAGE IS 7,221,500 GALLONS LESS THAN LAST MONTH
2,469,500 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,862,919 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,331,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 76.44 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1579 LBS. FED CALCULATED CONCENTRATION: ___3.47__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.77 __ MG/L
POLYPHOSPHATE: 1139 _ LBS. FED CALCULATED CONCENTRATION: ___0.88___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.77 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __24 NUMBER OF LEAKS OR BREAKS REPAIRED: _4_ ___
MXU’S: _ BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __29 COMMERCIAL: ___1_ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
November
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 393 165,000
7 1527 1125 508 22,770,000
8 1384 840 302 16,675,000
9 1368 861 404 15,044,000
TOTAL PUMPED 54,645,000
CURRENT MONTH’S PUMPAGE IS 3,096,500 GALLONS LESS THAN LAST MONTH
5,510,400 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,821,800 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,317,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 78.76 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1395 LBS. FED CALCULATED CONCENTRATION: ___3.08__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.75 __ MG/L
POLYPHOSPHATE: 1048 _ LBS. FED CALCULATED CONCENTRATION: ___0.81___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.77 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __18 NUMBER OF LEAKS OR BREAKS REPAIRED: _2_ ___
MXU’S: _6 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __29 COMMERCIAL: ____ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
December
2023 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 394 14,246,000
7 1527 1125 512 16,308,000
8 1384 840 299 13,664,000
9 1368 861 360 13,521,000
TOTAL PUMPED 57,739,000
CURRENT MONTH’S PUMPAGE IS 3,085,000 GALLONS MORE THAN LAST MONTH
7,348,200 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,862,548 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,543,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 94.45 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1336 LBS. FED CALCULATED CONCENTRATION: ___2.38__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.71 __ MG/L
POLYPHOSPHATE: 1095 _ LBS. FED CALCULATED CONCENTRATION: ___0.68___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.71 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __12 NUMBER OF LEAKS OR BREAKS REPAIRED: _1_ ___
MXU’S: _21 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __19 COMMERCIAL: ____ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
January
2024 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 392 18,844,000
7 1527 1125 508 11,280,500
8 1384 840 328 14,955,000
9 1368 861 365 12,133,000
TOTAL PUMPED 57,212,500
CURRENT MONTH’S PUMPAGE IS 526,500 GALLONS LESS THAN LAST MONTH
7,723,800 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,845,565 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,200,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 100.49 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1232 LBS. FED CALCULATED CONCENTRATION: ___2.06__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.65 __ MG/L
POLYPHOSPHATE: 1044 _ LBS. FED CALCULATED CONCENTRATION: ___0.61___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.65 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __11 NUMBER OF LEAKS OR BREAKS REPAIRED: _2_ ___
MXU’S: _5 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __21 COMMERCIAL: ____ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
February
2024 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 393 15,078,000
7 1527 1125 506 10,846,000
8 1384 840 319 13,619,000
9 1368 861 358 11,269,000
TOTAL PUMPED 50,812,000
CURRENT MONTH’S PUMPAGE IS 6,400,500 GALLONS LESS THAN LAST MONTH
5,450,500 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,752,138 ___GALLONS
DAILY MAXIMUM PUMPED: __ 1,978,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 71.60 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1163 LBS. FED CALCULATED CONCENTRATION: ___2.06__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.64 __ MG/L
POLYPHOSPHATE: 1039 _ LBS. FED CALCULATED CONCENTRATION: ___0.91___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.65 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __16 NUMBER OF LEAKS OR BREAKS REPAIRED: _1_ ___
MXU’S: _1 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __21 COMMERCIAL: ____ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
United City of Yorkville
WATER DEPARTMENT REPORT
March
2024 _
MONTH / YEAR
WELLS
NO WELL DEPTH
(FEET)
PUMP DEPTH
(FEET)
WATER ABOVE PUMP
(FEET)
THIS MONTH’S PUMPAGE
(GALLONS)
4 1394 795 393 16,052,000
7 1527 1125 550 12,431,700
8 1384 840 323 13,384,000
9 1368 861 390 12,290,000
TOTAL PUMPED 54,157,700
CURRENT MONTH’S PUMPAGE IS 3,345,700 GALLONS MORE THAN LAST MONTH
4,017,700 GALLONS MORE THAN LAST YEAR
DAILY AVERAGE PUMPED: _ 1,747,023 ___GALLONS
DAILY MAXIMUM PUMPED: __ 2,289,000 GALLONS
DAILY AVERAGE PER CAPITA USE: ___ 71.44 __ GALLONS (Population 23,000)
WATER TREATMENT:
CHLORINE: 1243 LBS. FED CALCULATED CONCENTRATION: ___2.93__ MG/L
FLUORIDE: _ 0 LBS. FED MEASURED CONCENTRATION: _____0.66 __ MG/L
POLYPHOSPHATE: 1123 _ LBS. FED CALCULATED CONCENTRATION: ___0.93___ MG/L
WATER QUALITY:
BACTERIOLOGICAL SAMPLES ANALYZED BY ILLINOIS ENVIRONMENTAL PROTECTION AGENCY:
__30 SATISFACTORY _____ UNSATISFACTORY (EXPLAIN)
___________________________________________________________________________________________
FLOURIDE: __ 3 __ SAMPLE(S) TAKEN CONCENTRATION: _ 0.65 MG/L
MAINTENANCE:
NUMBER OF METERS REPLACED: __7 NUMBER OF LEAKS OR BREAKS REPAIRED: _2_ ___
MXU’S: _12 BATTERIES REPLACED: _
NEW CUSTOMERS:
RESIDENTIAL: __16 COMMERCIAL: ____ INDUSTRIAL/GOVERNMENTAL: ___ ___
COMMENTS:
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #2
Tracking Number
PW 2024-32
Capital Project Update
Public Works Committee – April 16, 2024
None
Informational
A status update on projects will be given.
Brad Sanderson Engineering
Name Department
The purpose of this memo is to update the Public Works Committee as to the status of the several
projects. A summary on the status of the projects is provided below:
Construction Projects
2023 Water Main Replacement Program – Contract A
The work is substantially complete. Punchlist items are expected to be addressed this spring.
2023 Water Main Replacement Program – Contract B
The work is substantially complete. Punchlist items are expected to be addressed this spring.
2024 Water Main Replacement Program – Contract B
Construction is underway and estimated to be 40% complete. The contract completion date is July 31st.
Planning/Design Projects
Downtown Riverwalk Feasibility Study
Design engineering has commenced.
WIFIA Loan Application
Work has begun on the application.
Kennedy / Freedom Place Intersection Improvements
Design engineering is complete. We are working on land acquisition with the City Attorney. A letting is
scheduled for April 8th.
2024 RTBR
The contract has been awarded. The contract substantial completion date is July 26th with a final of
September 27th.
2024 Local Road Program
Design engineering has begun and is approximately 70% complete. We are targeting a May letting.
Van Emmon Street STP
Design engineering has begun and is approximately 70% complete. We are targeting a fall letting.
Well 10 Raw Water Main
The contract has been awarded pending IGA approval. The contract substantial completion date is
August 10th with a final of October 15th.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: April 4, 2024
Subject: Capital Improvement Projects Update
Well 10
The contract has been awarded pending IGA approval. The contract completion date is April 2025.
2024 Water Main Improvements – Contract A
The contract has been awarded. Work is projected to begin in May. The contract completion date is
November 8th.
Center Street Water Main
Design engineering has begun and is approximately 80% complete. We are anticipating a May letting.
Rt 47 Water Main Replacement – Water Park Way to Jericho
Design engineering has begun and is approximately 90% complete. We have made an initial submittal to
IDOT for their review.
Well No. 7 Electrical
Design engineering has commenced. We are anticipating a May letting.
Eldamain Water Main Loop
Design engineering has commenced. Easement acquisition is in process.
Corneils Sanitary Sewer
Design engineering has commenced. Easement acquisition is in process.
Southern Sanitary Sewer Connection
Design engineering has commenced. Easement acquisition is in process.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #3
Tracking Number
PW 2024-33
Bond/LOC Reduction Summary Through March 31, 2024
Public Works Committee – April 16, 2024
None
Informational
Brad Sanderson Engineering
Name Department
Please see the attached reduction summary through March 31, 2024. If you have any questions,
please let me know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: March 31, 2024
Subject: 2024 Bond/LOC Reduction Summary
31-Mar-24
2024 Bond and Letter of Credit Reduction Report
Date Development/Project
Engineer
Concurrence
City Administrator
Concurrence
Mayor
Concurrence Reduction Final Release Reduction Value Remaining Balance
1/4/2024 Bristol Bay Unit 10 X X X 1,935,804.50$ 486,992.50$
1/4/2024 Bristol Bay Unit 12 X X X 737,852.00$ 217,451.80$
1/25/2024 Grande Reserve Units 13, 14 and 23 Sidewalk X X X 26,120.00$ 18,760.00$
2/27/2024 Ashley Road Improvements X X X 48,401.17$ -$
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Please note, there is no page 7 of 9 for the Associated Technical Services LTD (ATS) proposal.
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #4
Tracking Number
PW 2024-34
Leak Detection Proposal
Public Works Committee – April 16, 2024
Supermajority (6 out of 9)
Approval
Proposals from leak detection companies to leak detection services on all water
main as part of the non-revenue water loss calculation as required for LM water.
Eric Dhuse Public Works
Name Department
Summary
Staff is proposing a multi-year contract with M.E.Simpson to perform leak detection on
all 156 miles of water main as required by our decision to use Lake Michigan water. The
proposal is for a 3-year term.
Background
Each year we are required to survey all our water mains for leaks. This is to ensure that
we stay below the mandated 10% non-revenue water loss that has been set for Lake Michigan
water users. Even though we are not current users, we must be below the 10% threshold to
receive Lake Michigan water.
For the past few years, we have used M.E.Simpson to perform the leak detection surveys.
They have been thorough, affordable, and good to work with. There are very few companies that
perform this service, and even fewer that perform to the level we expect. They have earned our
respect and trust by being thorough with their surveys, and very accurate with pinpointing the
location of leaks. This is a very important aspect of the service, having accurate locations saves
time, energy, and money when staff repairs the leaks.
To be sure that we are getting the best price, we asked another leak detection company to
provide a quote for the same services that M.E. Simpson provides for us. We solicited
Associated Technical Services, ATS, to provide the quote. I have attached the proposal for your
review. ATS is a good company, we have used their services on and off for over 25 years.
When we compare the quotes, ATS did not quote 3 years, but the 1-year quote was
$54,834.20 which was considerably higher than M.E. Simpson’s quote of $40,560. ATS also
offered an incentive-based survey for $30,957.16 plus $425 for any water main leaks, and $125
for any fire hydrant leaks. I do not recommend this service at this time. Once we have our non -
revenue water losses consistently under 10%, we can look at that type of option.
When we asked ATS to amend their quote for 3 years, they simply changed the dates, but
nothing else. I take that as the price will stay at $54,834.20 for each year.
M.E. Simpson quoted us $40,560 in year 1, $40,560 in year 2, and $41,340 in year 3 of
the contract. The increase in year 3 is a 2% increase. I feel that we are getting better pricing
from M.E. Simpson, and we have been very satisfied with their work through the years.
At this time, we have $40,000 budgeted within the Lake Michigan Capital Project
Projection that was approved as part of the FY 25 budget.
Recommendation
Staff recommends the approval of the quote from M.E. Simpson Co., Inc. for the 3 year
term.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: April 8, 2024
Subject: Proposed Leak Detection Quote
www.ATSLIMITED.com Office: 630.834.1558
ASSOCIATED TECHNICAL SERVICES LTD 321 E Kenilworth Ave., VILLAPARK, IL
February 21, 2024
City of Yorkville
610 Tower Ln.
Yorkville, Illinois 60560
Attn: Mr. Jon Bauer
Water/Sewer Department Foreman
RE: 2024-26 Water Distribution System Leak
Detection & Location Survey Proposal
Dear Mr. Bauer,
We are pleased to present the following proposal to perform a multi-phase “ATS COMPREHENSIVE
LEAK DETECTION & LOCATION SURVEY” for the City of Yorkville.
With an "ATS Leak Survey Program" your water conservation program will fast track to its best
possible course. Of the three factors that create an "unaccounted for water loss figure" (UAW): System
Leakage, Metering Errors, and Accounting Procedures, an "ATS Leak Survey Program" is the most cost-
effective and time-efficient measure that a water utility can take to reduce its Unaccounted-for Water
Loss. This is water which is treated and pumped out to your customers only to be lost through leaks into
the ground and adjacent sewers lines without generating any revenue.
As each newly discovered leak is repaired, the Village will realize immediate returns on your leak
survey dollars. In fact, over the years, ATS Leak Surveys have averaged a $15: $1 return in recovered
water vs. the cost of hiring ATS. Nationwide studies have determined that of these three major factors, a
properly performed leak survey will have the biggest positive impact in reducing water loss in the least
amount of time while spending a fraction of the cost of a typical meter testing & replacement program.
We also recommend that both metering and accounting procedures be assessed as an important part of
any comprehensive water system audit. Annual Fire Hydrant Flushing and Flow Testing, plus Valve
Assessment Programs will help ensure that your water system operates at peak efficiency.
“Why Is ATS Your Best Choice?”
QUALITY: “Quality is never an accident. It is always the result of high intention, sincere effort, intelligent
direction, and skillful execution. It represents the wise choice of many alternatives.”
ATS has earned its standing as one of the most innovative and successful leak location firms in
America. We have conducted literally hundreds of leak surveys in cities of all sizes, ages, and make-
ups, all across the Midwest region. Many of these cities have also had experience with other leak survey
firms in addition to ATS. In every one of those cities, ATS has never failed to find less than 2 to 10 times
the amount of leakage than the competitor’s survey that preceded the ATS Survey.
Established 1979
WATER CONSERVATION SPECIALISTS
EMERGENCY LEAK PINPOINTING ● LEAK DETECTION SURVEYS ● UNDERGROUND UTILITY LOCATION ● GIS / GPS SURVEYS
VALVE EXERCISING ● CCTV PIPE INSPECTIONS ● HYDRANT TESTING & FLUSHING ● LOCATION EQUIPMENT SALES & TRAINING
City of Yorkville 2 of 9 February 21, 2024
2024-26 Leak Survey Proposal
A Comprehensive ATS Leak Survey is typically accomplished with these steps:
Pre-Survey Meeting – conducted with ATS Survey Project Manager, to discuss all aspects of
the project from methodology, equipment, documentation, and results with the Village.
The Designated Survey Area is divided up into manageable “survey sub-areas” which are
scaled directly from your maps to get the quantity of water main in each area.
ATS Crews will check in with the Village at the start of every survey workday. You will always
know where we will be that day and what kind of progress we are making. Our office never
closes. ATS Crews and Offices are available 24 hours a day / 365 days a year.
Ultrasonic Leak Detection Phase of each survey sub-area. We will log every monitored
appurtenance, every detected suspect leak site, all map discrepancies and any inaccessible
points that need to be found or exposed, so they can be surveyed.
Map Discrepancies - All appurtenances that are shown incorrectly or not shown at all on your
maps will be logged on our survey sheets.
Computerized Electronic Leak Location Phase – Re-survey every suspect leak site and
accurately pinpoint every subsequently detected leak.
Leak Location Reports are submitted as leaks are located. Leak locations are marked,
diagramed, and documented in detail.
Final Survey Report - Gather Leak Repair Data, Recovery calculations, Leak Locations and
assemble Final Report. Present the comprehensive Final Survey Report to the Village
WATER SYSTEM DATA AND SURVEY HISTORY
The New Lenox Water Distribution System contains 156 lineal miles (836,680 lineal feet) of Gray Cast
Iron and Ductile Iron Water Main. All these pipe materials adequately transmit leak sounds for leak
detection. The New Lenox water system serves a population of 26,141 residents through approx. 8,900
metered water services. This is significant because water service line leaks are the most common leak
that we find with ATS Leak Surveys.
The water system contains 2,250 Fire Hydrants and 2,160 Mainline Valves. Every single one of them
in the designated survey area will be used as primary checkpoints for leak sounds. Every accessible
Hydrant Auxiliary Valve will also be monitored for leak sounds. Hundreds of Curb Stops (B-Boxes) will
also be checked for leak sounds as needed.
City of Yorkville 3 of 9 February 21, 2024
2024-26 Leak Survey Proposal
There are good reasons why choosing ATS makes excellent business sense.
Superior Experience - ATS helped introduce leak location correlators, and subsequently started to
specialize in leak detection in 1979. As a result, ATS has performed more leak surveys and pinpointed
more leaks with this technology than anyone. ATS developed the leak survey techniques, correlator
survey specs and field strategies that have become the standards for the industry. Over the years many
of FCS – Fluid Conservation Systems’ top people including Regional Managers, Sales Staff, Instructors,
and their longtime Director of Operations also received training from ATS. FCS also uses ATS for Beta
testing new equipment innovations plus software upgrades and developments.
Conserving Municipal Manpower and Resources - Many public works departments are already stretched
to their limit, providing quality services to your citizens. With our tremendous amount of municipal leak
survey experience, ATS frees up your staff so that they can concentrate on their normal duties without
distraction. Municipal involvement is normally answering questions and freeing up inaccessible points \
during the location phase on an “as-needed basis”.
24 Hour Customer Support During and After the Survey – ATS never has less than two crews on call 24
hours a day / 365 days a year. ATS has a fleet of 10 Correlator Equipped “ATS Leakmobiles” out in the
field five days a week. Every mobile van is fully equipped with an experienced and trained two-person
crew capable of handling any leak location or utility location situation you will ever have. While other
water suppliers typically wait 3 or more hours for our competitors to arrive, ATS is almost always on the
scene in 60 - 90 minutes or less of your call for help. No other firm consistently responds to emergencies
as quickly as ATS.
Superior Results - Like anything in life, the person who practices their craft every day is going to have
distinct and measurable advantages over the person that does not do it as often, and subsequently, as
well. For 43 years, ATS has been out in the field everyday performing leak surveys, utility locations and
leak pinpointing. Subsequently our listening skills are going to be that much more acute. Your survey is
more effectively accomplished while we detect more leaks and pinpoint them with more consistent
accuracy than a more infrequent correlator operator can do.
No one listens more intently to every accessible access point than ATS. Therefore, we detect more
suspect leak sounds than anyone else.
No one works at a suspect leak site more aggressively than ATS. Therefore, we turn more suspect
leak sounds into confirmed leak locations than anyone else.
No one spends more time analyzing a suspect leak site as thoroughly as ATS. Therefore no one
pinpoints more leaks as accurately as ATS does. For our clients, more precise leak pinpointing
means less digging and less restoration costs.
ATS spends more time performing your leak survey so you can spend less time repairing them and
get a greater return in recovering precious water and reducing your water losses.
City of Yorkville 4 of 9 February 21, 2024
2024-26 Leak Survey Proposal
ESTIMATE OF COST
The ATS Comprehensive Leak Survey Program is the most thorough and successful leak survey
program in business on two fronts – Superior Findings and Consistently Accurate Pinpointing. Put it all
together and you will get the most cost-effective leak survey possible.
OPTION A: All-Inclusive (lump sum) Based Survey Pricing - With this type of contract proposal,
the detection phase is a lump sum figure and pinpointing is priced per pinpointed leak. Final billing will be
based upon the total amount of surveyed water main. Total price is locked in regardless of the actual
total number and types of pinpointed leaks. This is our most popular survey program. Without
guaranteed money beyond the detection phase, this unique contract pricing puts the incentive on ATS to
produce results.
OPTION B: Incentive-Based Pricing gives the Village the most flexibility and the opportunity to
save money if the water system turns out to be tighter than expected. The Village still wins if it ends up
that your water system contains a good number of leaks because you won’t spend an extra dollar without
getting an accurate leak location in return. Since there are no fee guarantees for ATS beyond the
detection phase, there is obvious incentive for ATS to find as many leaks as possible for the Village. The
more leaks we find, the more money you save.
OPTION C: Fire Hydrant Survey allows ATS to move through system swiftly and timely. This is
your best choice when you have limited funds in your budget. Also allows for repairs to be done in a
timely fashion and prepare for the next year’s fiscal budget.
All-Inclusive Based Pricing
Detection and Location Phase:
836,680 lineal feet of water main @ $ 0.065 per L.F. = $ 54,384.20
Incentive- Based Pricing
Detection Phase: 836,680 @ $ 0.037 per lineal foot of water main = $ 30,957.16
Location Phase: $ 425.00 per leak that is pinpointed in the field.
$ 125.00 per leak that is determined to be a leaking Fire Hydrant.
Hydrant Survey Only
Option C:
Detection Phase: 836,680 per lineal feet of water main @ $ 0.025 per LF = $ 20,917.00
Location Phase: $ 425.00 for Every Pinpointed Main Line and Service Line Leak.
$ 125.00 for Every Fire Hydrant Leak and Valve Leak.
SURVEY COMPLETION TIME: We estimate the DETECTION PHASE of the survey can be completed
in approximately 35 - 50 workdays (Weather permitting). The duration of the LOCATION PHASE will
depend upon the number of suspect leak sites to investigate and actual number, type and location of
those pinpointed leaks. Based upon our experience, another 15 - 20 workdays for pinpointing are
possible.
City of Yorkville 5 of 9 February 21, 2024
2024-26 Leak Survey Proposal
Scope of Work
ATS Comprehensive Survey Program: Every fire hydrant, accessible hydrant auxiliary valve, and every
mainline valve will be monitored for leak sounds. When a water system starts to get tighter, there is
more emphasis on the surveyor to have to dig deeper to find the leaks that are not making obvious leak
sounds. This fact makes monitoring every valve essential to finding these tough leaks. Valves are the
best quality listening point possible. The thoroughness of this technique ensures that every detectable
leak is found.
ULTRASONIC LEAK DETECTION: The existence and general neighborhood of every detected suspect
leak is established with FCS S-30 Ultrasonic Leak Detection Equipment. A preliminary leak size and
leak type classification is also made at that time. A significant difference between an ATS Leak Survey
and the other surveyors is in the ultrasonic leak detection phase’s number of checkpoints. You put
yourself in the best position to detect more leaks by listening to as many points as possible, especially
mainline valves. No one checks more points for leak sounds as accurately and as thoroughly as ATS.
DETECTION SURVEY RECORDS: Every accessible fire hydrant, hydrant auxiliary valve and mainline
valve is monitored for suspect leak sounds. B-Boxes are checked only in the vicinity of a detected
suspect leak site. Valuable survey and system data is collected and logged on these records. This data
includes Appurtenance Type and Location, General Conditions Encountered, Accessibility, Map
Discrepancies and Leak Sound Characteristics.
COMPUTERIZED LEAK ANALYSIS & PINPOINTING: Every suspect leak site, no matter how slight the
sound, is electronically confirmed with one of our 10 computerized FCS AccuCorr, FCS Tri-Corr 2002,
FCS 9090 or Sewerin SeCorr Leak Noise Correlator Systems. The pinpointing phase begins with
ultrasonically resurveying every suspect leak site, electronic Correlator analysis of every suspect leak
site to either eliminate a suspect leak site or accurately confirm the presence of the leak and pinpoint its
exact location. By analyzing, timing, and measuring leak sound waves simultaneously from two
monitoring points, the leak’s exact location is pinpointed with unmatched consistent accurately.
WATER MAIN and VALVE LOCATION: All of the water main and service connections are accurately
located in the vicinity of every leak location. This helps ensure that every survey leak is pinpointed as
accurately as possible. All utility line location work is expertly performed with Radiodetection RD7000,
RD8000 High Performance Utility Location Systems, Schonstedt, CTS Berger and Radiodetection
Ferromagnetic Metal Locators. No one works a leak site harder than ATS!
“X” MARKS THE SPOT! The pinpointed location of every mainline, service line and valve leak will be
marked in the field with spray marking paint with an “X”. The exceptions are homeowner’s side service
leaks and hydrant leaks. A “Leak Location Report” form documents the location and type, characteristics
of every pinpointed leak.
LEAK LOCATION REPORTS: This is an individual report form that details the exact location and
characteristics of each pinpointed leak. These forms are submitted daily as the leaks are pinpointed.
The Village with actual leak repair information updates each Leak Report which is used to calculate
water loss and revenue recovery data for the Final Report
City of Yorkville 6 of 9 February 21, 2024
2024-26 Leak Survey Proposal
FINAL REPORT: Three (3) copies of a comprehensive FINAL SURVEY REPORT will be submitted after
the completion of the survey. Additional copies are available upon request. Your Final Report will
concisely detail all our survey activities and findings, estimated & calculated leak sizes, and revenue
recovery calculations for each leak. We also include survey area maps showing leak locations in each
area and system-wide leak locations, plus each individual leak location report with Village repair and
calculated leak size information, general observations, and recommendations.
INITIATING THE SURVEY: We only need your verbal authorization followed by your Purchase Order
and / or signed ATS Leak Survey Contracts, to schedule your Pre-Survey Meeting, and initiate your
Survey. The Pre-Survey Meeting details all aspects of the survey.
Yours Truly,
ASSOCIATED TECHNICAL SERVICES LTD.
Marcia A. Kaplar
Marcie A. Kaplar
Survey
Manager
City of Yorkville 8 of 9 February 21, 2024
2024-26 Leak Survey Proposal
GENERAL CONDITIONS
LEAK DETECTION & LOCATION SURVEYS
Responsibility of ATS / Associated Technical Services Ltd.
A) Two-Person crew qualified to operate the ATS Leak Detection & Location System.
B) The “ATS Leak Detection & Location System” consists of:
FCS S30 Ultrasonic Leak Surveyor Instruments (Leak Detection Phase)
FCS/Fluid Conservation Systems and Sewerin Leak Noise Correlators (Leak Location Phase)
FCS and Sewerin Ultrasonic Preamplifiers (Leak Location Phase)
FCS, Wilcoxen, Vibrometer, Sewerin Accelerometers, Gas Sensors, Hydrophone Sensors
Radcom FCS SoundSens Programmable Leak Correlation / Localization System
Radiodetection RD7000 and RD8000 Utility Location Systems; CST Berger, Fisher, Schonstedt and
Radiodetection Ferro Magnetic Location Equipment for buried valve enclosures.
C) “ATS Leakmobile” - Mobile Van with self-contained power supply and /or capability of operating from
an alternate VAC 60 Hz source, or suitable alternate vehicle at the discretion of ATS.
D) Mobilization / Mileage – Round Trip, Portal-to-Portal and On-Site.
E) On-Site Consultation with the Owner or their representatives, as necessary.
F) The entire area designated by the Owner shall be surveyed for leakage. Detected leaks shall be
pinpointed only on that part of the water system maintained by the Owner. Unless it is previously
specified and ordered, customer service line leaks will only be pinpointed up to the municipal side of
the curb stop without additional charges. Leaks on the customer side of the curb stop typically
require a separate appointment so ATS can contact the service line inside the building.
G) Only those leaks that are detected by the ATS Leak Survey are to be included in the pinpointing
phase of this contract. Unless other previous arrangements are made, any pinpointing of any
incidentally or coincidentally occurring leakage, main breaks or previously known leakage that was
not initially included in our proposal or as a part of this agreement shall be charged at our normal
rates for scheduled / emergency service callouts.
H) If the “Re-monitoring of Repaired Leak Sites” service is specified, included in our proposal and
ordered, this agreement, leak repairs to that site must be completed within 30 days after that leak’s
location report was submitted to the Owner. The Owner then must notify ATS at the time of repairs
so re-monitoring can be scheduled. All subsequently detected leakage will be located.
I) ATS will establish and mark the location of a leak or leaks in the field with either marking paint, a field
stake and / or written individual “ATS Leak Location Report”.
J) ATS will provide basic traffic warning equipment and traffic control and re-direction with flagmen.
on an as-needed basis, whenever conditions dictate the necessity of these safety precautions.
ATS Work Zone Safety Equipment includes but is not limited to safety vests, vehicle arrow.
boards, strobe warning lights and safety cones that are used whenever our vehicles are parked
during the leak survey on residential and other light or slower traffic areas.
City of Yorkville 9 of 9 February 21, 2024
2024-26 Leak Survey Proposal
GENERAL CONDITIONS FOR LEAK SURVEYS
RESPONSIBILITY OF OWNER
The Owner will ensure easy access to all main line valves, valve boxes or other strategically
necessary access points. This may also include exposing and cleaning out auxiliary valves and b-boxes
on an as-needed basis if they will facilitate the accurate confirmation and pinpointing of a detected leak.
This could include breaking loose needed valve covers; pumping water out all valve vaults and boxes
and, if necessary, removing debris from those enclosures to make the valves and adjoining pipelines
accessible. The Owner will also make access available to any point or location strategically needed by
ATS to perform said work at the discretion of ATS.
If the Owner orders leak pinpointing between the curb stop and the customer’s building, the Owner
shall be responsible for contact with the customer. Pinpointing can be performed on a weekday from
9:00 AM to 1:00 PM without incurring overtime charges.
The Owner will make available to ATS all available location maps, schematics, as-built drawings,
final reports from previous leak surveys, and any other data pertaining to the area being surveyed.
Access to the “IDOT LMO-2” Annual Water Audit Reports is also very helpful.
The Owner will make available knowledgeable, qualified personnel for consultation and assistance
regarding the Owner’s water system.
Identify the authorized representatives of the Owner to act on behalf of the Owner and sign ATS
agreements, purchase orders and additional work orders.
Give ATS right of access, and necessary identification required, and notify appropriate authorities
(Police, Fire Dept., Public Works Dept., etc.) as needed of program underway.
The Owner will at its option, provide Traffic Warning Equipment, Traffic Control and Re-Direction with
Flagmen on an as-needed basis, should conditions dictate the necessity of this safety precaution.
Instances such as a lane closure in a heavy traffic area may require hiring the services of a Work
Zone Safety Vendor to provide the necessary traffic control equipment such as barricades, warning
lights, arrow panels and temporary barriers. The Owner must approve any use of a Work Zone
Safety Vendor in advance. The owner will be responsible for the costs of the Work Zone Safety
Vendor.
Owner’s repair crews shall make a reasonable effort to provide ATS with accurate leak repair
information whenever this data is available. Repair data should detail the following: Date of repair;
type of leak; approximate size and shape of the leak orifice; approximate water pressure; and method
of repair. This information is necessary for ATS to make leak size, water loss and revenue recovery
calculations for a comprehensive “Leak Survey Final Report”.
Please Note: ATS does not guarantee the detection or accurate pinpointing of a leak or leaks
but does assure that the best effort in that regard will be put forward.
Certain input data to the ATS Leak Detection & Location System is based upon information received
from the Owner. The accuracy of the Owner’s data will directly affect the results of the Leak Survey.
ATS will attempt to verify such data by consultation with the Owner and thereupon will have a right to rely
upon the accuracy of the Owner’s data. ATS is not liable for any costs to the Owner as a result of
incomplete or inaccurate data supplied by the Owner or their representatives.
Intentionally Left Blank
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #5
Tracking Number
PW 2024-35
Pavement Management Program Update – Preliminary Engineering Agreement
Public Works Committee – April 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
Proposed construction engineering agreement with EEI for the Pavement Management Update.
Background
Attached is the proposed Construction Engineering Agreement for the Pavement
Management Update. This update will score the roads for us and assist us in deciding which
roads need attention in the 5-year CIP. This will be the second update to the plan, the original
work was performed in 2013, an update in 2018, and now an update in 2023.
EEI’s proposed contract would manage the project, process and analyze the data, make
recommendations, and assist in the budgeting for the projects. The cost for these services would
be a fixed fee of $89,920. This money is budgeted in the approved FY25 budget in the
Engineering Services line within the City-Wide Capital Fund.
Recommendation
Staff recommends approval of the construction engineering agreement with EEI for the
Pavement Management Update.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: April 10, 2024
Subject: Pavement Management Update Engineering Agreement
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 1
Pavement Management Program Update
United City of Yorkville
Professional Services Agreement – Preliminary Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
ENGINEER agrees to furnish to the City the following services: The ENGINEER
shall provide any and all necessary engineering services to the City as indicated
on the Scope of Services (Attachment B). Preliminary Engineering for a Pavement
Management System update for the City’s approximate 120 miles of roadways will
be provided.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the
Contractor shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to Contractor:
ENGINEER shall receive as compensation for all work and services to be
performed herein, an amount based on the Estimated Level of Effort and
Associated Cost included in Attachment C. Preliminary Engineering will be paid
for as a Fixed Fee (FF) in the amount of $89,920, of which direct expenses are
estimated at $45,500. The hourly rates for this project are shown in the attached
2024 Standard Schedule of Charges (Attachment E). All payments will be made
according to the Illinois State Prompt Payment Act and not less than once every
thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
written notice of any change in the rates specified in Section C hereof (or on any
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 2
E. Ownership of Records and Documents:
Contractor agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. Contractor agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the freedom of information act or
if already previously disclosed by a third party. Upon termination of this agreement,
Contractor agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by Contractor without contractors
consent. Modifications of any signed duplicate original document not authorized
by ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kendall County, Illinois.
G. Independent Contractor:
Contractor shall have sole control over the manner and means of providing the
work and services performed under this agreement. The City’s relationship to the
Contractor under this agreement shall be that of an independent contractor.
Contractor will not be considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The Contractor certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to
perform the service.
Anti-Bribery: The Contractor certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or
admission of bribery or attempted bribery of an officer or employee of the State of
Illinois or any other state.
Loan Default: If the Contractor is an individual, the Contractor certifies that he/she
is not in default for a period of six months or more in an amount of $600 or more
on the repayment of any educational loan guaranteed by the Illinois State
Scholarship Commission made by an Illinois institution of higher education or any
other loan made from public funds for the purpose of financing higher education (5
ILCS 385/3).
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 3
Felony Certification: The Contractor certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The Contractor certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720
Illinois Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The Contractor certifies that it is in compliance with the
Drug Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective
date of this contract. The Drug Free Workplace Act requires, in part, that
Contractors, with 25 or more employees certify and agree to take steps to ensure
a drug free workplace by informing employees of the dangers of drug abuse, of
the availability of any treatment or assistance program, of prohibited activities and
of sanctions that will be imposed for violations; and that individuals with contracts
certify that they will not engage in the manufacture, distribution, dispensation,
possession, or use of a controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
Contractor agrees to comply with applicable provisions of the Illinois Human
Rights Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the
Americans with Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the
rules applicable to each. The equal opportunity clause of Section 750.10 of the
Illinois Department of Human Rights Rules is specifically incorporated herein. The
Contractor shall comply with Executive Order 11246, entitled Equal Employment
Opportunity, as amended by Executive Order 11375, and as supplemented by U.S.
Department of Labor regulations (41 C.F.R. Chapter 60). The Contractor agrees
to incorporate this clause into all subcontracts under this Contract.
International Boycott: The Contractor certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979
or the regulations of the U.S. Department of Commerce promulgated under that
Act (30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires
the Contractor (and any subcontractors) to maintain, for a period of 3 years after
the later of the date of completion of this Contract or the date of final payment
under the Contract, all books and records relating to the performance of the
Contract and necessary to support amounts charged to the City under the
Contract. The Contract and all books and records related to the Contract shall be
available for review and audit by the City and the Illinois Auditor General. If this
Contract is funded from contract/grant funds provided by the U.S. Government,
the Contract, books, and records shall be available for review and audit by the
Comptroller General of the U.S. and/or the Inspector General of the federal
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 4
sponsoring agency. The Contractor agrees to cooperate fully with any audit and to
provide full access to all relevant materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The Contractor certifies that
he/she is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien
The Internal Revenue Service requires that taxes be withheld on payments made
to non resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the Contractor certifies that
its Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
Contractor shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on
account of damage to or destruction of property resulting from the performance of
work under this agreement by Contractor or its Subcontractors, or due to or arising
in any manner from the wrongful act or negligence of Contractor or its
Subcontractors of any employee of any of them. In the event that the either party
shall bring any suit, cause of action or counterclaim against the other party, the
non-prevailing party shall pay to the prevailing party the cost and expenses
incurred to answer and/or defend such action, including reasonable attorney fees
and court costs. In no event shall the either party indemnify any other party for the
consequences of that party’s negligence, including failure to follow the
ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of
the types of services rendered hereunder. (Not applicable as having been
previously supplied)
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 5
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed
by both parties. In the event that any provisions of this agreement shall be held to
be invalid or unenforceable, the remaining provisions shall be valid and binding on
the parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimate of Level of Effort and Associated Cost
Attachment D: Estimated Schedule
Attachment E: 2024 Standard Schedule of Charges
UNITED CITY OF YORKVILLE PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 6
L. Notices:
All notices required to be given under the terms of this agreement shall be given
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time to time substitute addresses
or persons in connection with required notices.
Agreed to this _____day of __________________, 2024.
United City of Yorkville: Engineering Enterprises, Inc.:
___________________________ __________________________
John Purcell Brad Sanderson, PE
Mayor Chief Operating Officer / President
___________________________ __________________________
Jori Behland Angie Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. ATTACHMENT A – APRIL 2024
PAGE 1
STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furn ish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction docum ents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provisio n of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinio n
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in el ectronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at th e
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations.
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
ENGINEERING ENTERPRISES, INC. ATTACHMENT A – APRIL 2024
PAGE 2
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have i ncurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warran ty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a) Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b) Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c) Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d) Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against the ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to car ry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions b eing taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting su ch force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of in voices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of th e
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonab le fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
UNITED CITY OF YORKVILLE, IL PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 1
Pavement Management Program Update
United City of Yorkville, IL
Professional Services Agreement - Preliminary Engineering
Attachment B – Scope of Services
1. Project Management and Coordination
• Budget Tracking
• Management of Personnel and the Engineering Contract
• Coordination with the City
• Coordination with Sub-Consultants
2. Project Meetings
• Kick-Off Meeting with IMS and City Staff
• Progress Meeting to Review Data with City Staff
• Progress Meeting to Review Project Budgeting & 5-Year Plan with City Staff
3. Yearly Pavement Management Update
• Update City’s Pavement Management Database
• Gather Most Up to Date Budget Information
• Update Roadway Costs Based on Current Unit Prices
• Finalize 2025 Roadway Program and Get Approval from City Council
4. Data Inventory & Processing
• Perform Surface Condition Assessment on City Maintained Streets (includes 2-passes
on all roads)
• Conduct Pavement Surface Distress Testing including the following:
o Linear Cracking,
o Fatigue Cracking
o Block Cracking
o Rutting
o Raveling
• Distresses Will be Captures by Type, Extent and Severity
• Gather Asset Management Information
o Crosswalks
o Parkway Trees
• Obtain Photographs at 25’ Intervals
• Identify Other Appurtenances and Include General Notes Regarding Items such as
Presence of Curbing and Type of Roadway Surface
5. Data Analysis/Condition Evaluation
• Utilize Road Inspection Pavement Distress Detection to determine PCI Calculation for
Each Street (0-100)
• Perform QC/QA check on all data in comparison to 2019 Pavement Management
Study
• Make Future Condition Projections
• Meet with City Staff to Review Data for Any Discrepancies or Issues
6. Budgeting
• Review Past Road Program Budgets with City Staff
UNITED CITY OF YORKVILLE, IL PAVEMENT MANAGEMENT PROGRAM UPDATE
PAGE 2
• Run Different Budget Scenarios for New 5-Year Plan
• Establish Unit Costs Based on Local Cost Factors and Historical Bid Tabs
• Compute Conceptual Cost Estimates Based on Factors Above
7. Five Year Plan Development
• Compile and Tabulate a Priority Listing of the Maintenance, Rehabilitation or
Reconstruction Request For Each Street in the Program System
• Meet with City Staff to Determine Future Priorities for Rehabilitation Work and
Determine Draft 5-Year Plan
• Develop Draft 5-Year Plan for Repair of the System Streets That Takes Into Account
Different Funding Scenarios
8. Final Memo and Exhibits
• Make Revisions to Draft 5-Year Plan based on Input from City Staff
• Put Together Final 5-Year Plan, Memo and Exhibits for Approval by City Council
• Provide a Presentation to the City Council for Final 5-Year Plan Approval
9. GIS Integration
• Integrate Pavement Inspection Data into City’s GIS Database
• Integrate Paving History and 5-Year Plan into City’s GIS Database
ATTACHMENT C: ESTIMATED LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2413-P
PROJECT TITLE DATE PREPARED BY
Pavement Management Program Update
ROLE PIC PM SPE 1 PE SPT 2 ST ADMIN
PERSON
RATE $246 $210 $186 $168 $175 $140 $72
PRELIMINARY ENGINEERING
1.1 4 12 16 3,504$
1.2 4 4 6 14 2,832$
1.3 2 8 8 16 6 40 7,188$
1.4 2 4 2 4 12 2,002$
1.5 2 6 8 1,428$
1.6 2 6 8 8 24 4,584$
1.7 2 12 8 28 2 6 58 10,394$
1.8 2 12 8 28 2 6 4 62 10,682$
1.9 2 2 8 12 1,806$
Insert Task Subtotal:16 58 32 98 8 30 4 246 44,420$
16 58 32 98 8 30 4 246 44,420
EEI STAFF DIRECT EXPENSES
PIC Principal In Charage Printing/Scanning = 500$
PM Project Manager IMS (Data Collection) = 45,000$
SPE 1 Senior Project Engineer I
PE Project Engineer DIRECT EXPENSES =45,500$
SPT 2 Senior Project Technician II
ST Senior Technician LABOR SUMMARY
ADMIN Adminstrative Assistant EEI Labor Expenses = 44,420$
TOTAL LABOR EXPENSES 44,420$
TOTAL COSTS 89,920$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
PROJECT TOTAL:
CJO4/5/24
COSTTASK
NO.TASK DESCRIPTION HOURS
Project Management and Coordination
Final Memo and Exhibits
GIS Integration
Project Meetings
Yearly Pavement Management Update
Data Inventory and Processing
Data Analysis & Condition Evaluation
Budgeting
Five Year Plan Development
ATTACHMENT D: ESTIMATED SCHEDULE
CLIENT PROJECT NUMBER
United City of Yorkville YO2413-P
PROJECT TITLE DATE PREPARED BY
Pavement Management Program Update CJO
MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
GIS Integration
Final Memo and Exhibits
Project Meetings
Yearly Pavement Management Update
Data Inventory and Processing
Data Analysis & Condition Evaluation
Budgeting
Five Year Plan Development
TASK
NO.TASK DESCRIPTION
4/5/24
Project Management and Coordination
2024 2025
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00 Principal E-3 $241.00 Senior Project Manager E-2 $234.00 Project Manager E-1 $210.00 Senior Project Engineer/Surveyor II P-6 $200.00 Senior Project Engineer/Surveyor I P-5 $186.00 Project Engineer/Surveyor P-4 $168.00 Senior Engineer/Surveyor P-3 $155.00 Engineer/Surveyor P-2 $140.00 Associate Engineer/Surveyor P-1 $127.00 Senior Project Technician II T-6 $175.00 Senior Project Technician I T-5 $164.00 Project Technician T-4 $153.00 Senior Technician T-3 $140.00 Technician T-2 $127.00 Associate Technician T-1 $111.00 GIS Technician II G-2 $125.00 GIS Technician G-I 1 $114.00 Engineering/Land Surveying Intern I-1 $ 82.00 Executive Administrative Assistant A-4 $ 77.00 Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024
ATTACHMENT E
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #6
Tracking Number
PW 2024-36
Kennedy Road and Freedom Place Intersection Improvements
Public Works Committee – April 16, 2024
Consideration of Contract Award
Kennedy Road and Freedom Place Intersection Improvements – Recommendation
of Award
Brad Sanderson Engineering
Name Department
Bids were received, opened and tabulated for work to be done on the Kennedy Road and
Freedom Place Intersection Improvements at 10:00 a.m., April 8, 2024. Representatives of
contractors bidding the project and our firm were in attendance. A tabulation of the bids and the
engineer’s estimate is attached for your information and record. The low bid was below our
Engineer’s Estimate and within the FY2025 budget.
We recommend the acceptance of the bid and approval of award be made to the low bidder, “D”
Construction, Inc., 1488 So. Broadway, Coal City, IL 60416, in the total amount of $567,530.89.
If you have any questions or require additional information, please let us know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Jori Behland, City Clerk
Rob Fredrickson, Finance Director
Date: April 8, 2024
Subject: Kennedy Road and Freedom Place Intersection Improvements
Page 1 of 1
BID TABULATION ENGINEER'S ESTIMATE GENEVA CONSTRUCTION D CONSTRUCTION BUILDERS PAVING, LLC
BIDS RECEIVED 10:00 A.M. 04/08/24 52 Wheeler Road 1350 Aurora Ave 1488 S. Broadway 4413 Roosevelt Road Suite 108
Sugar Grove, IL 60554 Aurora, IL 60505 Coal City, IL 60416 Hillside, IL 60514
TOTAL BID $724,707.65 $592,433.83 $567,530.89 $682,000.88
BID BOND N/A X X X
SIGNED BID N/A X X X
CURRAN CONTRACTING CO.
286 Memorial Court
Crystal Lake, IL 60014
TOTAL BID $684,376.38
BID BOND X
SIGNED BID X
BID SUMMARY
KENNEDY ROAD AND FREEDOM PLACE INTERSECTION IMPROVEMENTS
UNITED CITY OF YORKVILLE
ENGINEERING ENTERPRISES, INC.
52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
BIDS REC'D 4/8/2024
ITEM UNIT UNIT UNIT UNIT UNIT
NO.DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 TREE REMOVAL (OVER 15 UNITS DIAMETER)UNIT 326 26.40$ 8,606.40$ 22.75$ 7,416.50$ 22.75$ 7,416.50$ 24.00$ 7,824.00$ 40.00$ 13,040.00$
2 NITROGEN FERTILIZER NUTRIENT POUND 69 2.20$ 151.80$ 3.00$ 207.00$ 2.00$ 138.00$ 3.00$ 207.00$ 3.00$ 207.00$
3 PHOSPHORUS FERTILIZER NUTRIENT POUND 69 2.20$ 151.80$ 3.00$ 207.00$ 2.00$ 138.00$ 3.00$ 207.00$ 3.00$ 207.00$
4 POTASSIUM FERTILIZER NUTRIENT POUND 69 2.20$ 151.80$ 3.00$ 207.00$ 2.00$ 138.00$ 3.00$ 207.00$ 3.00$ 207.00$
5 EARTH EXCAVATION CU YD 465 40.00$ 18,600.00$ 55.00$ 25,575.00$ 80.00$ 37,200.00$ 85.00$ 39,525.00$ 70.00$ 32,550.00$
6 REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL CU YD 832 40.00$ 33,280.00$ 50.00$ 41,600.00$ 55.00$ 45,760.00$ 40.00$ 33,280.00$ 50.00$ 41,600.00$
7 POROUS GRANULAR EMBANKMENT CU YD 465 50.00$ 23,250.00$ 55.00$ 25,575.00$ 35.00$ 16,275.00$ 60.00$ 27,900.00$ 75.00$ 34,875.00$
8 GEOTECHNICAL FABRIC FOR GROUND STABILIZATION SQ YD 2,046 3.00$ 6,138.00$ 2.00$ 4,092.00$ 2.00$ 4,092.00$ 1.25$ 2,557.50$ 3.00$ 6,138.00$
9 TOPSOIL FURNISH AND PLACE, 8"SQ YD 3,722 12.10$ 45,036.20$ 10.74$ 39,974.28$ 11.00$ 40,942.00$ 6.00$ 22,332.00$ 15.00$ 55,830.00$
10 SEEDING, CLASS 2A ACRE 0.8 2,662.00$ 2,129.60$ 4,500.00$ 3,600.00$ 3,611.00$ 2,888.80$ 4,500.00$ 3,600.00$ 6,000.00$ 4,800.00$
11 EROSION CONTROL BLANKET SQ YD 3,399 2.75$ 9,347.25$ 3.25$ 11,046.75$ 1.50$ 5,098.50$ 3.55$ 12,066.45$ 2.00$ 6,798.00$
12 TURF REINFORCEMENT MAT SQ YD 323 6.60$ 2,131.80$ 8.50$ 2,745.50$ 4.50$ 1,453.50$ 9.00$ 2,907.00$ 15.00$ 4,845.00$
13 TEMPORARY EROSION CONTROL SEEDING POUND 77 11.00$ 847.00$ 3.00$ 231.00$ 6.00$ 462.00$ 3.00$ 231.00$ 6.50$ 500.50$
14 TEMPORARY DITCH CHECKS FOOT 210 19.80$ 4,158.00$ 12.00$ 2,520.00$ 8.00$ 1,680.00$ 12.00$ 2,520.00$ 20.00$ 4,200.00$
15 PERIMETER EROSION BARRIER FOOT 2,435 2.75$ 6,696.25$ 3.00$ 7,305.00$ 2.00$ 4,870.00$ 3.00$ 7,305.00$ 5.00$ 12,175.00$
16 INLET AND PIPE PROTECTION EACH 8 198.00$ 1,584.00$ 210.00$ 1,680.00$ 250.00$ 2,000.00$ 210.00$ 1,680.00$ 275.00$ 2,200.00$
17 AGGREGATE SUBGRADE IMPROVEMENT 12"SQ YD 1,486 17.00$ 25,262.00$ 23.07$ 34,282.02$ 26.00$ 38,636.00$ 35.00$ 52,010.00$ 25.00$ 37,150.00$
18 SUBBASE GRANULAR MATERIAL, TYPE B 6"SQ YD 560 12.00$ 6,720.00$ 12.00$ 6,720.00$ 18.00$ 10,080.00$ 15.00$ 8,400.00$ 11.00$ 6,160.00$
19 HOT-MIX ASPHALT BASE COURSE, 6"SQ YD 1,486 26.00$ 38,636.00$ 38.00$ 56,468.00$ 30.00$ 44,580.00$ 45.00$ 66,870.00$ 55.00$ 81,730.00$
20 BITUMINOUS MATERIALS (TACK COAT)POUND 3,443 0.01$ 34.43$ 0.01$ 34.43$ 0.01$ 34.43$ 0.01$ 34.43$ 0.75$ 2,582.25$
21 LONGITUDINAL JOINT SEALANT FOOT 3,388 7.70$ 26,087.60$ 4.00$ 13,552.00$ 3.75$ 12,705.00$ 3.75$ 12,705.00$ 4.00$ 13,552.00$
22 HOT-MIX ASPHALT SURFACE REMOVAL - BUTT JOINT SQ YD 41 0.01$ 0.41$ 32.00$ 1,312.00$ 35.00$ 1,435.00$ 21.00$ 861.00$ 30.00$ 1,230.00$
23 HOT-MIX ASPHALT BINDER COURSE, IL- 9.5, N50 TON 450 75.00$ 33,750.00$ 100.00$ 45,000.00$ 125.00$ 56,250.00$ 100.00$ 45,000.00$ 80.00$ 36,000.00$
24 HOT-MIX ASPHALT SURFACE COURSE, IL-9.5, MIX "D", N50 TON 520 85.00$ 44,200.00$ 100.00$ 52,000.00$ 140.00$ 72,800.00$ 85.00$ 44,200.00$ 85.00$ 44,200.00$
25 PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH SQ FT 318 20.00$ 6,360.00$ 15.00$ 4,770.00$ 23.00$ 7,314.00$ 23.00$ 7,314.00$ 16.00$ 5,088.00$
26 DETECTABLE WARNINGS SQ FT 48 50.00$ 2,400.00$ 45.00$ 2,160.00$ 40.00$ 1,920.00$ 40.00$ 1,920.00$ 45.00$ 2,160.00$
27 PAVEMENT REMOVAL SQ YD 168 20.00$ 3,360.00$ 20.00$ 3,360.00$ 61.00$ 10,248.00$ 60.00$ 10,080.00$ 40.00$ 6,720.00$
28 DRIVEWAY PAVEMENT REMOVAL SQ YD 278 20.00$ 5,560.00$ 11.35$ 3,155.30$ 12.00$ 3,336.00$ 17.00$ 4,726.00$ 20.00$ 5,560.00$
29 COMBINATION CURB AND GUTTER REMOVAL FOOT 168 10.00$ 1,680.00$ 8.00$ 1,344.00$ 25.00$ 4,200.00$ 16.00$ 2,688.00$ 13.00$ 2,184.00$
30 SIDEWALK REMOVAL SQ FT 301 5.00$ 1,505.00$ 1.50$ 451.50$ 6.00$ 1,806.00$ 3.50$ 1,053.50$ 5.00$ 1,505.00$
31 AGGREGATE SHOULDERS, TYPE B 6"SQ YD 828 9.00$ 7,452.00$ 22.00$ 18,216.00$ 11.50$ 9,522.00$ 17.00$ 14,076.00$ 15.00$ 12,420.00$
32 PIPE CULVERT REMOVAL FOOT 33 20.00$ 660.00$ 43.00$ 1,419.00$ 135.00$ 4,455.00$ 200.00$ 6,600.00$ 40.00$ 1,320.00$
CURRAN CONTRACTING CO.
286 Memorial Court
Crystal Lake, IL 60014Coal City, IL 60416
1488 S. Broadway
Aurora, IL 60505
UNITED CITY OF YORKVILLE
Sugar Grove, IL 60554
BUILDERS PAVING, LLC
4413 Roosevelt Road Suite 108
Hillside, IL 60514
BID TABULATION D CONSTRUCTION
BID TABULATION
KENNEDY ROAD AND FREEDOM PLACE INTERSECTION IMPROVEMENTS
52 Wheeler Road
GENEVA CONSTRUCTION ENGINEER'S ESTIMATE
1350 Aurora Ave
ENGINEERING ENTERPRISES, INC.
52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
BIDS REC'D 4/8/2024
ITEM UNIT UNIT UNIT UNIT UNIT
NO.DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
CURRAN CONTRACTING CO.
286 Memorial Court
Crystal Lake, IL 60014Coal City, IL 60416
1488 S. Broadway
Aurora, IL 60505
UNITED CITY OF YORKVILLE
Sugar Grove, IL 60554
BUILDERS PAVING, LLC
4413 Roosevelt Road Suite 108
Hillside, IL 60514
BID TABULATION D CONSTRUCTION
BID TABULATION
KENNEDY ROAD AND FREEDOM PLACE INTERSECTION IMPROVEMENTS
52 Wheeler Road
GENEVA CONSTRUCTION ENGINEER'S ESTIMATE
1350 Aurora Ave
33 PRECAST REINFORCED CONCRETE FLARED END SECTIONS 12"EACH 1 2,000.00$ 2,000.00$ 1,795.00$ 1,795.00$ 2,700.00$ 2,700.00$ 4,000.00$ 4,000.00$ 1,500.00$ 1,500.00$
34 STORM SEWERS, CLASS A, TYPE 1 12"FOOT 495 80.00$ 39,600.00$ 97.00$ 48,015.00$ 47.00$ 23,265.00$ 70.00$ 34,650.00$ 90.00$ 44,550.00$
35 STORM SEWERS, CLASS B, TYPE 1 6"FOOT 20 100.00$ 2,000.00$ 51.00$ 1,020.00$ 115.00$ 2,300.00$ 170.00$ 3,400.00$ 75.00$ 1,500.00$
36 CONCRETE HEADWALLS FOR PIPE DRAINS EACH 1 500.00$ 500.00$ 560.00$ 560.00$ 1,100.00$ 1,100.00$ 1,650.00$ 1,650.00$ 800.00$ 800.00$
37 MANHOLES, TYPE A, 4'-DIAMETER, TYPE 1 FRAME, OPEN LID EACH 1 4,000.00$ 4,000.00$ 3,315.00$ 3,315.00$ 8,500.00$ 8,500.00$ 13,000.00$ 13,000.00$ 7,500.00$ 7,500.00$
38 INLETS, TYPE A, TYPE 8 GRATE EACH 3 2,000.00$ 6,000.00$ 2,406.00$ 7,218.00$ 2,100.00$ 6,300.00$ 3,100.00$ 9,300.00$ 2,000.00$ 6,000.00$
39 INLETS TO BE ADJUSTED EACH 2 1,000.00$ 2,000.00$ 636.00$ 1,272.00$ 1,050.00$ 2,100.00$ 1,555.00$ 3,110.00$ 1,200.00$ 2,400.00$
40 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 FOOT 198 40.00$ 7,920.00$ 50.00$ 9,900.00$ 60.00$ 11,880.00$ 58.65$ 11,612.70$ 55.00$ 10,890.00$
41 SHORT TERM PAVEMENT MARKING FOOT 1,156 0.01$ 11.56$ 1.15$ 1,329.40$ 1.00$ 1,156.00$ 0.35$ 404.60$ 1.00$ 1,156.00$
42 SHORT TERM PAVEMENT MARKING REMOVAL SQ FT 249 0.01$ 2.49$ 1.75$ 435.75$ 5.00$ 1,245.00$ 2.50$ 622.50$ 4.00$ 996.00$
43 TEMPORARY PAVEMENT MARKING - LINE 4"- PAINT FOOT 2,190 0.01$ 21.90$ 0.50$ 1,095.00$ 0.85$ 1,861.50$ 0.10$ 219.00$ 1.75$ 3,832.50$
44 THERMOPLASTIC PAVEMENT MARKING - LETTERS AND SYMBOLS SQ FT 78 5.50$ 429.00$ 6.00$ 468.00$ 5.00$ 390.00$ 5.00$ 390.00$ 6.50$ 507.00$
45 THERMOPLASTIC PAVEMENT MARKING - LINE 4"FOOT 6,129 1.00$ 6,129.00$ 1.00$ 6,129.00$ 0.90$ 5,516.10$ 0.90$ 5,516.10$ 1.60$ 9,806.40$
46 THERMOPLASTIC PAVEMENT MARKING - LINE 6" FOOT 473 1.22$ 577.06$ 1.50$ 709.50$ 1.10$ 520.30$ 1.10$ 520.30$ 2.50$ 1,182.50$
47 THERMOPLASTIC PAVEMENT MARKING - LINE 12" FOOT 831 3.30$ 2,742.30$ 3.00$ 2,493.00$ 3.00$ 2,493.00$ 3.00$ 2,493.00$ 3.50$ 2,908.50$
48 THERMOPLASTIC PAVEMENT MARKING - LINE 24"FOOT 22 6.60$ 145.20$ 6.00$ 132.00$ 6.00$ 132.00$ 6.00$ 132.00$ 6.00$ 132.00$
49 REMOVE EXISTING FLARED END SECTION EACH 1 1,000.00$ 1,000.00$ 295.00$ 295.00$ 710.00$ 710.00$ 1,050.00$ 1,050.00$ 400.00$ 400.00$
50 BIKE PATH REMOVAL SQ YD 571 20.00$ 11,420.00$ 6.00$ 3,426.00$ 17.50$ 9,992.50$ 8.50$ 4,853.50$ 15.00$ 8,565.00$
51 TRIAXIAL GEOGRID REINFORCEMENT, TYPE I SQ YD 1,486 8.00$ 11,888.00$ 7.65$ 11,367.90$ 5.00$ 7,430.00$ 3.00$ 4,458.00$ 6.00$ 8,916.00$
52 PARTIAL DEPTH PATCHING (SPECIAL)SQ YD 150 100.00$ 15,000.00$ 70.50$ 10,575.00$ 65.00$ 9,750.00$ 85.00$ 12,750.00$ 85.00$ 12,750.00$
53 EXPLORATION TRENCH, SPECIAL FOOT 100 50.00$ 5,000.00$ 25.00$ 2,500.00$ 100.00$ 10,000.00$ 50.00$ 5,000.00$ 80.00$ 8,000.00$
54 TEMPORARY ACCESS (COMMERCIAL ENTRANCE)EACH 2 500.00$ 1,000.00$ 400.00$ 800.00$ 250.00$ 500.00$ 555.00$ 1,110.00$ 1,200.00$ 2,400.00$
55 TEMPORARY ACCESS (ROAD)EACH 1 1,000.00$ 1,000.00$ 300.00$ 300.00$ 500.00$ 500.00$ 775.00$ 775.00$ 1,500.00$ 1,500.00$
56 HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH SQ YD 3,612 5.42$ 19,577.04$ 6.00$ 21,672.00$ 5.50$ 19,866.00$ 4.15$ 14,989.80$ 6.00$ 21,672.00$
57 TRAFFIC CONTROL AND PROTECTION, (SPECIAL)L SUM 1 30,000.00$ 30,000.00$ 8,000.00$ 8,000.00$ 74,830.75$ 74,830.75$ 80,000.00$ 80,000.00$ 50,000.00$ 50,000.00$
57 TEMPORARY PAVEMENT MARKING REMOVAL SQ FT 730 5.00$ 3,650.00$ 1.50$ 1,095.00$ 1.00$ 730.00$ 0.10$ 73.00$ 2.00$ 1,460.00$
58 RELOCATE SIGN PANEL AND POST EACH 5 200.00$ 1,000.00$ 260.00$ 1,300.00$ 200.00$ 1,000.00$ 150.00$ 750.00$ 400.00$ 2,000.00$
59 ALLOWANCE - ITEMS ORDERED BY THE ENGINEER UNIT 20,000 1.00$ 20,000.00$ 1.00$ 20,000.00$ 1.00$ 20,000.00$ 1.00$ 20,000.00$ 1.00$ 20,000.00$
60 HOT-MIX ASPHALT DRIVEWAY PAVEMENT, 2"SQ YD 233 30.00$ 6,990.00$ 30.00$ 6,990.00$ 23.00$ 5,359.00$ 20.00$ 4,660.00$ 50.00$ 11,650.00$
TOTAL BID (Items 1 - 60) 567,530.89$ 592,433.83$ 682,000.88$ 684,376.38$ 724,707.65$
% BELOW/ABOVE ENGINEER'S ESTIMATE -21.69%-18.25%-5.89%-5.57%
ENGINEERING ENTERPRISES, INC.
52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #7
Tracking Number
PW 2024-37
Kennedy Rd. & Freedom Pl. – Construction Engineering Agreement
Public Works Committee – April 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
A proposed Construction Engineering Agreement for the Kennedy Road and Freedom
Place intersection improvements.
Background
A tentative agreement has been reached with Blackberry Oaks which may be in front of
the council on April 23rd, and bids have been opened and will soon be awarded. With the
passage of this construction engineering agreement, we will have our items in place to be able to
get this project completed in a timely manner.
The agreement is structured as an hourly rate with an estimated cost of $88,621. This
money is included in the approved FY25 budget in the City-Wide Capital fund.
Recommendation
Staff recommends approval of the construction engineering agreement with EEI for the
Kennedy Road and Freedom Place Intersection Improvements.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: April 11, 2024
Subject: Kennedy and Freedom Pl. Construction Engineering Agreement
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 1
Kennedy Road & Freedom Place Intersection Improvements
United City of Yorkville
Professional Services Agreement – Construction Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
ENGINEER agrees to furnish to the City the following services: The ENGINEER
shall provide any and all necessary engineering services to the City as indicated
on the Scope of Services (Attachment B). Construction Engineering for all
roadways indicated on Attachment E will be provided. Engineering will be in
accordance with all City and Illinois Department of Transportation requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the
Contractor shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to Contractor:
ENGINEER shall receive as compensation for all work and services to be
performed herein, an amount based on the Estimated Level of Effort and
Associated Cost included in Attachment C. Construction Engineering will be paid
for as an Hourly Rate in the amount of $88,621. The hourly rates for this project
are shown in the attached 2024 Standard Schedule of Charges (Attachment F).
All payments will be made according to the Illinois State Prompt Payment Act and
not less than once every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
written notice of any change in the rates specified in Section C hereof (or on any
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 2
E. Ownership of Records and Documents:
Contractor agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. Contractor agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the freedom of information act or
if already previously disclosed by a third party. Upon termination of this agreement,
Contractor agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by Contractor without contractors
consent. Modifications of any signed duplicate original document not authorized
by ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kendall County, Illinois.
G. Independent Contractor:
Contractor shall have sole control over the manner and means of providing the
work and services performed under this agreement. The City’s relationship to the
Contractor under this agreement shall be that of an independent contractor.
Contractor will not be considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The Contractor certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to
perform the service.
Anti-Bribery: The Contractor certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or
admission of bribery or attempted bribery of an officer or employee of the State of
Illinois or any other state.
Loan Default: If the Contractor is an individual, the Contractor certifies that he/she
is not in default for a period of six months or more in an amount of $600 or more
on the repayment of any educational loan guaranteed by the Illinois State
Scholarship Commission made by an Illinois institution of higher education or any
other loan made from public funds for the purpose of financing higher education (5
ILCS 385/3).
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 3
Felony Certification: The Contractor certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The Contractor certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720
Illinois Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The Contractor certifies that it is in compliance with the
Drug Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective
date of this contract. The Drug Free Workplace Act requires, in part, that
Contractors, with 25 or more employees certify and agree to take steps to ensure
a drug free workplace by informing employees of the dangers of drug abuse, of
the availability of any treatment or assistance program, of prohibited activities and
of sanctions that will be imposed for violations; and that individuals with contracts
certify that they will not engage in the manufacture, distribution, dispensation,
possession, or use of a controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
Contractor agrees to comply with applicable provisions of the Illinois Human
Rights Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the
Americans with Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the
rules applicable to each. The equal opportunity clause of Section 750.10 of the
Illinois Department of Human Rights Rules is specifically incorporated herein. The
Contractor shall comply with Executive Order 11246, entitled Equal Employment
Opportunity, as amended by Executive Order 11375, and as supplemented by U.S.
Department of Labor regulations (41 C.F.R. Chapter 60). The Contractor agrees
to incorporate this clause into all subcontracts under this Contract.
International Boycott: The Contractor certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979
or the regulations of the U.S. Department of Commerce promulgated under that
Act (30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires
the Contractor (and any subcontractors) to maintain, for a period of 3 years after
the later of the date of completion of this Contract or the date of final payment
under the Contract, all books and records relating to the performance of the
Contract and necessary to support amounts charged to the City under the
Contract. The Contract and all books and records related to the Contract shall be
available for review and audit by the City and the Illinois Auditor General. If this
Contract is funded from contract/grant funds provided by the U.S. Government,
the Contract, books, and records shall be available for review and audit by the
Comptroller General of the U.S. and/or the Inspector General of the federal
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 4
sponsoring agency. The Contractor agrees to cooperate fully with any audit and to
provide full access to all relevant materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The Contractor certifies that
he/she is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien
The Internal Revenue Service requires that taxes be withheld on payments made
to non resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the Contractor certifies that
its Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
Contractor shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on
account of damage to or destruction of property resulting from the performance of
work under this agreement by Contractor or its Subcontractors, or due to or arising
in any manner from the wrongful act or negligence of Contractor or its
Subcontractors of any employee of any of them. In the event that the either party
shall bring any suit, cause of action or counterclaim against the other party, the
non-prevailing party shall pay to the prevailing party the cost and expenses
incurred to answer and/or defend such action, including reasonable attorney fees
and court costs. In no event shall the either party indemnify any other party for the
consequences of that party’s negligence, including failure to follow the
ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of
the types of services rendered hereunder. (Not applicable as having been
previously supplied)
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 5
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed
by both parties. In the event that any provisions of this agreement shall be held to
be invalid or unenforceable, the remaining provisions shall be valid and binding on
the parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimate of Level of Effort and Associated Cost
Attachment D: Estimated Schedule
Attachment E: Location Map
Attachment F: 2024 Standard Schedule of Charges
UNITED CITY OF YORKVILLE KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 6
L. Notices:
All notices required to be given under the terms of this agreement shall be given
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time to time substitute addresses
or persons in connection with required notices.
Agreed to this _____day of __________________, 2024.
United City of Yorkville: Engineering Enterprises, Inc.:
___________________________ __________________________
John Purcell Brad Sanderson, PE
Mayor Chief Operating Officer / President
___________________________ __________________________
Jori Behland Angie Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. ATTACHMENT A – APRIL 2024
PAGE 1
STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furnish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction documents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provision of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinion
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in electronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at the
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations.
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
ENGINEERING ENTERPRISES, INC. ATTACHMENT A – APRIL 2024
PAGE 2
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have incurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warranty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a) Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b) Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c) Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d) Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against the ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to carry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions being taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting such force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of invoices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of the
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonable fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
UNITED CITY OF YORKVILLE, IL KENNEDY ROAD AND FREEDOM PLACE INTERSECTION IMPROVEMENTS
PAGE 1
Kennedy Road and Freedom Place Intersection Improvements
United City of Yorkville, IL
Professional Services Agreement - Construction Engineering
Attachment B – Scope of Services
The United City of Yorkville intends to widen and resurface Kennedy Road at Freedom Place.
Our proposed scope of services for Construction Engineering will include the following:
3.1 Construction Administration
• Prepare for, Attend and Facilitate the Preconstruction Meeting with the Contractor Including
Preparation of Meeting Minutes
• Shop Drawing Review
• Coordinate with City Services (Garbage, Mail, Etc.)
• Review Engineering Plans, Specifications and Prepare Field Book
• Prepare/Verify Pay Estimates and Change Orders
• Gather Invoices and Waivers of Lien
• Provide Weekly Updates to City or as Required Based on Onsite Activities
3.2 Construction Layout and Record Drawings
• Stake Proposed Storm Sewer, Roadway Excavation and Widening
• Perform Post Construction Field Survey for Record Drawings
• Prepare and Review Record Drawings
3.3 Construction Observation and Documentation
• Review Construction Layout
• Take Pre-Construction Videos and Photos of Pre-Existing Conditions
• Provide Resident Engineering Services for Construction
• Monitor Adherence to Specifications
• Monitor Adherence to Construction Schedule and Make Recommendations When
Appropriate.
• Monitor Traffic Control on a Regular Basis.
• Coordinate Any Required Testing on Behalf of the City and Review Test Reports
• Provide Daily Quantity Tracking, Documentation and Daily Field Reports
• Perform Punch Walks, Prepare Punch List Letters and Provide Follow Up Inspections and
Recommend Acceptance When Appropriate (2 Each)
• Prepare project Closeout Paperwork
The following scope of services will be provided by EEI’s Subconsultant:
Rubino Engineering – Material Testing for Quality Assurance
ATTACHMENT C: ESTIMATED LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2219-P
PROJECT TITLE DATE PREPARED BY
Kennedy Road and Freedom Place Intersection Improvements
ROLE PIC SPM PM SPE 1 SPT 2 SPT 1 ADMIN
PERSON
RATE $246 $234 $210 $186 $175 $164 $72
CONSTRUCTION ENGINEERING
3.1 2 4 10 2 18 3,672$
3.2 2 4 8 16 16 46 8,220$
3.3 8 372 2 382 71,016$
Insert Task Subtotal:2 6 22 380 16 16 4 446 82,908$
2 6 22 380 16 16 4 446 82,908
EEI STAFF DIRECT EXPENSES
PIC Principal In Charge Printing/Scanning = -$
SPM Senior Project Manager Rubino (Material Testing) = 2,788$
PM Project Manager Vehicle Charges ($65/day) = 2,925$
SPE 1 Senior Project Engineer I DIRECT EXPENSES =5,713$
SPT T 2 Senior Project Technician II
SPT 1 Senior Project Technician II LABOR SUMMARY
ADMIN Adminstrative Assistant EEI Labor Expenses = 82,908$
TOTAL LABOR EXPENSES 82,908$
TOTAL COSTS 88,621$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
PROJECT TOTAL:
CJO4/3/24
COSTTASK
NO.TASK DESCRIPTION HOURS
Contract Administration
Construction Layout and Record Drawings
Observation and Documentation
ATTACHMENT D: ESTIMATED SCHEDULECLIENT PROJECT NUMBERUnited City of Yorkville YO2210-PPROJECT TITLEDATE PREPARED BYKennedy Road and Freedom Place Intersection Improvements CJOAPR MAYJUN JULAUG SEP OCT NOVCONSTRUCTION ENGINEERING3.13.23.3 52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.comObservation and DocumentationConstruction LayoutTASK NO.TASK DESCRIPTION4/3/242024Contract Administration
GrandeConstit
uti
o
n
J
e
t
e
r
FreedomKennedy
Engineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
www.eeiweb.com
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
JUNE 2022
YO2219
H:\GIS\PUBLIC\ELGIN\2022\
MJT ³ATTACHMENT E KENNEDY ROAD & FREEDOM PLACE INTERSECTION IMPROVEMENTS LOCATION MAP
YO2219_Kennedy Road & Freedom Place Intersection Improvements
Service Layer Credits:
400 0 400200 Feet
PROJECT LIMITS
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00 Principal E-3 $241.00 Senior Project Manager E-2 $234.00 Project Manager E-1 $210.00 Senior Project Engineer/Surveyor II P-6 $200.00 Senior Project Engineer/Surveyor I P-5 $186.00 Project Engineer/Surveyor P-4 $168.00 Senior Engineer/Surveyor P-3 $155.00 Engineer/Surveyor P-2 $140.00 Associate Engineer/Surveyor P-1 $127.00 Senior Project Technician II T-6 $175.00 Senior Project Technician I T-5 $164.00 Project Technician T-4 $153.00 Senior Technician T-3 $140.00 Technician T-2 $127.00 Associate Technician T-1 $111.00 GIS Technician II G-2 $125.00 GIS Technician I G-1 $114.00 Engineering/Land Surveying Intern I-1 $ 82.00 Executive Administrative Assistant A-4 $ 77.00 Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024
ATTACHMENT F
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #8
Tracking Number
PW 2024-38
Supplemental MFT Resolution for Bulk Rock Salt
Public Works Committee – April 16, 2024
Majority
Approval
Annual resolution appropriating MFT funds for the purchase of bulk rock salt
Eric Dhuse Public Works
Name Department
Summary
Staff is brining forward the required forms to purchase bulk rock salt using MFT funds.
Background
Each year we participate in the bulk rock salt purchasing program through the State of
Illinois using MFT funds. The program opens in March of each year, but we won’t learn the
winning bidder or price until late October of this year.
In the meantime, we need to formally approve anticipated spending of MFT funds
through a resolution (attached) and submit the Maintenance Expenditure Statement which tracks
our fund usage. Once this is completed and approved by IDOT, we will be allowed to use MFT
funds to purchase bulk rock salt for the upcoming snow removal season.
Our bid for this year was for 1600 tons of salt. The program we selected allows us to
purchase a minimum of 80% (1280 tons) up to 120% (1920 tons) under the contract price. I
have asked to appropriate $190,000 for salt purchase this year. This amount is the total amount
that is in the approved FY 25 budget. This is a conservative number and I do not expect to spend
all the funds. This past year the salt bid came in at $79.22 per ton and I have budgeted upwards
of $100/per ton to be safe. If we do not use the funds, it will return to our MFT fund as an
unencumber amount of money that can be used on other approved projects.
Recommendation
I recommend the approval of the IDOT resolution for maintenance to allow the City to
purchase bulk rock salt using MFT funds.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: April 8, 2024
Subject: MFT Resolution for Salt Purchase
Resolution for Maintenance
Under the Illinois Highway Code
BLR 14220 (Rev. 12/13/22)Completed04/09/24
District
3
County
Kendall
Resolution Number Resolution Type
Supplemental
Section Number
25-00000-00-GM
BE IT RESOLVED, by the
Governing Body Type
Council of the
Local Public Agency Type
City of
Name of Local Public Agency
Yorkville Illinois that there is hereby appropriated the sum of
DollarsOne Hundred Ninety Thousand Dollars () $190,000.00
of Motor Fuel Tax funds for the purpose of maintaining streets and highways under the applicable provisions of Illinois Highway Code from
Beginning Date
05/01/24 to
Ending Date
04/30/25 .
BE IT FURTHER RESOLVED, that only those operations as listed and described on the approved Estimate of Maintenance Costs,
including supplemental or revised estimates approved in connection with this resolution, are eligible for maintenance with Motor Fuel Tax
funds during the period as specified above.
BE IT FURTHER RESOLVED, that
Local Public Agency Type
City of
Name of Local Public Agency
Yorkville
shall submit within three months after the end of the maintenance period as stated above, to the Department of Transportation, on forms
available from the Department, a certified statement showing expenditures and the balances remaining in the funds authorized for
expenditure by the Department under this appropriation, and
BE IT FURTHER RESOLVED, that the Clerk is hereby directed to transmit four (4) certified originals of this resolution to the district office
of the Department of Transportation.
I
Name of Clerk
Jori Behland
Local Public Agency Type
City Clerk in and for said
Local Public Agency Type
City
of
Name of Local Public Agency
Yorkville in the State of Illinois, and keeper of the records and files thereof, as
provided by statute, do hereby certify the foregoing to be a true, perfect and complete copy of a resolution adopted by the
Governing Body Type
Council of
Name of Local Public Agency
Yorkville at a meeting held on
Date
.
IN TESTIMONY WHEREOF, I have hereunto set my hand and seal this
Day
day of
Month, Year
.
(SEAL, if required by the LPA) Clerk Signature & Date
APPROVED
Regional Engineer Signature & Date
Department of Transportation
Instructions for BLR 14220
BLR 14220 (Rev. 12/13/22)Completed04/09/24
This form shall be used when a Local Public Agency (LPA) wants to perform maintenance operations using Motor Fuel Tax (MFT) funds.
Refer to Chapter 14 of the Bureau of Local Roads and Streets Manual (BLRS Manual) for more detailed information. This form is to be
used by a Municipality or a County. Road Districts will use BLR 14221. For signature requirements refer to Chapter 2, Section 3.05(b) of
the BLRS Manual.
When filling out this form electronically, once a field is initially completed, fields requiring the same information will be auto-populated.
Resolution Number Insert the resolution number as assigned by the LPA, if applicable.
Resolution Type From the drop down box, choose the type of resolution:
-Original would be used when passing a resolution for the first time for this project.
-Supplemental would be used when passing a resolution increasing appropriation above
previously passed resolutions.
-Amended would be used when a previously passed resolution is being amended.
Section Number Insert the section number of the improvement covered by the resolution.
Governing Body Type From the drop down box choose the type of administrative body. Choose Board for County; Council or
President and Board of Trustees for a City, Village or Town.
LPA Type From the drop down box choose the LPA body type; County, City, Town or Village.
Name of LPA Insert the name of the LPA.
Resolution Amount Insert the dollar value of the resolution for maintenance to be paid for with MFT funds in words,
followed by the same amount in numerical format in the ().
Beginning Date Insert the beginning date of the maintenance period. Maintenance periods must be a 12 or 24 month
consecutive period.
Ending Date Insert the ending date of the maintenance period.
LPA Type From the drop down box choose the LPA body type; County, City, Town or Village.
Name of LPA Insert the name of the LPA.
Name of Clerk Insert the name of the LPA Clerk.
LPA Type From the drop down box choose the LPA body type; County, City, Town or Village.
LPA Type From the drop down box choose the LPA body type; County, City, Town or Village.
Name of LPA Insert the name of the LPA.
Governing Body Type From the drop down box choose the type of administrative body. Choose Board for County; Council or
President and Board of Trustees for a City, Village or Town.
Name of LPA Insert the name of the LPA.
Date Insert the date of the meeting.
Day Insert the day the Clerk signed the document.
Month, Year Insert the month and year of the clerk's signature.
Clerk Signature Clerk shall sign here.
Seal The Clerk shall seal the document here, if required. If a seal is required, electronic signatures should
not be used.
Approved The Department of Transportation representative shall sign and date here upon approval.
A minimum of three (3) certified signed originals must be submitted to the Regional Engineer's District office OR email PDF
completed form with electronic signatures to your local District LRS office.
Following IDOT's approval, distribution will be as follows:
Local Public Agency Clerk
Engineer (Municipal, Consultant or County)
BLR 14222 (Rev. 05/26/23)
Local Public Agency General Maintenance
Page 1 of 2Completed04/09/24
Submittal Type Supplemental Estimate of Maintenance Costs
District
3
Estimate of Cost For
Municipality
Maintenance Period
Local Public Agency
City of Yorkville
County
Kendall
Section Number
25-00000-00-GM
Beginning
05/01/24
Ending
04/30/25
Maintenance Items
Maintenance
Operation
Maint Eng
Category
Insp.
Req.
Material Categories/
Point of Delivery or
Work Performed by
an Outside Contractor Unit Quantity Unit Cost Cost
Total
Maintenance
Operation
Cost
Snow Removal IIA TON 1,900 $100.00 $190,000.00 $190,000.00
Total Operation Cost $190,000.00
Estimate of Maintenance Costs Summary
Maintenance MFT Funds RBI Funds Other Funds Estimated Costs
Local Public Agency Labor
Local Public Agency Equipment
Materials/Contracts(Non Bid Items)
Materials/Deliver & Install/Materials Quotations (Bid Items)
Formal Contract (Bid Items)
Maintenance Total
Estimated Maintenance Eng Costs Summary
Maintenance Engineering MFT Funds RBI Funds Other Funds Total Est Costs
Preliminary Engineering
Engineering Inspection
Material Testing
Advertising
Bridge Inspection Engineering
Maintenance Engineering Total
Total Estimated Maintenance
Remarks
SUBMITTED
Local Public Agency Official Signature & Date
Title
APPROVED
Regional Engineer Signature & Date
Department of TransportationCounty Engineer/Superintendent of Highways Signature & Date
BLR 14222 (Rev. 05/26/23)Page 2 of 2Completed04/09/24
Estimate of Maintenance Costs Submittal Type Supplemental
Local Public Agency
City of Yorkville
County
Kendall
Section
25-00000-00-GM
Maintenance Period
Beginning
05/01/24
Ending
04/30/25
IDOT Department Use Only
Received Location
Received Date Additional Location?
WMFT Entry By Entry Date
BLR 14222 (Rev. 05/26/23)Completed04/09/24
Instructions for BLR 14222 - Page 1 of 4
NOTE: Form instructions should not be included when the form is submitted
This form is used by all Local Public Agencies (LPAs) to submit their maintenance program and also submit their maintenance expenditure statements. A
resolution (BLR 14220) must be submitted and approved by the Illinois Department of Transportation (IDOT) prior to incurring any expenditures. For items
required to be bid the estimate of cost must be submitted prior to submittal of required bidding documents. Authorizations will be made based on the
resolution and/or the approved contract/acceptance/material quotations documents.
The maintenance expenditure statement must be submitted within 3 months of the end of the maintenance period. Maintenance resolutions and estimates
submitted for future maintenance periods after that date will not be processed until the delinquent maintenance expenditure statement has been submitted.
Only one form needs to be completed per maintenance period, combine all operations on one form.
For additional information refer to the Bureau of Local Roads Manual (BLRS), Chapter 14. For signature requirements refer to Chapter 2, section 3.05(b) of
the BLRS Manual.
For items being completed for the estimate all materials, equipment, labor and contract amounts are considered estimates. For estimates where LPA
equipment is completed, an Equipment Rental Schedule (BLR 12110) must also be submitted for approval. When completing the form for the Maintenance
Expenditure all items must be actual amounts spent.
Maintenance — From the drop down choose which type of document is being submitted. Choose Estimate of Cost if an estimate is being
submitted, choose Maintenance Expenditure Statement if a maintenance expenditure statement is being submitted
Submittal — Choose the type of submittal, if this is the first submittal choose original, if revising a previous submittal choose, revised. If adding to
a previous submittal choose supplemental.
Estimate of Cost For — Select the type of LPA submitting this form from the drop down. Types to choose are County, Municipality, or Road
District/Township.
Local Public Agency — Insert the name of the Local Public Agency.
County — Insert the County in which the Local Public Agency is located.
Maintenance Period
Beginning — Insert the beginning date of the maintenance period.
Ending — Insert the ending date of the maintenance period.
Section — Insert the section number assigned to this project. The letters at the end of the section number will always be a "GM".
Maintenance Operations — List each maintenance operation separately
Maintenance Eng. Category — From the drop down choose the maintenance engineering category as it applies to the operation listed
to the left. The definitions of the categories can be found in the BLRS Manual Chapter 14, section 14-2.04
Maintenance Engineering Categories are:
Category I — Services purchased without a proposal such as electric energy or materials purchased from Central Management
Services' Joint Purchasing Program or another joint purchasing program that has been approved by the District BLRS or CBLRS.
Category II-A — Maintenance items that are not included in Maintenance Engineering Category I or do not require competitive sealed
bids according to Section 12-1.02(a) or a local ordinance/resolution.
Category II-B — Routine maintenance items that require competitive sealed bids according to Section12-1.02(a) or a local ordinance/
resolution. Routine maintenance includes all items in the following work categories: snow removal, street sweeping, lighting and traffic
signal maintenance, cleaning ditches or drainage structures, tree trimming or removal, mowing, crack sealing, pavement marking,
shoulder maintenance limited amounts of concrete curb and gutter repair, scour mitigation, pavement patching, and minor drainage
repairs.
Category III — Maintenance items that are not covered by Maintenance Engineering Category I or Category II-B and require
competitive bidding with a material proposal, a deliver and install proposal or material quotation.
Category IV — Maintenance items that are not covered by Maintenance Engineering Category I or Category II-B and require
competitive bidding with a formal contract proposal.
BLR 14222 (Rev. 05/26/23)Completed04/09/24
Instructions for BLR 14222 - Page 2 of 4
The instructions listed below only apply to the maintenance estimate of cost. For LPA's using Local Public Agency Labor and/or Local Public Agency
Equipment Rental, the estimated amounts are only listed on those specific lines and are not to be included with each operation on the estimate of cost.
Insp Req — From the drop down choose No or Yes as it applies to the maintenance operation listed to the left. Items requiring no engineering
inspection should be no.
Material Categories/Point of Delivery or Work Performed by an Outside Contractor — List the items for each operation on a separate line,
grouping items for the same operation together, for the operation listed to the left. If work being done as a contract list work by contractor.
Unit — Insert the unit of measure for the material listed to the left, if applicable.
Quantity — Insert the quantity for the material listed to the left, if applicable.
Unit Cost — Insert the unit cost of the material listed to the left, if applicable.
Cost — No entry necessary, this is a calculated field. This is the quantity times the unit cost.
Total Maintenance Operation Cost — Insert the total of the Maintenance Operation Cost, for items done by a contract insert the
estimated contract amount.
Maintenance
Estimate of Maintenance Costs Summary — Under each item listed below, list the amount of estimated MFT funds, Rebuild Illinois (RBI) funds
and local funds to be expended, if applicable. The total Estimated cost is a calculated field.
Local Public Agency Labor — Insert the estimated amount for LPA labor for all maintenance operations, if applicable.
Local Public Agency Equipment Rental — Insert the estimated amount for LPA equipment rental for all maintenance operations, if applicable.
Materials/Contracts (Non Bid Items) — Insert the estimated amount for materials and/or contracts for items the LPA is not required to bid, if
applicable.
Materials/Deliver & Install, Material Quotations — For the operation listed to the left insert the estimate amount to be expended using a bidding
process for material/deliver & install proposal and/or material quotations, if applicable.
Formal Contracts — Insert the total amount estimated to be expended on formal contracts. This will be for items required to be bid.
Total Estimated Cost — This is a calculated field and will be automatically filled in for each type. This is the sum of all funding for the item.
Total Maintenance Operation Cost — This is a calculated field, no entry is necessary. This is the sum of all items estimated to be expended on
this operation.
Total Maintenance Cost — This is a calculated field, no entry is necessary. This is the sum of all maintenance operation costs.
Maintenance Engineering Cost Summary — For each item listed below, list under the funding type what the estimated amount to be expended for
each item.
Preliminary Engineering Fee — Insert the amount of funds estimated to be expended for Preliminary Engineering, if applicable.
Engineering Inspection Fee — Insert the amount of funds estimated to be expended for Engineering Inspection, if applicable.
Material Testing Costs — Insert the dollar amount of funds estimated to be expended on material testing costs, if applicable.
BLR 14222 (Rev. 05/26/23)Completed04/09/24
Instructions for BLR 14222 - Page 3 of 4
Advertising Costs — Insert the amount of funds estimated to be expended on advertising costs, if applicable.
Bridge Inspection Costs — Insert the amount of funds estimated to be expended on bridge inspection costs, if applicable.
Total Maintenance Engineering — This is a calculated field, no entry is necessary. This is the sum of all maintenance engineering costs listed
above.
Totals — This is a calculated field. It is the total of the estimated maintenance cost plus the estimated
maintenance engineering cost.
These instructions apply to the Maintenance Expenditure Statement.
Maintenance Operation — Type in the name of the maintenance operation for which the amounts to the right will be completed. For a form that
was completed as an Estimate of Cost and is now being changed to a Maintenance Expenditure Statement, this field will be completed from the
estimate.
Maint Eng Category — From the drop down select the Maintenance Engineering Category that applies to the operation listed to the left.
LPA Labor — For the operation listed to the left insert the amount expended for LPA labor, if applicable.
LPA Equipment Rental — For the operation listed to the left insert the amount expended on LPA equipment rental if applicable.
Materials/Contracts (Non-Bid) — For the operation listed to the left insert the amount expended for materials and/or contracts that was not
required to be bid, if applicable.
Materials/Deliver & Install/Material Quotations (Bid Items) — Insert the total amount expended on Materials Proposals, Deliver and Install
proposals, Materials Quotations (Bid Items). This will be for items that were required to be bid.
Formal Contract — For the operation listed to the left insert the amount expended for items bid using the formal contract process, if applicable.
Total Operation Cost — This is a calculated field, it will sum the amounts expended for the operation listed to the left.
Operation Engineering Inspection Fee — For the operation listed to the left insert the amount of engineering inspection charged for this operation,
if applicable.
Total Maintenance — This is a calculated field, no entry necessary. It is the sum of all maintenance operations.
Maintenance Engineering Cost Summary Preliminary Engineering Fee — Insert the dollar amount of funds spent on preliminary engineering for
this maintenance section.
Engineering Inspection Fee — Insert the amount of funds expended for Engineering Inspection, if applicable.
Material Testing Costs — Insert the dollar amount of funds spent on material testing costs, if applicable.
Advertising Costs — Insert the dollar amount of funds spent on advertising costs, if applicable.
Bridge Inspection Costs — Insert the dollar amount of funds spent on bridge inspection costs, if applicable.
Total Maintenance Engineering — This is a calculated field, no entry is necessary. This is the sum of all maintenance engineering costs listed
above.
Total Maintenance Program Costs — Insert the total cost of the Maintenance and Maint. Engineering. The maintenance amount will be the
amount from the Total Cost from the Maintenance Items table. The Maint. Eng will be the Maintenance Engineering Total from above.
BLR 14222 (Rev. 05/26/23)Completed04/09/24
Instructions for BLR 14222 - Page 4 of 4
Contributions, Refunds, Paid with Other Funds — Enter the dollar amount of contributions, refunds or amounts paid with other funds for this
maintenance section, if applicable, for both maintenance and maintenance engineering.
Total Motor Fuel Tax/Rebuild Illinois Portion — These are calculated fields, no entry is necessary. This is the sum of the total cost minus the
amount paid with local funds.
Motor Fuel Tax Portion — Insert the amount of the total cost that was paid for with Motor Fuel Tax funds for Maintenance and Maint. Engineering,
as applicable.
Motor Fuel Tax Funds Authorized — Insert the net amount of Motor Fuel Tax Funds authorized for each type.
Motor Fuel Tax Surplus/Deficit — These are calculated fields, no entry is necessary. This is the sum of the Total Motor Fuel Tax funds expended
minus the amount of Motor Fuel Tax funds authorized. A positive number will result in a credit to the unobligated fund of the Motor Fuel Tax fund.
A negative number means more funds were spent than authorized. If the negative number has a resolution to cover the overage, the item(s) that
resulted in the overage have been approved by IDOT, and are covered in the overrun policy, this amount will be authorized. If these conditions
are not met you must contact your District office for guidance.
Rebuild Illinois Portion — Insert the amount of the total cost that was paid for with Rebuild Illinois funds for Maintenance and Maint. Engineering,
as applicable.
Rebuild Illinois Funds Authorized — Insert the net amount of Rebuild Illinois Funds authorized for each type.
Rebuild Illinois Surplus/Deficit — These are calculated fields, no entry is necessary. This is the sum of the Total Rebuild Illinois funds expended
minus the amount of Rebuild Illinois funds authorized. A positive number will result in a credit to the unobligated fund of the Motor Fuel Tax fund.
A negative number means more funds were spent than authorized. If the negative number has a resolution to cover the overage, the item(s) that
resulted in the overage have been approved by IDOT, and are covered in the overrun policy, this amount will be authorized. If these conditions
are not met you must contact your District office for guidance.
Difference — No entry necessary, this field is automatically calculated. It is the difference between Total Motor Fuel Tax/Rebuild Illinois Portion
for Maintenance and Maint. Engineering. The fields must equal zero; if not, review the amounts inserted under Motor Fuel Tax and Rebuild
Illinois need to be corrected.
Remarks — Enter remarks as applicable covering the items entered.
Certification — Upon submittal of this form as the maintenance expenditure statement the LPA official shall check this box as certification.
End of instructions for Maintenance Expenditure Statement
Submitted
Local Public Agency Official — The proper official shall sign, insert their title and date here. For Estimates of Cost covering a Township/Road
District the road commissioner shall sign and date as Local Public Agency Official. For Municipalities the municipal official shall sign and date
here.
County Engineer/Superintendent of Highways — For County project and/or Township/Road District projects the county engineer/superintendent
of highways shall sign here.
Approved — Upon approval the Regional Engineer shall sign and date here. This approval is subject to change based upon a documentation
review by the Department.
When submitting the form via USPS mail, submit a minimum of three (3) signed original must be submitted to the Regional Engineer's District office. This
form may be submitted electronically with electronic signatures.
Following the Regional Engineer's approval, distribution will be as follows:
Local Public Agency Clerk
Engineer (Consultant or County Engineer)
District File
IDOT Department Use Only The Following fields are for IDOT use only.
Received
Location Enter the location received from the drop down.
Date Enter the date the document was received.
WMFT Entry
By Enter the name of the person entering the information into the WMFT system.
Date Enter the date on which the information was entered.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Staff is looking for feedback.
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #9
Tracking Number
PW 2024-39
Oak Street Parking Restriction
Public Works Committee – April 16, 2024
None
Informational
Please see the attached memo.
Erin Willrett Administration
Name Department
Memorandum
To: Public Works Committee
From: Erin Willrett, Assistant City Administrator
CC: Bart Olson, City Administrator
Date: April 16, 2024
Subject: Oak Street Parking Restriction
Summary
Discussion of a proposal to direct staff to notify residents of a proposal to enact parking
restrictions on Oak Street.
Background
Alderman Corneils received a complaint that there have been parking issues on Oak
Street (near Cannonball Trail). From initial reports, it appears that employees or customers of
the industrial building to the north of Oak Street are parking on Oak St, preventing free flow of
traffic. Alderman Corneils does not have a specific parking restriction proposal (i.e. one side vs.
both sides) at this time.
The City only has jurisdiction on Oak Street from Cannonball Trail to approximately
mid-block to the east. Please see the red shaded area on the attached map. Further east is
controlled by Bristol Township. Please see the green shaded area on the attached map.
The City Council has historically followed this process for implementing parking
restrictions:
1) A committee reviews the request and makes a recommendation to proceed as outlined
below
a. This can occur during this meeting. Feedback would need to be provided on
whether the parking restriction to be considered is one side of the street or both
sides of the street.
2) The City Council approves the recommendation of the committee to proceed
a. This could occur at the April 23, 2024 City Council meeting
3) The staff send mailers to all homes adjacent to the proposed parking restriction inviting
them to provide written comment or attend a future committee meeting
a. If approved, we would send these letters out by the end of April for the PW
committee meeting on May 21, 2024.
4) The committee reviews public comment on the parking restriction
a. If approved, we propose the May 21, 2024 PW committee meeting
5) The City Council reviews the committee recommendation and takes final action on the
proposed parking restriction
a. If approved, we propose the May 28, 2024 City Council meeting
Recommendation
Staff is looking for feedback regarding initiating the parking restriction process along the
portion of Oak Street that the City has control of and asks the City Council to direct staff to send
resident mailers for a potential May Public Works committee meeting.
O a k S t r e e tCannonballTrail
CrossStreetO a k S t r e e t
CrossStreet003
001
003
004
002
007
Oak Street
Map data from OpenStreetMap
4/11/2024, 11:50:19 AM
0 0.01 0.020.01 mi
0 0.02 0.040.01 km
1:1,048
Kendall County GIS
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Staff is looking for feedback.
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #10
Tracking Number
PW 2024-40
Tuscany Trail Parking Restriction
Public Works Committee – April 16, 2024
None
Informational
Please see the attached memo.
Erin Willrett Administration
Name Department
Memorandum
To: Public Works Committee
From: Erin Willrett, Assistant City Administrator
CC: Bart Olson, City Administrator
Date: April 16, 2024
Subject: Tuscany Trail Parking Restriction
Summary
Discussion of a proposal to direct staff to notify residents of a proposal to enact parking
restrictions on Tuscany Trail.
Background
Alderman Corneils received neighborhood resident complaints that there will be parking
issues, once the cricket stadium is built near this subdivision. The Police have gotten a few
complaints of overnight parking along this roadway in recent months. Despite Tuscany Trail
being a no-load street, it has been observed that there is an Oswego resident parking along the
Yorkville curve approaching the Oswego boundary overnight. Oswego prohibits overnight
parking and Yorkville does not.
In other locations of the City, parking restrictions have been placed on the interior radius
of the curve. On the attached map, the highlighted area is approximately 675 feet of restriction
from the Yorkville City limits along the interior radius of the curve. Allowing parking in this
area may lead to a sight line issue if there was more traffic along this roadway because of the
stadium. The City could also restrict the area south or west of the curve as well.
The City Council has historically followed this process for implementing parking
restrictions:
1) A committee reviews the request and makes a recommendation to proceed as outlined
below
a. This can occur during this meeting. Feedback would need to be provided on
whether the parking restriction should be considered.
2) The City Council approves the recommendation of the committee to proceed
a. This could occur at the April 23, 2024, City Council meeting.
3) The staff send mailers to all homes adjacent to the proposed parking restriction inviting
them to provide written comment or attend a future committee meeting.
a. If approved, we would send these letters out by the end of April for the PW
committee meeting on May 21, 2024.
4) The committee reviews public comment on the parking restriction
a. If approved, we propose the May 21, 2024, PW committee meeting.
5) The City Council reviews the committee recommendation and takes final action on the
proposed parking restriction.
a. If approved, we propose the May 28, 2024, City Council meeting.
Recommendation
Staff is looking for feedback regarding initiating the parking restriction process along the
Tuscany Trail and asks the City Council to direct staff to send resident mailers for a potential
May Public Works committee meeting.
E a s tM illb r o o k Circle
GainsCourt
TuscanyTrailEastMillbrookCircleWest Millbr ook Cir c l e ConcordDriveSouthGrapeVineTrailC
o
n
c
ord
Driv
e
S
o
uth
Tuscany TrailEastMillbrookCircle
GrapeVineTrailGrapeVineTrail001
001
003
Tuscany Trail Restriction
Map data from OpenStreetMap
4/11/2024, 1:29:04 PM
0 0.06 0.110.03 mi
0 0.09 0.180.04 km
1:4,514
Kendall County GIS
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
Old Business #1
Tracking Number
PW 2023-84
Proposed Rt 47 Improvements
Public Works Committee – April 16, 2024
PW – 11/21/23
A discussion took place at the 11/21/23
PW meeting.
PW 2023-84
None
Informational
Brad Sanderson Engineering
Name Department
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Rob Fredrickson, Finance Director
Jori Behland, City Clerk
Date: April 4, 2024
Subject: Rt 47 Improvements
This memo is to provide an update on the materials presented at the November 2023 Public
Works Committee Meeting. At the time, there was a request to provide more detail on the
proposed medians for all three proposed Rt 47 Improvement projects.
The three proposed projects are as follows:
Rt 47 – Water Park Way to Jericho
Rt 47 – Carpenter to Water Park Way
Rt 47 – Caton Farm Road to Rt 71
Attached are the pre-final plans that IDOT has provided the City for the projects noted above.
The proposed grassed medians have been highlighted in green.
Median design is based on the IDOT Design Manual which governs the design of all IDOT
highway features. In general, the following items are taken into account during the design
process:
Access needs, design speeds, availability of right-of-way, safety, capacity, intersection
spacing, traffic signals and intersection design.
Raised medians near the intersections generally narrow to 8-10’ wide and are planned to
be concrete in the IDOT projects on the north side of the City. Grassed medians in these
areas are generally discouraged due to worker safety concerns.
Grassed medians are provided on the project south of Rt 71, south of Ament Road. It
appears that right-of-way and access issues may have governed the median design north
of Ament Road.