Public Works Packet 2024 07-16-24
AGENDA
PUBLIC WORKS COMMITTEE MEETING
Tuesday, July 16, 2024
6:00 p.m.
East Conference Room #337
651 Prairie Pointe Drive, Yorkville, IL
Citizen Comments:
Minutes for Correction/Approval: June 18, 2024
New Business:
1. PW 2024-53 Capital Improvement Projects Update
2. PW 2024-54 Quarterly Bond and Letter of Credit Reduction Summary
3. PW 2024-55 Heartland Meadows – One Year Maintenance Guarantee Release
4. PW 2024-56 Windett Ridge Unit 2 – Consideration of Acceptance
5. PW 2024-57 Timber Ridge Estates Water Main Extension – Plat of Easement
6. PW 2024-58 2024 Local Road Program – Change Order No. 1 (Faxon Road)
7. PW 2024-59 2023 Water Main Replacement – Contract A – Change Order No. 2 (Final Balancing)
8. PW 2024-60 Water Audit Update
9. PW 2024-61 Route 126 Water Main Improvements – Design Engineering Agreement
10. PW 2024-62 Lake Michigan South Receiving Station Standpipe – Design Engineering Agreement
11. PW 2024-63 Northwest Elevated Water Storage Tank – Design Engineering Agreement
12. PW 2024-64 YBSD Water Main Extension – Contract Award
13. PW 2024-65 YBSD Water Main Extension – Construction Engineering Agreement
Old Business:
Additional Business:
United City of Yorkville
651 Prairie Pointe Drive
Yorkville, Illinois 60560
Telephone: 630-553-4350
www.yorkville.il.us
UNITED CITY OF YORKVILLE
WORKSHEET
PUBLIC WORKS COMMITTEE
Tuesday, July 16, 2024
6:00 PM
CITY HALL CONFERENCE ROOM
---------------------------------------------------------------------------------------------------------------------------------------
CITIZEN COMMENTS:
---------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------
MINUTES FOR CORRECTION/APPROVAL:
---------------------------------------------------------------------------------------------------------------------------------------
1. June 18, 2024
□ Approved __________
□ As presented
□ With corrections
---------------------------------------------------------------------------------------------------------------------------------------
NEW BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
1. PW 2024-53 Capital Improvement Projects Update
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
2. PW 2024-54 Quarterly Bond and Letter of Credit Reduction Summary
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
3. PW 2024-55 Heartland Meadows – One Year Maintenance Guarantee Release
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
4. PW 2024-56 Windett Ridge Unit 2 – Consideration of Acceptance
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
5. PW 2024-57 Timber Ridge Estates Water Main Extension – Plat of Easement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
6. PW 2024-58 2024 Local Road Program – Change Order No. 1 (Faxon Road)
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
7. PW 2024-59 2023 Water Main Replacement – Contract A – Change Order No. 2 (Final Balancing)
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
8. PW 2024-60 Water Audit Update
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
9. PW 2024-61 Route 126 Water Main Improvements – Design Engineering Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
10. PW 2024-62 Lake Michigan South Receiving Station Standpipe – Design Engineering Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
11. PW 2024-63 Northwest Elevated Water Storage Tank – Design Engineering Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
12. PW 2024-64 YBSD Water Main Extension – Contract Award
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
13. PW 2024-65 YBSD Water Main Extension – Construction Engineering Agreement
□ Moved forward to CC __________
□ Approved by Committee __________
□ Bring back to Committee __________
□ Informational Item
□ Notes ___________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------
ADDITIONAL BUSINESS:
---------------------------------------------------------------------------------------------------------------------------------------
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
Minutes
Tracking Number
Minutes of the Public Works Committee – June 18, 2024
Public Works Committee – July 16, 2024
Majority
Committee Approval
Minute Taker
Name Department
DRAFT
Page 1 of 2
UNITED CITY OF YORKVILLE
PUBLIC WORKS COMMITTEE
Tuesday, June 18, 2024, 6:00pm
Yorkville City Hall, East Conference Room #337
651 Prairie Pointe Drive, Yorkville, IL
IN ATTENDANCE:
Committee Members
Chairman Ken Koch Alderman Rusty Corneils
Alderman Craig Soling Alderman Matt Marek via Zoom
Other City Officials
Assistant City Administrator Erin Willrett Public Works Director Eric Dhuse
Engineer Brad Sanderson, EEI
Other Guests: None
The meeting was called to order at 6:00pm by Chairman Ken Koch.
Citizen Comments: None
Previous Meeting Minutes: May 21, 2024
The minutes were approved as presented on a unanimous voice vote.
New Business:
1. PW 2024-47 2023 Water Main Replacement Contract B – Balancing Change Order No. 2
Mr. Sanderson said this is the final balancing Change Order for the second project from last year. The contractor
and city agreed on the quantities which resulted in an increase of $86,000 for Contract A, still below budget.
Additional curb and gutter needed replacing and adjustments were made to connections along with additional
restoration. He recommended approval and this will move to the consent agenda.
2. PW 2024-48 Corneils Road Interceptor Sewer – Balancing Change Order No. 3
This project was thought to be done a year ago, but it was discovered a quantity was not accounted for. This is
an increase but, still less than contract value. Mr. Sanderson recommended approval and the committee agreed,
moving it to the consent agenda.
3. PW 2024-49 Public Works Equipment and Truck Purchase
a. Purchase of a Trackless MT7 Utility Tractor
b. Purchase of a 2024 Ford F-350
Mr. Dhuse said the Trackless utility tractor is an engine with a cab allowing various attachments to be added. He
said this unit is used equipment and will be used for mowing, snow removal and loading leaves, etc. He said it
is equivalent to getting 5 tractors in one. It is budgeted and the price is about $12,000 less than budget. It can
also be used on snow removal on the bridge and is easier to maneuver in the downtown or on trails. This will
move to the Council regular agenda.
Three quotes were obtained for the 1-ton truck and the price was $56,221 at Haggerty Ford in West Chicago. It
is under budget and will be able to be used for snowplowing later. The committee was OK with this and it
moves to the Council regular agenda.
Page 2 of 2
4. PW 2024-50 Resolution Approving an Intergovernmental Agreement Between the United City of Yorkville
and Yorkville-Bristol Sanitary District
Director Dhuse said this is for water main down Center St., through Jaycee Park, under the creek and under
River Rd. to arrive at the YBSD expansion. The city is asking YBSD to oversize this and the city will incur
costs of $93,072. He said the city is waiting for one more approval from the Army Corps of Engineers. Mr.
Sanderson said they are working with Army Corps and bids were taken, but none will be awarded until the
permitting is resolved. This will be brought back to the July Public Works meeting, but the committee did
approve the agreement.
5. PW 2024-51 Lake Michigan South Receiving Station – Design Engineering Agreement
6. PW 2024-52 Lake Michigan North Receiving Station – Design Engineering Agreement
Mr. Dhuse said the cost of the south station is $269,743, slightly more than the north station and includes the
survey work. A professional acquisition person will assist and insure it is eligible for the WIFIA program. It is
located at Restore Church and a design will be needed to meet the deadlines. The north side receiving station is
expected to be near Bright Farms. Mr. Sanderson said steps need to be taken to acquire land and do the design
work and he said DWC is also pushing for the work to be done. At the July Public Works meeting, the tanks will
be discussed and there will be a separate contract for them. The committee discussed the style of water towers
and costs and Mr. Sanderson explained the mechanics behind the globe-type vs. the stand pipe. Mr. Dhuse noted
that the north side receiving station funding is through the SRF (State Revolving Fund) rather than WIFIA. The
city must have this bid by the end of this year to use the SRF money. These items move to the regular agenda.
Old Business: None
Additional Business:
Alderman Corneils asked about the sealcoating machine purchased last year and if there is a schedule of work.
Mr. Dhuse said work will be done in July and August and the schedule will be provided. Trails in Raintree and
Windett Ridge will be done after some patchwork. He listed other work that has already been done.
In response to an earlier query by Chairman Koch, a draft summary of Lake Michigan water project costs was
provided. Mr. Koch asked about money spent on fixing leaks and if it was in the report. He suggested it might
be appropriate to discuss this report at the Administration Committee meeting.
There was no further business and the meeting adjourned at 6:25pm.
Minutes respectfully transcribed by
Marlys Young, Minute Taker
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #1
Tracking Number
PW 2024-53
Capital Project Update
Public Works Committee – July 16, 2024
None
Informational
A status update on projects will be given.
Brad Sanderson Engineering
Name Department
The purpose of this memo is to update the Public Works Committee as to the status of the several
projects. A summary of the status of the projects is provided below:
Construction Projects
2024 Water Main Replacement Program – Contract A
Construction is underway and estimated to be 40% complete. The contract completion date is November
8th.
2024 Water Main Replacement Program – Contract B
Construction is substantially complete. The contract completion date is July 31st.
Well 10 Raw Water Main
Construction is underway and estimated to be 80% complete. The contract substantial completion date is
August 10th with a final of October 15th.
Well 10
The contract has been awarded. Work is expected to begin in October. The contract completion date is
April 2025.
2024 RTBR
Construction is underway and estimated to be 50% complete. The contract substantial completion date is
July 26th with a final of September 27th.
2024 Local Road Program
A preconstruction meeting will be scheduled soon. The contract completion date is October 18th.
Planning/Design Projects
WIFIA Loan Application
The application is complete.
YBSD/Center Street Water Main
Contract award is pending permit approval.
Rt 47 Water Main Replacement – Water Park Way to Jericho
Design engineering has begun and is approximately 95% complete.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: July 3, 2024
Subject: Capital Improvement Projects Update
Well No. 7 Electrical
Design engineering has commenced. We are anticipating an August letting.
Eldamain Water Main Loop
Design engineering has commenced. Easement acquisition is in process.
Southern Sanitary Sewer Connection
Design engineering has commenced. Easement acquisition is in process.
Corneils Sanitary Sewer
Design engineering has commenced. Easement acquisition is in process.
2025 Water Main Replacement
Design engineering has commenced.
LM – North Receiving Station
Design engineering has commenced.
LM – South Receiving Station
Design engineering has commenced.
LM – Bluestem Water Main Improvements
Design engineering has commenced.
Kennedy / Freedom Place Intersection Improvements
Contract award is pending final land acquisition.
Van Emmon Street STP
Design engineering has begun and is approximately 90% complete. We are targeting a September letting.
Pavement Management Update
The field acquisition of data is complete.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #2
Tracking Number
PW 2024-54
Bond/LOC Reduction Summary Through June 30, 2024
Public Works Committee – July 16, 2024
None
Informational
Brad Sanderson Engineering
Name Department
Please see the attached reduction summary through June 30, 2024. If you have any questions,
please let me know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: July 3, 2024
Subject: 2024 Bond/LOC Reduction Summary
30-Jun-24
2024 Bond and Letter of Credit Reduction Report
Date Development/Project
Engineer
Concurrence
City Administrator
Concurrence
Mayor
Concurrence Reduction Final Release Reduction Value Remaining Balance
1/4/2024 Bristol Bay Unit 10 X X X 1,935,804.50$ 486,992.50$
1/4/2024 Bristol Bay Unit 12 X X X 737,852.00$ 217,451.80$
1/25/2024 Grande Reserve Units 13, 14 and 23 Sidewalk X X X 26,120.00$ 18,760.00$
2/27/2024 Ashley Road Improvements X X X 48,401.17$ -$
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #3
Tracking Number
PW 2024-55
Heartland Meadows – Performance Guarantee Release
Public Works Committee – July 16, 2024
Majority
Consideration of Approval
Release of Guarantee
Brad Sanderson Engineering
Name Department
The developer has completed the remaining punchlist items from the one-year warranty period
and we are now recommending a full release of their remaining performance guarantee provided
in the form of a collateral account. The value of the guarantee to be released is $133,399.30. The
public improvements were accepted on May 23, 2023.
The developer will provide a separate guarantee to cover the costs of the remaining sidewalk
within the undeveloped four lots. That guarantee will be released after completion of all
sidewalks.
The full guarantee of $133,399.30 should not be released until the sidewalk security is in place.
Please let us know if you have any questions.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: June 20, 2024
Subject: Heartland Meadows
()-()-()-PARK
WALNUT
JACKSONBRIDGE
ELM
LIBERTYBRISTOLALEXANDRA FREEMONT720
711
607
713
715
111
803
805
910
702
608
708
201
906
804
204
205
204
208
205
206
920
924
928
207
208
302
304
301
1065
306
1063
304
303
1061
307
308
1051
306
1047
307
901
1043
310
603
308
401
804
804
402
788
401
905
801
803
805
807
809
811840
838
836
834
832
830
828
826824822820818816814
813
811
809
807
805
803
801812
810
808
806
802
800
800 841
839
837
835
833
831
802
804
806
808
810
Engineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
HEARTLAND MEADOWS
LOCATION MAP
www.eeiweb.com DATE
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
JUNE 2024
YO1343
YO1343_Heartland_Meadows_Location_Map.MXD
H:\GIS\PUBLIC\YORKVILLE\2013\
MJT
NO.REVISIONS ³United City of Yorkville
651 Prairie Pointe Drive,
Yorkville, IL 60560
630-553-4350www.yorkville.il.us
UNITED CITY OF YORKVILLE
KENDALL COUNTY, ILLINOIS
Legend
Heartland Meadows Boundary
Roadway Acceptance
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #4
Tracking Number
PW 2024-56
Windett Ridge – Unit 2 – One Year Maintenance Guarantee Release
Public Works Committee – July 16, 2024
Majority
Consideration of Approval
Subdivision Acceptance Consideration
Brad Sanderson Engineering
Name Department
The developer has requested that the City accept the public improvements for ownership and
maintenance. All work related to the public improvements, including punch list work, has been
completed.
We recommend that the public improvements (water main, sanitary sewer, storm sewer, paving,
sidewalk, street lighting and parkway trees) as described in the attached Bill of Sale be accepted
for ownership and maintenance by the City.
As required by City Code, the developer will be responsible to provide a performance guarantee
to cover the one-year maintenance period. This period starts after the City formally accepts the
improvements.
Original EOPC Value $955,991.45
10% of Original EOPC $95,599.15
Required Value $95,599.15
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: July 16, 2024
Subject: Windett Ridge – Unit 2
1
BILL OF SALE
Seller, _______________, in consideration of One and 00/100th Dollar ($1.00), receipt
hereby acknowledged, does hereby sell, assign, transfer and convey to the Buyer, the United City
of Yorkville, an Illinois municipal corporation, at 651 Prairie Pointe Drive, Yorkville, Illinois
60560, the following personal property to wit described in Exhibit A attached hereto for the
development know as Windett Ridge – Unit 2 and generally shown on Exhibit B.
Seller hereby represents and warrants to Buyer that Seller is the absolute owner of said
property, that said property is free and clear of all liens, charges and encumbrances, and that
Seller has full right, power, and authority to sell said property and to make this Bill of Sale.
IN WITNESS WHEREOF, Seller has signed and sealed this Bill of Sale at
___________________________________, this _____ day of _______________, 20__.
_______________________
Signature of Seller
Name:
Title:
Subscribed and Sworn to
before me this _____ day
of _____________, 20__.
_______________________
Notary Public
EXHIBIT A
WINDETT RIDGE - UNIT 2
UNITED CITY OF YORKVILLE
UNIT QUANTITIY
UNIT QUANTITY
EACH 3 FOOT 700
EACH 9
FOOT 12
LUMP SUM 1
LUMP SUM 1
FOOT 675
EACH 1
EACH 1
CUBIC YARD 660
EACH 9
EACH 3
FOOT 695
EACH 1
EACH 1
EACH 1
CUBIC YARD 715
EACH 12
FOOT 120
FOOT 310
FOOT 495
FOOT 45
FOOT 30
EACH 1
EACH 1
EACH 1
EACH 2
EACH 3
EACH 2
EACH 1
EACH 2
FOOT 230
FOOT 165
FOOT 55
FOOT 600
EACH 1
EACH 3
EACH 5
FOOT 85
SQ FT 7495
EACH 2
5' WIDE - 5" PCC SIDEWALK W/ 4" AGGREGATE
DEMOLITION - EXISTING 18" RCP
SANITARY LIFT STATION
SANITARY LIFT STATION SITE WORK & INSTALLATION
4" FORCE MAIN, DIP
CORE & CONNECT TO EXISTING SANITARY MANHOLE
8" DUCTILE IRON WATER MAIN, CLASS 52
RECONSTRUCT EXISTING VAULT WITH 16"X8" VALVE
16"X8" PRESSURE CONNECTION WITH VALVE VAULT
RELOCATE EXISTING FIRE HYDRANT
18" RCP
24" RCP
15" RCP FLARED END SECTION W/ GRATE
18" RCP FLARED END SECTION W/ GRATE
UTILITIES
SANITARY SEWER CONSTRUCTION
6" SANITARY SERVICE COMPLETE - NEAR
6" SANITARY SERVICE COMPLETE - FAR
8" PVC SANITARY SEWER (SDR 26)
ROADWAY
WINDETT RIDGE ROAD
STREET LIGHTING
STREET LIGHT STANDARD, COMPLETE
48" MANHOLE W/ FRAME AND LID
48" CATCH BASIN W/ FRAME & GRATE
CORE & CONNECT FORCEMAIN TO EXISTING SAN. MH
TRENCH BACKFILL
1-1/2" TYPE K COPPER SERVICE, NEAR
6" PVC
15" RCP
4" SUMP PUMP CONNECTION
CORE & CONNECT EXISTING MANHOLE
DEMOLITION - EXISTING 24" RCP
24" RCP FLARED END SECTION W/ GRATE
24" INLET TYPE A W/ FRAME & GRATE
1-1/2" TYPE K COPPER SERVICE, FAR
TRENCH BACKFILL (CA-7)
SIDEWALK
TRENCH BACKFILL (CA-7)
RECONSTRUCT EXISTING MANHOLES
12" RCP
OUTLET CONTROL STRUCTURE
DEMOLITION - EXISTING 24" MANHOLE
DEMOLITION - EXISTING 12" RCP
DEMOLITION - EXISTING 6" PVC
DEMOLITION - EXISTING 48" MANHOLE
WATER MAIN CONSTRUCTION
STORM SEWER CONSTRUCTION
EXHIBIT A
WINDETT RIDGE - UNIT 2
UNITED CITY OF YORKVILLE
LUMP SUM 1
LUMP SUM 1
LUMP SUM 1
LUMP SUM 1
NATURALIZED AREAS
PARKWAY PLANTINGS
TREES
LANDSCAPE PLANTINGS
MISCELLANEOUS
Ca
u
l
f
i
e
l
d
P
t
Wi
n
d
e
t
t
R
i
d
g
e
R
d
Kentshire DrCounty of Will, Maxar, Microsoft
Engineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700 / www.eeiweb.con
WINDETT RIDGE
LOCATION MAP
DATE:JUNE 2024United City of Yorkville
651 Prairie Pointe Dr.
Yorkville, IL 60560
(630) 553-4350
http://www.yorkville.il.us
WINDETT RIDGE UNIT 2
UNITED CITY OF YORKVILLE
KENDALL COUNTY, ILLINOIS
CONSULTING ENGINEERS
NO.DATE REVISIONS
PROJECT NO.:
YO1802
PATH:
H:/GIS/PUBLIC/YORKVILLE/2018/
FILE:
fffää
N O R T H
Legend
Unit 2 Boundary
H:\GIS\Public\Yorkville\2018\YO1802\YO1802- Windett Ridge Unit 2\YO1802- Windett Ridge Unit 2.aprx
160 0 16080 Feet
GASB
WINDETT RIDGE - UNIT 2
UNITED CITY OF YORKVILLE
UNIT QUANTITIY UNIT PRICE COST
EACH 3 850.00$ 2,550.00$
EACH 9 1,750.00$ 15,750.00$
FOOT 12 30.00$ 360.00$
LUMP SUM 1 185,000.00$ 185,000.00$
LUMP SUM 1 185,000.00$ 185,000.00$
FOOT 675 35.00$ 23,625.00$
EACH 1 4,000.00$ 4,000.00$
EACH 1 4,000.00$ 4,000.00$
CUBIC YARD 660 35.00$ 23,100.00$
EACH 9 1,286.00$ 11,574.00$
EACH 3 2,500.00$ 7,500.00$
FOOT 695 56.40$ 39,198.00$
EACH 1 5,580.00$ 5,580.00$
EACH 1 14,000.00$ 14,000.00$
EACH 1 750.00$ 750.00$
CUBIC YARD 715 35.00$ 25,025.00$
EACH 12 350.00$ 4,200.00$
FOOT 120 25.00$ 3,000.00$
FOOT 310 27.00$ 8,370.00$
FOOT 495 30.00$ 14,850.00$
FOOT 45 35.00$ 1,575.00$
FOOT 30 45.00$ 1,350.00$
EACH 1 1,625.00$ 1,625.00$
EACH 1 2,250.00$ 2,250.00$
EACH 1 2,500.00$ 2,500.00$
EACH 2 1,200.00$ 2,400.00$
EACH 3 1,900.00$ 5,700.00$
EACH 2 2,500.00$ 5,000.00$
EACH 1 8,500.00$ 8,500.00$
EACH 2 2,500.00$ 5,000.00$
FOOT 230 12.50$ 2,875.00$
FOOT 165 12.00$ 1,980.00$
FOOT 55 10.75$ 591.25$
FOOT 600 4.00$ 2,400.00$
EACH 1 650.00$ 650.00$
EACH 3 500.00$ 1,500.00$
EACH 5 1,250.00$ 6,250.00$
FOOT 85 35.00$ 2,975.00$
SQ FT 7495 8.00$ 59,960.00$
TRENCH BACKFILL
SANITARY LIFT STATION SITE WORK & INSTALLATION
4" FORCE MAIN, DIP
CORE & CONNECT TO EXISTING SANITARY MANHOLE
SANITARY LIFT STATION
8" DUCTILE IRON WATER MAIN, CLASS 52
DEMOLITION - EXISTING 6" PVC
DEMOLITION - EXISTING 48" MANHOLE
DEMOLITION - EXISTING 24" MANHOLE
RECONSTRUCT EXISTING MANHOLES
DEMOLITION - EXISTING 12" RCP
48" CATCH BASIN W/ FRAME & GRATE
TRENCH BACKFILL (CA-7)
15" RCP
15" RCP FLARED END SECTION W/ GRATE
18" RCP FLARED END SECTION W/ GRATE
24" RCP FLARED END SECTION W/ GRATE
24" INLET TYPE A W/ FRAME & GRATE
48" MANHOLE W/ FRAME AND LID
16"X8" PRESSURE CONNECTION WITH VALVE VAULT
RELOCATE EXISTING FIRE HYDRANT
RECONSTRUCT EXISTING VAULT WITH 16"X8" VALVE
TRENCH BACKFILL (CA-7)
6" PVC
5' WIDE - 5" PCC SIDEWALK W/ 4" AGGREGATE
UTILITIES
SANITARY SEWER CONSTRUCTION
18" RCP
24" RCP
CORE & CONNECT EXISTING MANHOLE
DEMOLITION - EXISTING 18" RCP
SIDEWALK
STORM SEWER CONSTRUCTION
WATER MAIN CONSTRUCTION
4" SUMP PUMP CONNECTION
6" SANITARY SERVICE COMPLETE - NEAR
6" SANITARY SERVICE COMPLETE - FAR
8" PVC SANITARY SEWER (SDR 26)
CORE & CONNECT FORCEMAIN TO EXISTING SAN. MH
1-1/2" TYPE K COPPER SERVICE, NEAR
1-1/2" TYPE K COPPER SERVICE, FAR
12" RCP
OUTLET CONTROL STRUCTURE
DEMOLITION - EXISTING 24" RCP
GASB
WINDETT RIDGE - UNIT 2
UNITED CITY OF YORKVILLE
EACH 2 7,500.00$ 15,000.00$
LUMP SUM 1 20,482.60$ 20,482.60$
LUMP SUM 1 32,210.00$ 32,210.00$
LUMP SUM 1 9,785.60$ 9,785.60$
LUMP SUM 1 5,250.00$ 5,250.00$
TOTAL COST 712,763.25$
UNIT QUANTITY UNIT PRICE COST
FOOT 700 133.21$ 93,250.00$
TOTAL 700 TOTAL COST 93,250.00$
LANDSCAPE PLANTINGS
NATURALIZED AREAS
PARKWAY PLANTINGS
ROADWAY
WINDETT RIDGE ROAD
STREET LIGHTING
STREET LIGHT STANDARD, COMPLETE INCLUDING
WIRE & TRENCHING, ETC
MISCELLANEOUS
TREES
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #5
Tracking Number
PW 2024-57
Timber Ridge Estates – Water Main Easement
Public Works Committee – July 16, 2024
Majority
Consideration of Acceptance
Consideration of Acceptance
Brad Sanderson Engineering
Name Department
Attached are easement documents necessary for the construction of the off-site water main for
the Timber Ridge Estates development. We recommend that the City consider approving and
accepting the easement.
If you have any questions, let me know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: July 3, 2024
Subject: Timber Ridge Estates – Water Main Easement
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/gov_officials.php
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #6
Tracking Number
PW 2024-58
2024 Local Road Program – Change Order No. 1 (Faxon Road)
Public Works Committee – July 16, 2024
Majority
Consideration of Approval
Consideration of Change Order No. 1
Brad Sanderson Engineering
Name Department
The purpose of this memo is to present Change Order No. 1 for the above referenced project.
A Change Order, as defined by in the General Conditions of the Contract Documents, is a written order to
the Contractor authorizing an addition, deletion or revision in the work within the general scope of the
Contract Documents, or authorizing an adjustment in the Contract Price or Contract Time.
Background:
The City awarded the work for the above-referenced contract to Builders Paving, LLC in the amount of
$3,162,000.00. The project is currently in contracting.
Questions Presented:
Should the City approve Change Order No. 1 which would increase the contract value by $596,828.00?
Discussion:
The change order would increase the contract value to $3,758,836.00.
The City is potentially receiving funds to complete the improvements on Faxon Road from High Ridge
Lane to Twinleaf Trail.
We are recommending approval of the change order contingent upon receipt of the funds noted above.
Action Required:
Consideration of approval of Change Order No. 1.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Erin Willrett, Assistant City Administrator
Rob Fredrickson, Finance Director
Jori Behland, City Clerk
Date: June 24, 2024
Subject: 2024 Local Road Program
L:\Agendas - Packets\Packets\2024 Packets\Public Works\07-16-24\Local Road Program Change Order\3 - Change Order 1 -
Faxon Road Additional Paving.doc
CHANGE ORDER
Order No. 1
Date: June 24, 2024
Agreement Date: N/A
NAME OF PROJECT: 2024 Local Road Program
OWNER: United City of Yorkville
CONTRACTOR: Builders Paving, LLC
The following changes are hereby made to the CONTRACT DOCUMENTS:
1) Addition of Faxon Road Resurfacing
$596,828.00
Change of CONTRACT PRICE:
Original CONTRACT PRICE: $ 3,162,008.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER(S) $ 3,162,008.00
The CONTRACT PRICE due to this CHANGE ORDER will be (increased)(decreased) by:
$ _596,828.00
The new CONTRACT PRICE including this CHANGE ORDER will be $ 3,758,836.00
Justification:
1) Additional paving work on Faxon Road
Change to CONTRACT TIME:
The contract time is increased/decreased by 0 days.
Requested by: _ __ Builders Paving, LLC.
Recommended by: Engineering Enterprises, Inc.
Accepted by: United City of Yorkville_
Request for Approval of Change of Plans
BLR 13210 (Rev. 10/20/23)Page 1 of 2Completed06/21/2406/21/24
Local Public Agency
United City of Yorkville
County
KendallKendall
Route
Various Local Roads
Section Number
Request Number
1 Final
Contractor
Builders Paving, LLC
Address
4401 Roosevelt Road
City
Hillside
State
ILIL
Zip Code
60162
Date
06/24/2406/24/24
I recommend that this
AdditionAddition be made
The estimated quantities are shown below and the contractor agrees to furnish the materials and do the work at the unit prices.
toto the above contract.
Item Description
Unit of
Measure Quantity Unit Price
Addition (A)
or Deduction
(D)
Total Addition Total Deduction
-Preparation of Base Sq Yd 17000 $1.5000 AA $25,500.0000 $0.0000
-Hot-Mix Asphalt Surface Removal,
4.5"Sq Yd 17000 $5.0000 AA $85,000.0000 $0.0000
-Hot-Mix Asphalt Binder Course,
IL-19.0, N50
Ton 4284 $78.0000 AA $334,152.0000 $0.0000
-Hot-Mix Asphalt Surface Course,
IL-9.5, Mix "D", N50
Ton 1428 $80.0000 AA $114,240.0000 $0.0000
-Combination Curb and Gutter
Removal and Replacement
Foot 400 $36.0000 AA $14,400.0000 $0.0000
-Routing and Sealing Cracks Foot 7700 $0.6400 AA $4,928.0000 $0.0000
-Inlets To Be Adjusted Each 16 $538.0000 AA $8,608.0000 $0.0000
-Additional Traffic Control and
Protection L Sum 1 $10,000.0000AA $10,000.0000 $0.0000
-$0.0000 $0.0000
-$0.0000 $0.0000
-$0.0000 $0.0000
Total Changes $596,828.00 $0.00
Add Row
Total net
additionaddition $596,828.00 18.87%of the contract price.which isto date
Total Net Change $596,828.00
Amount of Original Contract $3,162,008.00
Amount of Previous Change Orders $0.00
Amount of adjusted/final contract $3,758,836.00
State fully the nature and reason for the change
Additional work on Faxon Road, please see location map.
BLR 13210 (Rev. 10/20/23)Page 2 of 2Completed06/21/2406/21/24
When the net increase or decrease in the cost of the contract is $10,000.00 or more, or the time of completion is increased or decreased
by 30 days or more, one of the following statements must be checked:
The Local Public Agency has determined that the circumstances which necessitate this change were not reasonably foreseeable
at the time the contract was signed.
The Local Public Agency has determined that the change is germane to the original contract as signed.
The Local Public Agency has determined that this change is in the best interest of the Local Public Agency and is
authorized by law.
Prepared By
Christopher J. Ott
Title of Preparer
Project Manager
Submitted/Approved
BY:
Local Public Agency Signature & Date
Title:
Approved:
Illinois Department of Transportation
For a Road District project County Engineer signature required.
County Engineer/Superintendent of HighwaysSignature & Date
Regional Engineer Signature & Date
IDOT Department Use Only
Received Location Received Date
Additional Location?
WMFT Entry By Entry Date
Unit 4
Unit 2
Unit 1
McMurtrie Way
North
l
a
n
d
L
nHigh Ridge LnE l d e n Dr
M c M u r t r i e
C t
Red
T ailCt
White Plains Ln AlanDale L n Ala n D a l e LnRedbud Dr
Nor
t
o
n
Ln
Denise Ct
H o n e y s u c k l e L n
Cannonball TrlCannonball Trl
I roqois Ln
Canyon
Trail Ct
RedTailLn Meadowview LnPat
r
i
ci
aLnAm
andaLn
Yellowstone
L
n
Western Ln CatalpaTrlTw i n l e a f T r l
Alice Ave
Fax o n R d
Faxon Rd
Sumac Dr NBr
i
dgeSt
W i n t e r b e r r y D r
Gol d e n r o d D r
Canyon Trl
LEGEND
Remove 4.5", Pave 4.5" Binder & 1.5" Surface
Engineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
Whispering Meadows
Remaining Paving
www.eeiweb.com DATE
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
June 2024
YO2408
YO2408_Whispering_Meadows_Paving .MXD
H:\GIS\PUBLIC\YORKVILLE\2024\
KJD
NO.REVISIONS ³United City of Yorkville
651 Prairie Pointe Drive
Yorkville, IL 60560
630-553-4350www.yorkville.il.us
0 500 1,000250
Feet
To: Contact:United City Of Yorkville
Yorkville 2024 Local Road ProgramProject Name:Bid Number:11160
Fax:Yorkville, IL 60560
Address:651 Prairie Pointe Drive Phone:(630) 553-4350
Project Location:Various Routes, Yorkville, IL Bid Date:5/13/2024
Addendum #:1
The following is a recap of our quantities and pricing for this project.
Total PriceUnit PriceUnitItem DescriptionItem #Estimated Quantity
01 17,000.00 SY $5.00 $85,000.00HMA Surf Rem 4.5"
02 4,284.00 TON $78.00 $334,152.00HMA BC 19.0 N50
03 17,000.00 SY $1.50 $25,500.00Prep Of Base
04 1.00 LS $10,000.00 $10,000.00TCP- RCO 1
Total Bid Price:$454,652.00
Notes:
•Our pricing is based upon completing all work in the 2024 construction season, unless otherwise noted, and is based upon material and cartage
rates in effect at the time of this proposal. Due to the volatility of the petroleum market, our proposal is subject to adjustment, based upon the
market price and availability of raw materials and cartage rates at the time of installation.
•This proposal is valid for a period of thirty (30) days from the date of issue and may be revised or rescinded thereafter, at our discretion, without
prejudice.
Payment Terms:
This is a unit price proposal, with the completed cost of each item based upon the unit prices and quantities as measured in the field.
ACCEPTED:
The above prices, specifications and conditions are satisfactory and
are hereby accepted.
Buyer:
Signature:
Date of Acceptance:
CONFIRMED:
Builders Paving, LLC
Authorized Signature:
Estimator:Chris Mentone
(847) 419-9000 cmentone@builderspavingllc.com
Page 1 of 1
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #7
Tracking Number
PW 2024-59
2023 Water Main Replacement – Contract A – Change Order No. 2 (Final Balancing)
Public Works Committee – July 16, 2024
Majority
Consideration of Approval
Consideration of Change Order No. 2 – Final
Brad Sanderson Engineering
Name Department
The purpose of this memo is to present Change Order No. 2 (Final Balancing) for the above referenced
project.
A Change Order, as defined by in the General Conditions of the Contract Documents, is a written order to
the Contractor authorizing an addition, deletion or revision in the work within the general scope of the
Contract Documents, or authorizing an adjustment in the Contract Price or Contract Time.
Background:
The United City of Yorkville and Performance Construction and Engineering, LLC entered into an
agreement for a Contract value of $1,799,287.00 for the above referenced project. Subsequent change
orders increased the Contract value to $1,827,193.00.
Questions Presented:
Should the City approve Change Order No. 2 (Final Balancing) which would decrease the contract
amount by $3,365.18.
Discussion:
Please see the attached summary spreadsheet.
We are recommending approval of the change order.
Action Required:
Consideration of approval of Change Order No. 2 (Final Balancing) in the amount of $3,365.18.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Erin Willrett, Assistant City Administrator
Krysti Barksdale-Noble, Community Dev. Dir.
Jori Behland, City Clerk
Date: June 17, 2024
Subject: 2023 Water Main Improvements – Contract A
CHANGE ORDER
Order No. 2 (Final Balancing)
Date: July 16, 2024
Agreement Date: March 28, 2023
NAME OF PROJECT: 2023 Water Main Improvements – Contract A
OWNER: United City of Yorkville
CONTRACTOR: Performance Construction & Engineering, LLC
The following changes are hereby made to the CONTRACT DOCUMENTS:
Change of CONTRACT PRICE:
Original CONTRACT PRICE: $1,799,287.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,827,193.00
The CONTRACT PRICE due to this CHANGE ORDER will be (increased) (decreased) by:
$3,365.18
The new CONTRACT PRICE including this CHANGE ORDER will be: $1,823,827.82
Change to CONTRACT TIME:
The CONTRACT TIME will be (increased) (decreased) by 0 calendar days.
The date for substantial completion for all work except restoration
The date for completion for all work will be
Justification
Please see attached spreadsheet. Quantities based on final measurement in the field.
Approvals Required
Requested by: United City of Yorkville
Recommended by: Engineering Enterprises, Inc.
Accepted by: Performance Construction & Engineering, LLC.
PAYABLE TO: Performance Const & Eng, LLC
ADDRESS: 217 W. John Street, Plano, IL 60545 FROM:12/11/2023 TO:6/11/2023
COMPLETED COMPLETED TOTAL TOTAL
ITEM AWARDED ADDED DEDUCTED UNIT QUANTITY THIS VALUE THIS COMPLETED COMPLETED
NO.ITEMS UNIT QUANTITY VALUE QUANTITY QUANTITY PRICE PAY PERIOD PAY PERIOD QUANTITY VALUE
1 TREE REMOVAL (OVER 15 UNITS DIAMETER)EACH 2 1,500.00$ 2.0 750.00$ 0.0 -$ 0.0 -$
2 TREE ROOT PRUNING EACH 14 3,500.00$ 250.00$ 0.0 -$ 14.0 3,500.00$
3 CONNECTION TO EXISTING WATER MAIN, 12-INCH EACH 1 7,500.00$ 7,500.00$ 0.0 -$ 1.0 7,500.00$
4 CONNECTION TO EXISTING WATER MAIN, 8-INCH EACH 8 40,000.00$ 5,000.00$ 0.0 -$ 8.0 40,000.00$
5 CONNECTION TO EXISTING WATER MAIN, 4-INCH EACH 1 4,000.00$ 4,000.00$ 0.0 -$ 1.0 4,000.00$
6 WATER MAIN, CLASS 52, WITH POLYETHYLENE WRAP, 12-INCH LF 1,507 241,120.00$ 24.5 160.00$ 0.0 -$ 1482.5 237,200.00$
7 WATER MAIN, CLASS 52, WITH POLYETHYLENE WRAP, 8-INCH LF 4,466 535,920.00$ 174.5 120.00$ 0.0 -$ 4291.5 514,980.00$
8 GATE VALVE (RESILIENT SEAT) IN 60" VAULT, 4-INCH EACH 1 4,500.00$ 4,500.00$ 0.0 -$ 1.0 4,500.00$
9 GATE VALVE (RESILIENT SEAT) IN 60" VAULT, 8-INCH EACH 18 99,000.00$ 5,500.00$ 0.0 -$ 18.0 99,000.00$
10 GATE VALVE (RESILIENT SEAT) IN 60" VAULT, 12-INCH EACH 4 28,000.00$ 7,000.00$ 0.0 -$ 4.0 28,000.00$
11 FIRE HYDRANT ASSEMBLY, WITH AUXILIARY VALVE, 6-INCH MJ EACH 16 120,000.00$ 7,500.00$ 0.0 -$ 16.0 120,000.00$
12 FIRE HYDRANT TO BE REMOVED EACH 9 2,250.00$ 4.0 250.00$ 0.0 -$ 13.0 3,250.00$
13 DUCTILE IRON FITTINGS LB 9,246 924.60$ 3527.0 0.10$ 0.0 -$ 5719.0 571.90$
14 WATER MAIN PROTECTION, PVC C-900, 12-INCH LF 30 2,250.00$ 30.0 75.00$ 0.0 -$ 0.0 -$
15 NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL - TYPE 1 TON 50 500.00$ 50.0 10.00$ 0.0 -$ 0.0 -$
16 NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL - TYPE 2 TON 50 500.00$ 50.0 10.00$ 0.0 -$ 0.0 -$
17 FOUNDATION MATERIAL CY 100 1,000.00$ 100.0 10.00$ 0.0 -$ 0.0 -$
18 EXPLORATORY EXCAVATION EACH 4 400.00$ 3.0 100.00$ 0.0 -$ 1.0 100.00$
19 WATER SERVICE CONNECTION, 1-INCH EACH 82 262,400.00$ 1.0 3,200.00$ 0.0 -$ 81.0 259,200.00$
20 WATER SERVICE PIPE, 1-INCH PEX LF 3,045 15,225.00$ 125.0 5.00$ 0.0 -$ 3170.0 15,850.00$
21 TEMPORARY WATER SERVICE (SPECIAL)EACH 2 7,000.00$ 3,500.00$ 0.0 -$ 2.0 7,000.00$
22 VALVE VAULT TO BE ABANDONED EACH 9 3,600.00$ 400.00$ 0.0 -$ 9.0 3,600.00$
23 VALVE BOX TO BE ABANDONED EACH 10 1,000.00$ 100.00$ 0.0 -$ 10.0 1,000.00$
24 SANITARY SEWER SERVICE REPAIR, PVC SDR-26, D-2241, 6-INCH EACH 5 3,750.00$ 4.0 750.00$ 0.0 -$ 1.0 750.00$
25 STORM SEWER REMOVAL AND REPLACEMENT WITH GASKETED 12" RCP LF 161 8,050.00$ 92.0 50.00$ 0.0 -$ 69.0 3,450.00$
26 STORM SEWER REMOVAL AND REPLACEMENT, 10" CMP LF 28 1,120.00$ 28.0 40.00$ 0.0 -$ 0.0 -$
27 STORM SEWER REMOVAL AND REPLACEMENT, 12" CMP LF 594 26,730.00$ 36.0 45.00$ 0.0 -$ 630.0 28,350.00$
28 STORM SEWER REMOVAL AND REPLACEMENT, 15" CMP LF 28 1,400.00$ 28.0 50.00$ 0.0 -$ 0.0 -$
29 STORM SEWER REMOVAL AND REPLACEMENT, 10" HDPE LF 25 875.00$ 9.0 35.00$ 0.0 -$ 34.0 1,190.00$
30 DISCONNECT AND ABANDON EXISTING WATER MAIN EACH 10 7,500.00$ 750.00$ 0.0 -$ 10.0 7,500.00$
31 INLET PROTECTION EACH 7 1,400.00$ 2.0 200.00$ 0.0 -$ 5.0 1,000.00$
32 WATER MAIN TESTING - PRESSURE AND DISINFECTION LS 1 10,000.00$ 10,000.00$ 0.00 -$ 1.00 10,000.00$
33 HOT-MIX ASPHALT PATCHING, 4" (SPECIAL)SY 310 12,400.00$ 947.0 40.00$ 0.0 -$ 1257.0 50,280.00$
34 HOT-MIX ASPHALT PATCHING, 6"SY 1,130 58,760.00$ 315.0 52.00$ 73.0 3,796.00$ 1445.0 75,140.00$
35 COMBINATION CONCRETE CURB AND GUTTER REMOVAL AND REPLACEMENT LF 110 6,600.00$ 41.2 60.00$ 28.3 1,698.00$ 68.8 4,128.00$
36 SIDEWALK REMOVAL SF 494 988.00$ 217.6 2.00$ 97.6 195.20$ 711.6 1,423.20$
37 PORTLAND CEMENT CONCRETE SIDEWALK 5-INCH SF 494 5,434.00$ 217.6 11.00$ 97.6 1,073.60$ 711.6 7,827.60$
38 DETECTABLE WARNING SF 16 560.00$ 8.0 35.00$ 3.6 126.00$ 24.0 840.00$
39 AGGREGATE SHOULDER, 2"SY 28 840.00$ 28.0 30.00$ 0.0 -$ 0.0 -$
40 HOT-MIX ASPHALT DRIVEWAY REMOVAL SY 1,260 12,600.00$ 927.8 10.00$ 24.8 248.00$ 2187.8 21,878.00$
41 HOT-MIX ASPHALT DRIVEWAY 3-INCH SY 1,260 31,500.00$ 346.2 25.00$ 24.8 620.00$ 913.8 22,845.00$
42 PORTLAND CEMENT CONCRETE DRIVEWAY REMOVAL SY 250 3,500.00$ 64.6 14.00$ 58.6 820.40$ 314.6 4,404.40$
43 PORTLAND CEMENT CONCRETE DRIVEWAY 6-INCH SY 250 23,000.00$ 64.6 92.00$ 58.6 5,391.20$ 314.6 28,943.20$
44 FENCE TO BE REMOVED AND RESET LF 87 3,480.00$ 40.00$ 87.0 3,480.00$ 87.0 3,480.00$
45 MAILBOX TO BE REMOVED AND RESET EACH 20 3,000.00$ 11.0 150.00$ 0.0 -$ 31.0 4,650.00$
46 SIGN TO BE REMOVED AND RESET EACH 10 1,500.00$ 7.0 150.00$ 0.0 -$ 3.0 450.00$
47 LANDSCAPING TO BE REMOVED AND RESET EACH 5 2,500.00$ 5.0 500.00$ 0.0 -$ 0.0 -$
48 RESTORATION SY 11,940 119,400.00$ 179.0 10.00$ 0.0 -$ 12119.0 121,190.00$
49 TRAFFIC CONTROL AND PROTECTION LS 1 40,310.40$ 40,310.40$ 0.00 -$ 1.00 40,310.40$
50 ALLOWANCE - ITEMS ORDERED BY THE ENGINEER UNIT 30,000 30,000.00$ 4546.12 1.00$ 0.0 -$ 34546.12 34,546.12$
1,799,287.00$ 17,448.40$ - TO DATE:1,823,827.82$
MISCELLANEOUS ADDITIONS TO THE PROJECT AT THE CITY'S DISCRETION (PAY ITEM 50)QUANTITY UNIT PRICE VALUES SUMMARY
1 WATER SERVICES TO HILLCREST NURSING HOME (AUP)2 13,953.00$ 27,906.00$ TOTAL COMPLETED CONSTRUCTION COSTS 1,823,827.82$
2 T&M REPAIR OF FAILED EXISTING WATER MAIN ON 8/30/2023 1 2,321.61$ 2,321.61$ DEDUCT RETAINAGE (0%)-$
3 T&M REPAIR OF EXISTING 8-INCH LEAKING VALVE 1 4,318.51$ 4,318.51$ TOTAL AMOUNT DUE TO CONTRACTOR 1,823,827.82$
4 TOTAL DEBITS 1,787,351.26$
5 NET AMOUNT DUE - THIS PAYMENT 36,476.56$
DEBITS VALUES
1 PAY ESTIMATE 1 483,811.02$
2 PAY ESTIMATE 2 613,963.89$
3 PAY ESTIMATE 3 298,895.36$ PREPARED BY:
4 PAY ESTIMATE 4 319,390.18$
5 PAY ESTIMATE 5 71,290.81$
ENGINEERING ENTERPRISES, INC.APPROVED BY:
52 WHEELER ROAD
SUGAR GROVE, ILLINOIS 60554 G:\Public\Yorkville\2022\YO2217-P 2023 Water Main Replacement\Construction\Pay Estimates\[Estimate YO2217.xlsx]Pay Est No. 6
BID VALUE AWARDED:VALUE COMPLETED - THIS REQUEST:
ENGINEERS PAYMENT ESTIMATE NO. 6 PAY PERIOD
2023 WATER MAIN IMPROVEMENTS - CONTRACT A
UNITED CITY OF YORKVILLE
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #8
Tracking Number
PW 2024-60
WY22 and WY2023 Water Audit Results and Recommendations
Public Works Committee – July 16, 2024
None
Informational
Please see the attached memo.
Brad Sanderson Engineering
Name Department
To meet the Lake Michigan Allocation permit requirements, the United City of Yorkville is
required to reduce Non-Revenue Water (NRW) to below 10% prior to connecting to DuPage
Water Commission (DWC) with water from Lake Michigan in 2028. To track progress, the
water audits for WY2022 and WY2023 have been prepared in accordance with the methodology
found in AWWA Manual M36 – Water Audits and Loss Control and associated software. The
City’s NRW for WY2022, the period from 10/1/21 through 9/30/22, is 8.3%, and then increases
in WY2023, the period from 10/1/22 through 9/30/23, to 14.8%. In Table No. 1 and Figure A
found on Page 2 of this memo, a historical summary of water audit results is provided, including
the water audit results for WY2022 and WY2023.
The components of NRW are: 1) Unbilled Authorized Consumption (which includes both
unbilled metered and unbilled unmetered water use), 2) Apparent Losses, and 3) Real Losses.
Apparent losses consist of the following: unauthorized consumption, customer metering
inaccuracies, and systematic data handling errors. The real losses include: 1) leakage on
distribution/transmission water mains, 2) leakage and overflows at storage facilities, and 3)
leakage at service connections.
The Water System Improvement Plan submitted to Illinois Department of Natural Resources
(IDNR) as part of the Lake Michigan Allocation permitting process for WY2021 addressed all
three (3) components. To reduce unbilled authorized water use, the City is reviewing all known
unbilled authorized water use with the intent of installing meters at these sources, where practical
and billing when appropriate. To address apparent water losses, the City is investing in replacing
all customer meters and converting to Advanced Metering Infrastructure (AMI) technology. In
regard to real losses, the City began to perform annual leak detection. Further, while the City has
periodically replaced water main at locations where water main breaks are most frequent, the
City developed and is implementing a five (5) year water main replacement program to replace
7.7 miles of water main installed prior to 1970.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Jori Behland, City Clerk
Rob Fredrickson, Finance Director
Date: July 3, 2024
Subject: WY2022 and WY2023 Water Audit Results and Recommendations
Subject: Award of 2011 Misc. Bituminous Patching Contract to Aurora Blacktop, Inc.
Table No. 1 Historical Water Audit Summary
Figure A. Historical Water Audit Summary
0%
10%
20%
30%
40%
50%
0
100
200
300
400
500
600
700
800
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Non-Revenue Water %Water (MG)Volume From Own Sources (MG)
NRW Volume (MG)
Billed, Metered Water Use (MG)
NRW %
NRW Reduction Goal (%)
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
WATER SUPPLIED - Total MG/Yr 555.34 476.15 466.02 509.92 541.80 560.58 574.09 550.75 607.60 638.00 627.27 677.05
AUTHORIZED CONSUMPTION
Billed Authorized Use MG/Yr 498.39 382.80 440.82 456.20 485.81 505.21 516.29 484.84 533.76 557.11 575.15 576.76
Unbilled Authorized Consumption MG/Yr 6.94 5.95 5.83 6.37 6.77 7.01 7.18 6.88 7.59 8.97 14.96 12.41
AUTHORIZED CONSUMPTION - Total MG/Yr 505.33 388.75 446.65 462.57 492.58 512.22 523.47 491.72 541.35 566.08 590.11 589.17
NON-REVENUE WATER
Water Supplied - Total MG/Yr 555.34 476.15 466.02 509.92 541.80 560.58 574.09 550.75 607.60 638.00 627.27 677.05
Less Billed and Unbilled Authorized Consumption - Total MG/Yr -505.33 -388.75 -446.65 -462.57 -492.58 -512.22 -523.47 -491.72 -541.35 -566.08 -590.11 -589.17
WATER LOSSES - Total MG/Yr 50.01 87.40 19.38 47.35 49.21 48.36 50.62 59.02 66.24 71.92 37.16 87.87
Plus Unbilled Authorized Consumption
(Unbilled Metered and Metered Water)MG/Yr 6.94 5.95 5.83 6.37 6.77 7.01 7.18 6.88 7.59 8.97 14.96 12.41
NON-REVENUE WATER-Total MG/Yr 56.95 93.35 25.20 53.72 55.99 55.37 57.80 65.91 73.84 80.89 52.12 100.28
NON-REVENUE WATER %%10.3%19.6%5.4%10.5%10.3%9.9%10.1%12.0%12.2%12.7%8.3%14.8%
Water Audit Line Item Unit Calendar Year Water Year
However, the Water System Improvement Plan was intended to be a living document which
would be reviewed, reevaluated, and modified as appropriate on an annual basis in conjunction
with the completion of the annual Water Audit. That being said, the two (2) key parameters to
determining the amount of NRW include the water supplied from water treatment plants and the
amount of water being billed. City staff has made great efforts in ensuring accurate information
is obtained for the water supplied to the distribution system; however, we observed significant
fluctuations in the billing data depending on assumptions within the queries. The current billing
system is outdated and has limited functionality to query the data with confidence for any given
Water Year. Therefore, given the City is not meeting the NRW reduction schedule as of
WY2023 and based on our observations and discussions with City staff while preparing the
water audits, we recommend the following work items be expedited such that they are complete
by September 30, 2026:
1. Completing the Customer Meter Change-out Program
2. Implementing a new billing software and then completing a third-party billing audit once
the billing software is in place.
These work items will improve the billing data integrity used in the water audit. The City
intends to connect to Lake Michigan in 2028, and therefore it is imperative that the City
demonstrate it has reached this goal in the water audit prior to connecting which is the water
audit for WY2027, the period from October 1, 2026, through September 30, 2027. Therefore, to
meet the NRW goal of less than 10% before connection to DWC, any critical NRW reduction
strategies should be implemented by no later than September 30, 2026, such that the impacts can
be observed in the WY2027 Water Audit.
If you have any questions or require additional information, please let us know.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #9
Tracking Number
PW 2024-61
Route 126 Water Main Improvements – Design Engineering Agreement
Public Works Committee – July 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
A proposed design engineering agreement from EEI for the design of the Rt. 126 for a
fixed fee proposed at $143,426 and an additional $63,811 for direct expenses.
Background
This is one of the final pieces for the south receiving station. This water main will begin
at the receiving station which is at the intersection of Wing Rd. and Rt. 126 and end at a point
east of Mill St. along Rt. 126 where it will tie into the water main for the Timber Ridge
subdivision. This water main will be a key distribution main to get Lake Michigan water into
our system in the south central and central pressure zones. These zones cover an area from Rt.
71 north all the way through the old part of town and up to Kennedy Rd.
This project was originally scheduled and budgeted late FY25 with the bulk of the project
to take place in FY26, but with WIFIA’s strict rules and regulations, we thought it prudent to
move up the schedule to make sure we have enough time to follow the WIFIA steps including
land acquisition. In this current fiscal year, we have $67,000 budgeted for design engineering
with an additional $209,000 for design engineering and $25,000 for land acquisition budgeted in
FY26. The proposed contract of $143,426 and $63,811 for direct costs will easily be under
budget in total, but will be over budget in FY25, due to this project being expedited.
Nonetheless, Finance Director Fredrickson believes that this FY25 overage will be easily
absorbed within the existing adopted budget (due to the implementation timing of the meter
replacement and ERP programs), so no budget amendment would be required. This entire
project is budgeted in the (51) Water Fund in the Water Sourcing – DWC line item 51-510-60-
00-6011 for reference.
Recommendation
Staff recommends approval of this proposal in the amount of $143,426 for design
engineering and $63,811 for direct costs.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: July 10, 2024
Subject: Rt. 126 Water Main Design Engineering Agreement
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 1
Route 126 Water Main Improvements
United City of Yorkville
Agreement for Professional Services – Design Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
The Engineer shall furnish the necessary personnel, materials, equipment and
expertise to make the necessary investigations, analysis and calculations along with
exhibits, cost estimates and narrative, to complete all necessary engineering
services to the City as indicated on the included Attachment A. Design Engineering
services shall be provided as indicated on the Scope of Services on Attachment B.
The Engineer shall work with the City to develop a contracting and bidding schedule
consistent with available funding. All Engineering will be in accordance with all City,
Standard Specifications for Water and Sewer Construction in Illinois, Illinois
Environmental Protection Agency, and Illinois Department of Transportation
requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non -
terminating party or upon completion of the Services. Upon termination the
ENGINEER shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to ENGINEER:
ENGINEER shall receive as compensation for all work and services to be performed
herein an amount based on the Estimated Level of Effort and Associated Cost
included in Attachment C. Design Engineering will be paid for monthly based on the
percentage of the project that is complete. The Fixed Fee amount for the Design
Engineering is $143,426.00. Additionally, direct expenses are expected to be
$63,811.00. The hourly rates for this project are shown in Attachment F. All
payments will be made according to the Illinois State Prompt Payment Act and not
less than once every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
written notice of any change in the rates specified in Section C hereof (or on any
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 2
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
E. Ownership of Records and Documents:
ENGINEER agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. ENGINEER agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the freedom of information act or
if already previously disclosed by a third party. Upon termination of this agreement,
ENGINEER agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by ENGINEER without Contractor’s
consent. Modifications of any signed duplicate original document not authorized by
ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kane County, Illinois.
G. Independent ENGINEER:
ENGINEER shall have sole control over the manner and means of providing the
work and services performed under this agreement. The City’s relationship to the
ENGINEER under this agreement shall be that of an independent ENGINEER.
ENGINEER will not be considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The ENGINEER certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to perform
the service.
Anti-Bribery: The ENGINEER certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or admission
of bribery or attempted bribery of an officer or employee of the State of Illinois or any
other state.
Loan Default: If the ENGINEER is an individual, the ENGINEER certifies that he/she
is not in default for a period of six months or more in an amount of $600 or more on
the repayment of any educational loan guaranteed by the Illinois State Scholarship
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 3
Commission made by an Illinois institution of higher education or any other loan
made from public funds for the purpose of financing higher education (5 ILCS 385/3).
Felony Certification: The ENGINEER certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The ENGINEER certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720 Illinois
Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The ENGINEER certifies that it is in compliance with the Drug
Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective date of
this contract. The Drug Free Workplace Act requires, in part, that Contractors, with
25 or more employees certify and agree to take steps to ensure a drug free
workplace by informing employees of the dangers of drug abuse, of the availability
of any treatment or assistance program, of prohibited activities and of sanctions that
will be imposed for violations; and that individuals with contracts certify that they will
not engage in the manufacture, distribution, dispensation, possession, or use of a
controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
ENGINEER agrees to comply with applicable provisions of the Illinois Human Rights
Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the Americans with
Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the rules applicable
to each. The equal opportunity clause of Section 750.10 of the Illinois Department
of Human Rights Rules is specifically incorporated herein. The ENGINEER shall
comply with Executive Order 11246, entitled Equal Employment Opportunity, as
amended by Executive Order 11375, and as supplemented by U.S. Department of
Labor regulations (41 C.F.R. Chapter 60). The ENGINEER agrees to incorporate
this clause into all subcontracts under this Contract.
International Boycott: The ENGINEER certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979 or
the regulations of the U.S. Department of Commerce promulgated under that Act
(30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20 -65 requires
the ENGINEER (and any subcontractors) to maintain, for a period of 3 years after
the later of the date of completion of this Contract or the date of final payment under
the Contract, all books and records relating to the performance of the Contract and
necessary to support amounts charged to the City under the Contract. The Contract
and all books and records related to the Contract shall be available for review and
audit by the City and the Illinois Auditor General. If this Contract is funded from
contract/grant funds provided by the U.S. Government, the Contract, books, and
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 4
records shall be available for review and audit by the Comptroller General of the
U.S. and/or the Inspector General of the federal sponsoring agency. The
ENGINEER agrees to cooperate fully with any audit and to provide full access to all
relevant materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The ENGINEER certifies that
he/she is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien
The Internal Revenue Service requires that taxes be withheld on payments made to
non resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the ENGINEER certifies that its
Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
ENGINEER shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on account
of damage to or destruction of property resulting from the perform ance of work
under this agreement by ENGINEER or its Subcontractors, or due to or arising in
any manner from the wrongful act or negligence of ENGINEER or its Subcontractors
of any employee of any of them. In the event that the either party shall bring any
suit, cause of action or counterclaim against the other party, the non-prevailing party
shall pay to the prevailing party the cost and expenses incurred to answer and/or
defend such action, including reasonable attorney fees and court costs. In no event
shall the either party indemnify any other party for the consequences of that party’s
negligence, including failure to follow the ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of the
types of services rendered hereunder. (Not applicable as having been previously
supplied)
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 5
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed by
both parties. In the event that any provisions of this agreement shall be held to be
invalid or unenforceable, the remaining provisions shall be valid and binding on the
parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimated Level of Effort and Associated Cost
Attachment D: Location Map
Attachment E: Anticipated Project Schedule
Attachment F: 2024 Standard Schedule of Charges
Attachment G: IEPA Professional Services Contract Clauses
Attachment H: USEPA / WIFIA Professional Services Contract Clauses
L. Notices:
All notices required to be given under the terms of this agreement shall be given
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time -to-time substitute addresses
or persons in connection with required notices.
Agreed to this ___day of _________, 2024.
United City of Yorkville Engineering Enterprises, Inc.:
_________________________________ _______________________________
John Purcell Brad Sanderson, P.E.
Mayor Chief Operating Officer /President
_________________________________ ______________________________
Jori Behland Angela R. Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. JULY 2024
PAGE 1
ATTACHMENT A – STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing. However, to
the extent that the Scope of Work differs from the Standard Terms and Conditions, the Scope of Work document controls.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furn ish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction docum ents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provisio n of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinio n
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in el ectronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at th e
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations. ENGINEER
agrees to cooperate with the OWNER, as necessary, to remediate a Hazardous Condition, but same may result in additional costs to
the OWNER.
ENGINEERING ENTERPRISES, INC. JULY 2024
PAGE 2
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have i ncurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warranty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a) Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b) Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c) Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d) Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against t he ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to carry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions b eing taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting su ch force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of in voices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of th e
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonab le fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 1
Route 126 Water Main Improvements – Design Engineering
United City of Yorkville, IL
Attachment B – Scope of Services
The United City of Yorkville requires Design Engineering services to install approximately 6,000
feet of 16” water main to serve as a transmission main from the south receiving station to the
existing water system. A map of the project location can be found in Attachment D of this
proposal.
The following list of work items establishes the scope of engineering services for this project:
DESIGN ENGINEERING:
2.1 Project Management and Administration
• Management of Personnel and the Engineering Contract
• Budget Tracking
• Coordination with the City and Subconsultants (Rubino Engineering)
2.2 Project Meetings
• Project Kick-Off Meeting Between the City and EEI
• One (1) Design Progress Meeting Between the City and EEI prior to Bidding
2.3 Topographic Survey & Easements
• Field Survey
• Drafting to Create Base File
• Preparing Easement Documents
2.4 Utility Coordination
• Design JULIE
• Plan Submission and Coordinate with Private Utilities
2.5 Final Plans, Specifications and Estimates
• Preparation of 60%, 90%, and 100% Engineering Plans
• Preparation of 90% and 100% Project Manual and Engineer’s Opinion of Probable
Construction Cost. Project Manual Shall Include Bidding and Contract Documents,
General Conditions, and Special Provisions.
• Internal QA/QC
2.6 Regulatory Agency Coordination and Permitting
• Prepare IEPA Construction Permit Application and Acquire Permit
• IDOT Permitting
• Coordination with Other Regulatory Agencies as Required
2.7 Bidding and Contracting Services
• Prepare Bidders List and Ad for Bid
• Submit Ad for Bid to the Local Paper and Post Bidding Documents on QuestCDN
UNITED CITY OF YORKVILLE ROUTE 126 WATER MAIN IMPROVEMENTS
PAGE 2
• Address Bid Questions and Prepare Addenda
• Attend Bid Opening
• Prepare Bid Tab, Bid Summary, and Recommendation of Award
• Execute Contract Documents
DIRECT EXPENSES
Legal Surveying
• Boundary Survey
• Easement Preparation
• Legal Descriptions of Easements
• Purchase Title Committments
Geotechnical and CCDD (Rubino Engineering, Inc.)
• Seven (7) Soil Borings 10’ in depth
• Prepare Geotechnical Report and CCDD Analysis
• Prepare LPC 662/663 Permit
EXCLUSIONS
The above scope of services does not include the following:
• Property Negotiations
• Environmental Surveys
• Sewer Televising
• Land Acquisition
The above scope summarizes the work items that will be completed for this contract. Additional
work items, including additional meetings beyond the meetings defined in the above scope
shall be considered outside the scope of the base contract and will be billed in accordance with
EEI’s Standard Schedule of Charges (Attachment F) in affect at the time the extra work is
performed.
ATTACHMENT C: ESTIMATED LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2419-P
PROJECT TITLE DATE PREPARED BY
Route 126 Water Main Improvements
ROLE PIC SPM PM SPE 1 SPM SPT2 ST CM SPT1 ADMIN
RATE $246 $241 $210 $186 $234 $175 $168 $175 $164 $70
DESIGN ENGINEERING
2.1 Project Management and Administration 20 - 32 8 - - - - - - 60 13,128$
2.2 Project Meetings 2 - 4 6 - - - - - - 12 2,448$
2.3 Topographic Survey & Easements - - 4 8 36 - 80 - - - 128 24,192$
2.4 Utility Coordination - - 3 12 - - - - - - 15 2,862$
2.5 Final Plans, Specifications, and Estimates - - 98 220 - - - 30 84 - 432 80,526$
2.6 Regulatory Agency Coordination and Permitting - - 29 54 - - - - - - 83 16,134$
2.7 Bidding and Contracting 1 - 8 10 - - - - - 5 24 4,136$
Design Engineering Subtotal:23 - 178 318 36 - 80 30 84 5 754 143,426$
23 - 178 318 36 - 80 30 84 5 754 143,426
EEI STAFF
PIC Principal In Charge 100$
SPM Senior Project Manager Legal Surveying =41,481$
PM Project Manager 9,600$
SPE 1 Senior Project Engineer I 12,630$
SPT 2 Senior Project Technician II DIRECT EXPENSES =63,811$
SPT 1 Senior Project Technician I
ST Senior Technician
ADMIN Adminstrative Assistant 143,426$
143,426$
207,237$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
DIRECT EXPENSES
TOTAL COSTS
Printing =
Title Commitments =
Geotechnical/CCDD =
EEI Labor Expenses =
TOTAL LABOR EXPENSES
LABOR SUMMARY
PROJECT TOTAL:
KDW7/8/24
COSTTASK
NO.TASK DESCRIPTION HOURS
GF
GF
GF
GFGF
GF
GF
GF
GF GF
GF
GF
GF GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GFGFGF
GF GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GFGF
GF
GF
GF
GF
GF
GF
GF
GFGFGFGFGFGF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GF
GFGF
GF
GF
GF
GF
GF
GF
GF
GFGF GF
GF
GF
GFGF
GFGF
GFGF
GF
GF
GF
GF
GF
GFGF
GF
GF
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(!(
!(
!(!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(!(
!(
!(
!(
!(!(
!(
!(
!(!(!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
STAGEC
O
A
C
H
SC
H
O
O
L
H
O
U
S
E
HAMPTON WING
PARKSI
D
E
ID
E
N
T
A
TI
M
B
E
R
O
A
K
ROUT
E
1
2
6
C
O
U
N
T
R
Y
H
I
L
L
S
RAINTREECROOKED CREEKHAZELT
I
N
E
INGEMUNSONBLUEBIRD
CLOVER
ASH
GREE
NFIELD TUR
N
WESTONSUNN
Y
D
E
L
LCHERRYPINE
MEAD
O
WL
A
R
K FAWN RIDGECANDLEBERRYJUNIPER
Engineering Enterprises, Inc.
52 Wheeler Road
Sugar Grove, Illinois 60554
(630) 466-6700
Legend
!(VALVE
GF HYDRANT
Water Main
Diameter
3" WATER MAIN AND SMALLER
4" WATER MAIN
6" WATER MAN
8" WATER MAIN
10" WATER MAIN
12" WATER MAIN
16" WATER MAIN
UNKNOWN WATER MAIN
WATER IMPROVEMENT LIMITS
ATTACHMENT D
ROUTE 126
WATER MAIN IMPROVEMENTS
LOCATION MAP
www.eeiweb.com
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
JULY 2024
YO2419
YO2419_Route 126 Water Main Improvements
H:\GIS\PUBLIC\YORKVILLE\2024\
MJT ³
1,400 0700 Feet
CONNECT TO
RECEIVING STATION
CONNECT TO
EXISTING WATER
MAIN
ATTACHMENT E: ESTIMATED SCHEDULE
CLIENT PROJECT NUMBER
United City of Yorkville YO2419-P
PROJECT TITLE DATE PREPARED BY
Route 126 Water Main Improvements KDW
JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL
DESIGN ENGINEERING
2.1
2.2
2.3
2.4
2.5
2.6
2.7
Note: Land acquisition anticipated to take 6-8 months
52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
Final Plans, Specifications, and Estimates
Regulatory Agency Coordination and Permitting
Bidding and Contracting
Project Management and Administration
Project Meetings
Topographic Survey
Utility Coordination
TASK
NO.TASK DESCRIPTION
7/8/24
2024 2025
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00 Principal E-3 $241.00 Senior Project Manager E-2 $234.00 Project Manager E-1 $210.00 Senior Project Engineer/Surveyor II P-6 $200.00 Senior Project Engineer/Surveyor I P-5 $186.00 Project Engineer/Surveyor P-4 $168.00 Senior Engineer/Surveyor P-3 $155.00 Engineer/Surveyor P-2 $140.00 Associate Engineer/Surveyor P-1 $127.00 Senior Project Technician II T-6 $175.00 Senior Project Technician I T-5 $164.00 Project Technician T-4 $153.00 Senior Technician T-3 $140.00 Technician T-2 $127.00 Associate Technician T-1 $111.00 GIS Technician II G-2 $125.00 GIS Technician I G-1 $114.00 Engineering/Land Surveying Intern I-1 $ 82.00 Executive Administrative Assistant A-4 $ 77.00 Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024
United States Environmental Protection Agency
Washington, D.C. 20460
Certification Regarding
Debarment, Suspension, and Other Responsibility Matters
The prospective participant certifies to the best of its knowledge and belief that it and its
principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible,
or voluntarily excluded from covered transactions by any Federal department or
agency;
(b) Have not within a three year period preceding this proposal been convicted of or had
a civil judgment rendered against them for commission of fraud or a criminal offense
in connection with obtaining, attempting to obtain, or performing a public: (Federal,
State, or local) transaction or contract under a public transaction; violation of Federal
or State antitrust statutes or commission of embezzlement, theft, forgery, bribery,
falsification or destruction of records, making false statements, or receiving stolen
property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a
government entity (Federal, State, or local) with commission of any of the offenses
enumerated in paragraph (1)(b) of this certification; and
(d) Have not within a three-year period preceding this application/proposal had one or
more public transactions (Federal, State, or local) terminated for cause or default.
I understand that a false statement on this certification may be grounds for rejection of this
proposal or termination of the award. In addition, under 18 USC Sec. 1001, a false statement
may result in a fine of up to $10,000 or imprisonment for up to 5 years, or both.
Typed Name and Title of Authorized Representative
Signature of Authorized Representative Date
I am unable to certify to the above statements. May explanation is attached.
EPA FORM 5700-49 (11-88)
EPA Project Control Number
ATTACHMENT H
SUPPLEMENTARY USEPA / WIFIA PROFESSIONAL SERVICES CONTRACT CLAUSES
ECONOMIC AND MISCELLANEOUS AUTHORITIES
DEBARMENT AND SUSPENSION AND PROHIBITIONS RELATING TO VIOLATIONS OF CWA AND
CAA WITH RESPECT TO FEDERAL CONTRACTS, GRANTS, OR LOANS
Debarment and Suspension. Contractor certifies that it will not knowingly enter into a contract with anyone
who is ineligible under the 2 CFR part 180 and part 1532 (per Executive Order 12549, 51 FR 6370, February
21, 1986) or who is prohibited under Section 306 of the Clean Air Act or Section 508 of the Clean Water
Act to participate in the [Project]. Suspension and debarment information can be accessed at
http://www.sam.gov. Contractor represents and warrants that it has or will include a term or conditions
requiring compliance with this provision in all of its subcontracts under this Agreement.
NEW RESTRICTIONS ON LOBBYING
Federal Lobbying Restrictions (31 U.S.C 1352). Recipients of federal financial assistance may not pay
any person for influencing or attempting to influence any officer or employee of a federal agency, a member
of Congress, an officer or employee of Congress, or an employee of a member of Congress with respect
to the award, continuation, renewal, amendment, or modification of a federal grant, loan, or contract. These
requirements are implemented for USEPA in 40 CFR Part 34, which also describes types of activities, such
as legislative liaison activities and professional and technical services, which are not subject to this
prohibition. Upon award of this contract, Contractor shall complete and submit to the City the certification
and disclosure forms in Appendix A and Appendix B to 40 CFR Part 34. Contractor shall also require all
subcontractors and suppliers of any tier awarded a subcontract over $100,000 to similarly complete and
submit the certification and disclosure forms pursuant to the process set forth in 40 CFR 34.110.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #10
Tracking Number
PW 2024-62
Lake Michigan South Receiving Station Standpipe – Design Engineering Agreement
Public Works Committee – July 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
A proposed design engineering agreement from EEI for the South Receiving Station
Standpipe. This tank is needed as part of the Lake Michigan project. This is budgeted for in the
approved FY 25 budget.
Background
As part of our Lake Michigan allocation, we are required to have 2 days’ worth of water
in storage. To meet this rule, the city has proposed to construct an EWST in the northwest
quadrant of the city and a standpipe in the southeast quadrant. This agreement addresses the
northwest EWST and its design.
Last month, the committee saw the design engineering agreements for the receiving
stations. This month is the storage tanks that we are going to pump water into from those
receiving stations. These are under separate contracts because this type of work is so specialized
and there are very few bidders. We want to keep this separate from the receiving stations to
ensure quality bidders.
EEI is proposing a fixed fee of $219,034. This is $30,966 under the budgeted amount. In
addition to the standard engineering work, this contract includes WIFIA coordination and
subcontractor oversight and management.
This is in the approved budget in the water fund line-item Water Sourcing-DWC 51-510-
60-00-6011.
Recommendation
Staff Recommends approval of this contract with EEI in the amount of $219,034.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: July 10, 2024
Subject: South Receiving Station Standpipe Design Engineering
Agreement
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 1
Lake Michigan South Receiving Station Standpipe
United City of Yorkville
Agreement for Professional Services – Design Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
The Engineer shall furnish the necessary personnel, materials, equipment and
expertise to make the necessary investigations, analysis and calculations along with
exhibits, cost estimates and narrative, to complete all necessary engineering
services to the City as indicated on the included Attachment A. Design Engineering
services shall be provided as indicated on the Scope of Services on Attachment B.
The Engineer shall work with the City to develop a contracting and bidding schedule
consistent with available funding. All Engineering will be in accordance with all City,
Standard Specifications for Water and Sewer Construction in Illinois, Illinois
Environmental Protection Agency, and Illinois Department of Transportation
requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the
ENGINEER shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to ENGINEER:
ENGINEER shall receive as compensation for all work and services to be performed
herein an amount based on the Estimated Level of Effort and Associated Cost
included in Attachment C. Design Engineering will be paid for monthly based on the
percentage of the project that is complete. The Fixed Fee amount for the Design
Engineering is $219,034.00. The hourly rates for this project are shown in
Attachment F. All payments will be made according to the Illinois State Prompt
Payment Act and not less than once every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
written notice of any change in the rates specified in Section C hereof (or on any
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 2
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
E. Ownership of Records and Documents:
ENGINEER agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. ENGINEER agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the freedom of information act or
if already previously disclosed by a third party. Upon termination of this agreement,
ENGINEER agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by ENGINEER without Contractor’s
consent. Modifications of any signed duplicate original document not authorized by
ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kane County, Illinois.
G. Independent ENGINEER:
ENGINEER shall have sole control over the manner and means of providing the
work and services performed under this agreement. The City’s relationship to the
ENGINEER under this agreement shall be that of an independent ENGINEER.
ENGINEER will not be considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The ENGINEER certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to perform
the service.
Anti-Bribery: The ENGINEER certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or admission
of bribery or attempted bribery of an officer or employee of the State of Illinois or any
other state.
Loan Default: If the ENGINEER is an individual, the ENGINEER certifies that he/she
is not in default for a period of six months or more in an amount of $600 or more on
the repayment of any educational loan guaranteed by the Illinois State Scholarship
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 3
Commission made by an Illinois institution of higher education or any other loan
made from public funds for the purpose of financing higher education (5 ILCS 385/3).
Felony Certification: The ENGINEER certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The ENGINEER certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720 Illinois
Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The ENGINEER certifies that it is in compliance with the Drug
Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective date of
this contract. The Drug Free Workplace Act requires, in part, that Contractors, with
25 or more employees certify and agree to take steps to ensure a drug free
workplace by informing employees of the dangers of drug abuse, of the availability
of any treatment or assistance program, of prohibited activities and of sanctions that
will be imposed for violations; and that individuals with contracts certify that they will
not engage in the manufacture, distribution, dispensation, possession, or use of a
controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
ENGINEER agrees to comply with applicable provisions of the Illinois Human Rights
Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the Americans with
Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the rules applicable
to each. The equal opportunity clause of Section 750.10 of the Illinois Department
of Human Rights Rules is specifically incorporated herein. The ENGINEER shall
comply with Executive Order 11246, entitled Equal Employment Opportunity, as
amended by Executive Order 11375, and as supplemented by U.S. Department of
Labor regulations (41 C.F.R. Chapter 60). The ENGINEER agrees to incorporate
this clause into all subcontracts under this Contract.
International Boycott: The ENGINEER certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979 or
the regulations of the U.S. Department of Commerce promulgated under that Act
(30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires
the ENGINEER (and any subcontractors) to maintain, for a period of 3 years after
the later of the date of completion of this Contract or the date of final payment under
the Contract, all books and records relating to the performance of the Contract and
necessary to support amounts charged to the City under the Contract. The Contract
and all books and records related to the Contract shall be available for review and
audit by the City and the Illinois Auditor General. If this Contract is funded from
contract/grant funds provided by the U.S. Government, the Contract, books, and
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 4
records shall be available for review and audit by the Comptroller General of the
U.S. and/or the Inspector General of the federal sponsoring agency. The
ENGINEER agrees to cooperate fully with any audit and to provide full access to all
relevant materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The ENGINEER certifies that
he/she is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien
The Internal Revenue Service requires that taxes be withheld on payments made to
non resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the ENGINEER certifies that its
Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
ENGINEER shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on account
of damage to or destruction of property resulting from the performance of work
under this agreement by ENGINEER or its Subcontractors, or due to or arising in
any manner from the wrongful act or negligence of ENGINEER or its Subcontractors
of any employee of any of them. In the event that the either party shall bring any
suit, cause of action or counterclaim against the other party, the non-prevailing party
shall pay to the prevailing party the cost and expenses incurred to answer and/or
defend such action, including reasonable attorney fees and court costs. In no event
shall the either party indemnify any other party for the consequences of that party’s
negligence, including failure to follow the ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of the
types of services rendered hereunder. (Not applicable as having been previously
supplied)
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 5
K.Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed by
both parties. In the event that any provisions of this agreement shall be held to be
invalid or unenforceable, the remaining provisions shall be valid and binding on the
parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimated Level of Effort and Associated Cost
Attachment D: Location Map
Attachment E: Anticipated Project Schedule
Attachment F: 2024 Standard Schedule of Charges
Attachment G: IEPA Professional Services Contract Clauses
Attachment H: USEPA / WIFIA Professional Services Contract Clauses
L. Notices:
All notices required to be given under the terms of this agreement shall be given
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time-to-time substitute addresses
or persons in connection with required notices.
Agreed to this ___day of _________, 2024.
United City of Yorkville Engineering Enterprises, Inc.:
_________________________________ _______________________________
John Purcell Bradley P. Sanderson, PE
Mayor Chief Operating Officer /President
_________________________________ ______________________________
Jori Behland Angela R. Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 1
ATTACHMENT A – STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing. However, to
the extent that the Scope of Work differs from the Standard Terms and Conditions, the Scope of Work document controls.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furnish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction documents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provision of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinion
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in electronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at the
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations. ENGINEER
agrees to cooperate with the OWNER, as necessary, to remediate a Hazardous Condition, but same may result in additional costs to
the OWNER.
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 2
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have incurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warranty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a)Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b)Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c)Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d)Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against the ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to carry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions being taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting such force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of invoices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of the
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonable fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 1
Lake Michigan South Receiving Station Standpipe – Design Engineering
United City of Yorkville, IL
Attachment B – Scope of Services
The United City of Yorkville requires Design Engineering services to construct a standpipe in
conjunction with the Lake Michigan South Receiving Station needed to connect to and receive
water supply from DuPage Water Commission (DWC). A concept site plan for the Receiving
Station which includes the approximate location of the standpipe can be found in Attachment D
of this proposal.
The City has begun implementing a multi-year program to construct required infrastructure to
connect to receive water supply from DWC utilizing funds from the Water Infrastructure and
Innovation Act of 2014 (WIFIA), and WIFIA funding is anticipated to be used for a portion of this
project.
The following list of work items establishes the scope of engineering services for this project:
PROJECT FACILITATION AND ADMINISTRATION:
0.01 Project Management and Administration
•Management of Personnel and the Engineering Contract
•Budget Tracking
•Coordination with the City and Subconsultants
0.02 On-going City Communication/Coordination Updates
0.03 Project Kickoff and Progress Review Meetings (3 Total Meetings with City plus Internal
Meetings)
•Project Kick-Off Meeting Between the City and EEI
o Prepare Discussion Outline and Minutes
o Attend Meeting at City Hall or Virtual
o Site Visit After Meeting
•Two (2) Design Progress Meetings Between the City and EEI prior to Bidding
o Prepare Discussion Outlines and Minutes
o Attend Meetings at City Hall or Virtual
PRELIMINARY DESIGN PHASE:
1.01 Confirm the Size and Dimensions of the Standpipe
1.02 Prepare Summary of Potential Bidders / Tank Erectors
1.03 Coordinate Soil Borings and Soils Report
1.04 Conduct Site Visits (2) - Pre and Post Design
1.05 Perform a JULIE Design Request
1.06 Coordination with North Receiving Station Design Team for Bid Item/Scope Boundaries
1.07 Prepare Draft Site Plan (Rough grading, Water Main, Storm Sewer/Drainage)
1.08 Prepare and Obtain the Following Permits/Sign-offs
•IDNR - EcoCAT Sign-off
•SHPO/HARGIS - Historic Sign-off
•Stormwater Permitting (Assumes No Wetlands, No Floodplain)
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 2
•IDNR - Notice of Intent (NOI)
•City Building Permit
•Federal Aviation Administration
1.09 Electrical/ComEd Application Preparation and Initial Coordination
1.10 Facilitate Mixing System Discussions with Vendors
1.11 Facilitate Cathodic Protection Discussions with Vendors
1.12 Prepare/Review Coating Systems and Tank Optional Features with City Staff
1.13 Develop Tank Orientation/Tank Cross-Section Plans
1.14 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City
1.15 Telecommunication Facility Location Coordination
1.16 Prepare 30% Complete Drawings and Specifications
1.17 Present Final Layout and Logo to City Council/PW Committee
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications
2.02 Coordination with Landscape Architect
2.03 Prepare 95% Complete Drawings and Specifications
2.04 Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
2.05 Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water Supplies)
2.06 Prepare 95% Engineer's Opinion of Probable Construction Cost
2.07 SCADA Integration and Design
2.08 Complete Plans and Specifications to 100%
2.09 Prepare 100% Engineer's Opinion of Probable Construction Cost
BIDDING AND CONTRACTING PHASE
3.01 Prepare Final Bid Documents and Coordinate Advertise for Bid
3.02 Respond to Bidder Inquiries/Prepare Addenda
3.03 Maintain Bidders List, Coordinate Addenda and Distribution Utilizing Quest
3.04 Prepare IEPA - Notice of Intent
3.05 Prepare for and Attend Bid Opening
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract
3.07 Attend City Council/PW Committee Meeting for Anticipated Contract Award
FUNDING ASSISTANCE
4.01 Coordinating WIFIA Loan
•Coordination with USEPA to furnish required documentation necessary for funding
(executed engineering agreements, final bid and contract documents, executed
construction contracts)
•Advertisement for DBE’s consistent with good faith requirements regarding use of
DBE’s
DIRECT EXPENSES
The following scope of services will be provided by EEI’s subconsultants:
•Electrical/SCADA (Consultant To Be Determined)
UNITED CITY OF YORKVILLE LAKE MICHIGAN SOUTH RECEIVING STATION STANDPIPE
PAGE 3
•Geotechnical and CCDD (Rubino Engineering, Inc.)
o Four (4) Soil Borings at a Maximum Depth of 100’ (or to refusal)
o Prepare Geotechnical Report and CCDD Analysis
o Prepare LPC 662/663 Permit
•Archaeological Survey
•Title Commitment
•Landscape Architecture
NOTES AND EXCLUSIONS
•The above scope of services does not include the following:
o Construction Engineering
o Topographic Survey and ALTA Survey
o Plat of Dedication and/or Plat of Easement preparation
o Land Acquisition and Property Negotiations
o Environmental Surveys
o WIFIA Loan Application or Loan Processing/Coordination other than items noted in
above scope
o Illinois PWSLP State Revolving Fund Coordination or Assistance
o New Electrical Service Fees
o Engineering Related to the Pump Station
o Engineering Related to an Altitude Valve
o Engineering related to a Chlorine Analyzer Within the Tank
o Permitting and Sign-off Coordination Other Than Those identified in 1.08 and 2.05
The above scope summarizes the work items that will be completed for this contract. Additional
work items, including additional meetings beyond the meetings defined in the above scope
shall be considered outside the scope of the base contract and will be billed in accordance with
EEI’s Standard Schedule of Charges (Attachment F) in affect at the time the extra work is
performed.
ATTACHMENT C: ESTIMATED LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2417-P
PROJECT TITLE DATE PREPARED BY
Lake Michigan South Receiving Station Standpipe
ROLE PIC QC/QA PM SPE 2 PE SPT 2 SPT 1 ADMIN
RATE $246 $241 $210 $200 $168 $175 $164 $70
PROJECT FACILITATION & ADMINISTRATION
0.01 Project Management and Administration 2 12 14 3,012$
0.02 On-going City Communication/Coordination/Updates 12 4 16 3,692$
0.03 9 9 12 3 12 45 9,519$
Project Facilitation & Administration Subtotal: 11 21 24 7 12 - - - 75 16,223$
PRELIMINARY DESIGN PHASE
1.01 Confirm the Size and Dimensions of the Standpipe 1 8 8 8 25 5,198$
1.02 Prepare Summary of Potential Bidders / Tank Erectors 1 2 2 4 9 1,733$
1.03 Coordinate Soil Borings and Soils Report 1 1 4 4 10 1,823$
1.04 Conduct Site Visits (2) - Pre and Post Design 6 6 6 18 3,714$
1.05 Perform a JULIE Design Request 2 6 8 1,428$
1.06 Coordination with North Receiving Station Design Team for Bid Item/Scope Boundaries 4 4 4 12 2,476$
1.07 Prepare Draft Site Plan (Rough grading, Water Main, Storm Sewer/Drainage) 2 8 1 8 12 31 5,806$
1.08 - -$
1 2 3 546$
1 2 4 7 1,246$
Stormwater Permitting (Assumes No Wetlands, No Floodplain) 1 8 2 11 2,146$
1 2 3 546$
City Building Permit 1 1 2 378$
Federal Aviation Administration 1 2 4 7 1,246$
1.09 Electrical/ComEd Application and Initial Coordination 4 12 12 28 5,500$
1.10 Facilitate Mixing System Discussions with Vendors 2 4 4 8 18 3,466$
1.11 Facilitate Cathodic Protection Discussions with Vendors 2 4 4 4 14 2,794$
1.12 Prepare/Review Coating Systems and Tank Optional Features with City Staff 2 4 4 4 14 2,794$
1.13 Develop Tank Orientation/Tank Cross-Section Plans 2 6 12 20 3,650$
1.14 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City 1 4 4 4 24 37 6,658$
1.15 Telecommunication Facility Location Coordination 4 24 28 4,736$
1.16 Prepare 30% Complete Drawings and Specifications 4 8 8 12 32 6,212$
1.17 2 2 492$
Preliminary Design Phase Subtotal: 4 42 73 41 83 24 72 - 339 64,588$
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications 12 12 12 36 6,888$
2.02 1 1 4 6 1,034$
2.03 4 40 8 40 40 132 24,244$
2.04 4 4 8 1,804$
2.05 1 4 6 11 2,089$
2.06 1 2 1 12 16 2,877$
2.07 SCADA Integration and Design 2 4 4 8 18 3,466$
2.08 Complete Plans and Specifications to 100% 4 2 4 2 8 12 32 6,018$
2.09 1 1 2 1 2 7 1,443$
Final Design Phase Subtotal: 5 15 73 28 77 - 68 - 266 49,863$
BIDDING AND CONTRACTING PHASE
3.01 1 4 2 8 15 2,825$
3.02 Respond to Bidder Inquiries/Prepare Addenda 6 12 6 16 40 7,854$
3.03 4 4 280$
3.04 Prepare IEPA - Notice of Intent 2 2 336$
3.05 Prepare for and Attend Bid Opening 4 4 2 10 1,652$
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract 1 4 2 7 1,053$
3.07 2 2 492$
Bidding and Contracting Phase Subtotal: 2 8 20 8 34 - - 8 80 14,492$
FUNDING ASSISTANCE
4.01 Coordinating WIFIA Loan 8 16 24 4,368$
Funding Assistance Subtotal: - - 8 - 16 - - - 24 4,368$
SURVEYING
5.01 Surveying (Topographic Survey and ALTA Survey)- -$
Surveying Subtotal: - - - - - - - - - -$
22 86 198 84 222 24 140 8 784 149,534
EEI STAFF
PIC Principal In Charge 500$
SPM Senior Project Manager Vehicle Charges/Mileage = 200$
PM Project Manager Electrical/SCADA = 30,000$
SPE 2 Senior Project Engineer II 30,000$
PE Project Engineer 5,000$
SPT 2 Senior Project Technician II Title Commitment = 800$
SPT 1 Senior Project Technician I 3,000$
ST Senior Technician DIRECT EXPENSES = 69,500$
ADMIN Adminstrative Assistant
149,534$
149,534$
219,034$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
Coordination with Landscape Architect
Printing =
Geotechnical and CCDD =
TOTAL COSTS
MLP
TASK
NO.TASK DESCRIPTION HOURS COST
Project Initiation & Progress Meetings (3 Total Meetings with City plus internal review meetings)
Permits/Sign-offs
IDNR - EcoCAT Sign-off
INCLUDED IN THE SOUTH RECEIVING STATION CONTRACT SCOPE
7/9/24
SHPO/HARGIS - Historic Sign-off
Present Final Layout and Logo to City Council/PW Committee
IDNR - Notice of Intent (NOI)
Maintain Bidders List, Coordinate Addenda and Distribution - Use Quest
Attend City Council/PW Committee Meeting for Anticipated Contract Award
Prepare 95% Complete Drawings and Specifications
Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water Supplies)
Prepare 95% Engineer's Opinion of Probable Construction Cost
Prepare 100% Engineer's Opinion of Probable Construction Cost
Prepare Final Bid Documents and Coordinate Advertise for Bid
LABOR SUMMARY
EEI Labor Expenses =
TOTAL LABOR EXPENSES
Landscape Architect =
Archaeological Survey =
PROJECT TOTAL:
DIRECT EXPENSES
320'400'
400'320'• •••Engineering Enterprises, Inc.11PROPOSED SOUTH DELIVERY STATIONSITE PLAN (PRELIMINARY)LAKE MICHIGANPRELIMINARY ENGINEERINGUNITED CITY OF YORKVILLEIL ROUTE 126WING ROADIL ROUTE 126WING ROADIL ROUTE 71LOCATION MAP
ATTACHMENT E: ESTIMATED SCHEDULE
CLIENT PROJECT NUMBER
United City of Yorkville YO2417-P
PROJECT TITLE DATE PREPARED BY
Lake Michigan South Receiving Station Standpipe MLP
JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY
PROJECT FACILITATION & ADMINISTRATION
0.01 Project Management and Administration
0.02 On-going City Communication/Coordination/Updates
0.03
PRELIMINARY DESIGN PHASE
1.01 Confirm the Size and Dimensions of the Standpipe
1.02 Prepare Summary of Potential Bidders / Tank Erectors
1.03 Coordinate Soil Borings and Soils Report
1.04 Conduct Site Visits (2) - Pre and Post Design
1.05 Perform a JULIE Design Request
1.06
1.07 Prepare Draft Site Plan (Rough grading, Water Main, Storm Sewer/Drainage)
1.08
Stormwater Permitting (Assumes No Wetlands, No Floodplain)
City Building Permit
Federal Aviation Administration
1.09 Electrical/ComEd Application and Initial Coordination
1.1 Facilitate Mixing System Discussions with Vendors
1.11 Facilitate Cathodic Protection Discussions with Vendors
1.12 Prepare/Review Coating Systems and Tank Optional Features with City Staff
1.13 Develop Tank Orientation/Tank Cross-Section Plans
1.14 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City
1.15 Telecommunication Facility Location Coordination
1.16 Prepare 30% Complete Drawings and Specifications
1.17
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications
2.02
2.03
2.04
2.05
2.06
2.07 SCADA Integration and Design
2.08 Complete Plans and Specifications to 100%
2.09
BIDDING AND CONTRACTING PHASE
3.01
3.02 Respond to Bidder Inquiries/Prepare Addenda
3.03
3.04 Prepare IEPA - Notice of Intent
3.05 Prepare for and Attend Bid Opening
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract
3.07
FUNDING ASSISTANCE
4.01 Coordinating WIFIA Loan
52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
Coordinate with Landscape Architect
IEPA REVIEW
Attend City Council/PW Committee Meeting for Anticipated Contract Award and
Coordinate Contracts
Prepare Final Bid Documents and Coordinate Advertise for Bid
Maintain Bidders List, Coordinate Addenda and Distribution - Use Quest
Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water
Supplies)
Prepare 95% Engineer's Opinion of Probable Construction Cost
Prepare 100% Engineer's Opinion of Probable Construction Cost
Project Initiation & Progress Meetings (3 Total Meetings with City plus internal
Coordination with North Receiving Station Design Team for Bid Item/Scope
Boundaries
Present Final Layout and Logo to City Council/PW Committee
Prepare 95% Complete Drawings and Specifications
IDNR - Notice of Intent (NOI)
Permits/Sign-offs
IDNR - EcoCAT Sign-off
SHPO/HARGIS - Historic Sign-off
7/9/24
TASK
NO.TASK DESCRIPTION 2025
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00
Principal E-3 $241.00
Senior Project Manager E-2 $234.00
Project Manager E-1 $210.00
Senior Project Engineer/Surveyor II P-6 $200.00
Senior Project Engineer/Surveyor I P-5 $186.00
Project Engineer/Surveyor P-4 $168.00
Senior Engineer/Surveyor P-3 $155.00
Engineer/Surveyor P-2 $140.00
Associate Engineer/Surveyor P-1 $127.00
Senior Project Technician II T-6 $175.00
Senior Project Technician I T-5 $164.00
Project Technician T-4 $153.00
Senior Technician T-3 $140.00
Technician T-2 $127.00
Associate Technician T-1 $111.00
GIS Technician II G-2 $125.00
GIS Technician I G-1 $114.00
Engineering/Land Surveying Intern I-1 $ 82.00
Executive Administrative Assistant A-4 $ 77.00
Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
ATTACHMENT F - STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024
ATTACHMENT G
IEPA PROFESSIONAL SERVICES CONTRACT CLAUSES
Audit and Access to Records Clause:
A. Books, records, documents and other evidence directly pertinent to performance of PWSLP/WPCLP
loan work under this agreement shall be maintained in accordance with generally accepted
Accounting Principles. The Agency or any of its authorized representatives shall have access to the
books, records, documents and other evidence for the purpose of inspection, audit and copying.
Facilities shall be provided for access and inspection.
B. Audits conducted pursuant to this provision shall be in accordance with auditing standards generally
accepted in the United States of America.
C. All information and reports resulting from access to records pursuant to the above shall be disclosed
to the Agency. The auditing agency shall afford the engineer an opportunity for an audit exit
conference and an opportunity to comment on the pertinent portions of the draft audit report.
D. The final audit report shall include the written comments, if any, of the audited parties.
E. Records shall be maintained and made available during performance of project services under this
agreement and for three years after the final loan closing. In addition, those records that relate to any
dispute pursuant to the Loan Rules Section 365.650 or Section 662.650 (Disputes) or litigation or the
settlement of claims arising out of project performance or costs or items to which an audit exception
has been taken, shall be maintained and made available for three years after the resolution of the
appeal, litigation, claim or exception.
Covenant Against Contingent Fees:
The professional services contractor warrants that no person or selling agency has been employed or
retained to solicit or secure this contract upon an agreement or understanding for a commission,
percentage, brokerage, or contingent fee, excepting bonafide employees. For breach or violation of this
warranty, the loan recipient shall have the right to annul this agreement without liability or in its discretion
to deduct from the contract price or consideration or otherwise recover, the full amount of such
commission, percentage, brokerage, or contingent fee.
Certification Regarding Debarment, Suspension and Other Responsibility Matters:
Form EPA 5700-49 is signed and attached as part of Attachment G.
USEPA Nondiscrimination Clause:
The contractor (engineer) shall not discriminate on the basis of race, color, national origin or sex in the
performance of this contract. The contractor shall carry out applicable requirements of 40 CFR Part 33 in
the award and administration of contracts awarded under EPA financial assistance agreements. Failure
by the contractor to carry out these requirements is a material breach of this contract which may result in
the termination of this contract or other legally available remedies.
USEPA Fair Share Percentage Clause:
The engineer agrees to take affirmative steps to assure that disadvantaged business enterprises are
utilized when possible as sources of supplies, equipment, construction and services in accordance with
the [WPC or PWS] Loan Program rules. As required by the award conditions of USEPA's Assistance
Agreement with Illinois EPA, the engineer acknowledges that the fair share percentages are 5% for MBEs
& 12% for WBEs”.
United States Environmental Protection Agency
Washington, D.C. 20460
Certification Regarding
Debarment, Suspension, and Other Responsibility Matters
The prospective participant certifies to the best of its knowledge and belief that it and its
principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible,
or voluntarily excluded from covered transactions by any Federal department or
agency;
(b) Have not within a three year period preceding this proposal been convicted of or had
a civil judgment rendered against them for commission of fraud or a criminal offense
in connection with obtaining, attempting to obtain, or performing a public: (Federal,
State, or local) transaction or contract under a public transaction; violation of Federal
or State antitrust statutes or commission of embezzlement, theft, forgery, bribery,
falsification or destruction of records, making false statements, or receiving stolen
property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a
government entity (Federal, State, or local) with commission of any of the offenses
enumerated in paragraph (1)(b) of this certification; and
(d) Have not within a three-year period preceding this application/proposal had one or
more public transactions (Federal, State, or local) terminated for cause or default.
I understand that a false statement on this certification may be grounds for rejection of this
proposal or termination of the award. In addition, under 18 USC Sec. 1001, a false statement
may result in a fine of up to $10,000 or imprisonment for up to 5 years, or both.
Typed Name and Title of Authorized Representative
Signature of Authorized Representative Date
I am unable to certify to the above statements. May explanation is attached.
EPA FORM 5700-49 (11-88)
EPA Project Control Number
ATTACHMENT H
SUPPLEMENTARY USEPA / WIFIA PROFESSIONAL SERVICES CONTRACT CLAUSES
ECONOMIC AND MISCELLANEOUS AUTHORITIES
DEBARMENT AND SUSPENSION AND PROHIBITIONS RELATING TO VIOLATIONS OF CWA AND
CAA WITH RESPECT TO FEDERAL CONTRACTS, GRANTS, OR LOANS
Debarment and Suspension. Contractor certifies that it will not knowingly enter into a contract with anyone
who is ineligible under the 2 CFR part 180 and part 1532 (per Executive Order 12549, 51 FR 6370, February
21, 1986) or who is prohibited under Section 306 of the Clean Air Act or Section 508 of the Clean Water
Act to participate in the [Project]. Suspension and debarment information can be accessed at
http://www.sam.gov. Contractor represents and warrants that it has or will include a term or conditions
requiring compliance with this provision in all of its subcontracts under this Agreement.
NEW RESTRICTIONS ON LOBBYING
Federal Lobbying Restrictions (31 U.S.C 1352). Recipients of federal financial assistance may not pay
any person for influencing or attempting to influence any officer or employee of a federal agency, a member
of Congress, an officer or employee of Congress, or an employee of a member of Congress with respect
to the award, continuation, renewal, amendment, or modification of a federal grant, loan, or contract. These
requirements are implemented for USEPA in 40 CFR Part 34, which also describes types of activities, such
as legislative liaison activities and professional and technical services, which are not subject to this
prohibition. Upon award of this contract, Contractor shall complete and submit to the City the certification
and disclosure forms in Appendix A and Appendix B to 40 CFR Part 34. Contractor shall also require all
subcontractors and suppliers of any tier awarded a subcontract over $100,000 to similarly complete and
submit the certification and disclosure forms pursuant to the process set forth in 40 CFR 34.110.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #11
Tracking Number
PW 2024-63
Northwest Elevated Water Storage Tank – Design Engineering Agreement
Public Works Committee – July 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
A proposed design engineering agreement from EEI for the Northwest Elevated Water
Storage Tank (EWST). This tank is needed as part of the Lake Michigan project. This is
budgeted for in the approved FY 25 budget.
Background
As part of our Lake Michigan allocation, we are required to have 2 days’ worth of water
in storage. To meet this rule, the city has proposed to construct an EWST in the northwest
quadrant of the city and a standpipe in the southeast quadrant. This agreement addresses the
northwest EWST and its design.
Last month, the committee saw the design engineering agreements for the receiving
stations. This month is the storage tanks that we are going to pump water into from those
receiving stations. These are under separate contracts because this type of work is so specialized
and there are very few bidders. We want to keep this separate from the receiving stations to
ensure quality bidders.
EEI is proposing a fixed fee of $258,234. This is $8,234 over the budgeted amount. In
addition to the standard engineering work, this contract also includes legal surveying, State
Revolving Fund coordination, subcontractor oversight and coordination for geotechnical and
landscape Architects. Lastly, this contract includes some design work for water main to get to
the site from the intersection of Eldamain and Corneils Rd.
This is in the approved budget in the water fund line-item Water Sourcing-DWC 51-510-
60-00-6011.
Recommendation
Staff Recommends approval of this contract with EEI in the amount of $258,234.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: July 10, 2024
Subject: Northwest EWST Design Engineering Agreement
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 1
Northwest Elevated Water Storage Tank
United City of Yorkville
Agreement for Professional Services – Design Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
The Engineer shall furnish the necessary personnel, materials, equipment and
expertise to make the necessary investigations, analysis and calculations along with
exhibits, cost estimates and narrative, to complete all necessary engineering
services to the City as indicated on the included Attachment A. Design Engineering
services shall be provided as indicated on the Scope of Services on Attachment B.
The Engineer shall work with the City to develop a contracting and bidding schedule
consistent with available funding. All Engineering will be in accordance with all City,
Standard Specifications for Water and Sewer Construction in Illinois, Illinois
Environmental Protection Agency, and Illinois Department of Transportation
requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the
ENGINEER shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to ENGINEER:
ENGINEER shall receive as compensation for all work and services to be performed
herein an amount based on the Estimated Level of Effort and Associated Cost
included in Attachment C. Design Engineering will be paid for monthly based on the
percentage of the project that is complete. The Fixed Fee amount for the Design
Engineering is $258,234.00. The hourly rates for this project are shown in
Attachment E. All payments will be made according to the Illinois State Prompt
Payment Act and not less than once every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
written notice of any change in the rates specified in Section C hereof (or on any
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 2
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
E. Ownership of Records and Documents:
ENGINEER agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. ENGINEER agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the freedom of information act or
if already previously disclosed by a third party. Upon termination of this agreement,
ENGINEER agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by ENGINEER without Contractor’s
consent. Modifications of any signed duplicate original document not authorized by
ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kane County, Illinois.
G. Independent ENGINEER:
ENGINEER shall have sole control over the manner and means of providing the
work and services performed under this agreement. The City’s relationship to the
ENGINEER under this agreement shall be that of an independent ENGINEER.
ENGINEER will not be considered an employee to the City for any purpose.
H. Certifications:
Employment Status: The ENGINEER certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to perform
the service.
Anti-Bribery: The ENGINEER certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or admission
of bribery or attempted bribery of an officer or employee of the State of Illinois or any
other state.
Loan Default: If the ENGINEER is an individual, the ENGINEER certifies that he/she
is not in default for a period of six months or more in an amount of $600 or more on
the repayment of any educational loan guaranteed by the Illinois State Scholarship
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 3
Commission made by an Illinois institution of higher education or any other loan
made from public funds for the purpose of financing higher education (5 ILCS 385/3).
Felony Certification: The ENGINEER certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The ENGINEER certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720 Illinois
Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The ENGINEER certifies that it is in compliance with the Drug
Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective date of
this contract. The Drug Free Workplace Act requires, in part, that Contractors, with
25 or more employees certify and agree to take steps to ensure a drug free
workplace by informing employees of the dangers of drug abuse, of the availability
of any treatment or assistance program, of prohibited activities and of sanctions that
will be imposed for violations; and that individuals with contracts certify that they will
not engage in the manufacture, distribution, dispensation, possession, or use of a
controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
ENGINEER agrees to comply with applicable provisions of the Illinois Human Rights
Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the Americans with
Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the rules applicable
to each. The equal opportunity clause of Section 750.10 of the Illinois Department
of Human Rights Rules is specifically incorporated herein. The ENGINEER shall
comply with Executive Order 11246, entitled Equal Employment Opportunity, as
amended by Executive Order 11375, and as supplemented by U.S. Department of
Labor regulations (41 C.F.R. Chapter 60). The ENGINEER agrees to incorporate
this clause into all subcontracts under this Contract.
International Boycott: The ENGINEER certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979 or
the regulations of the U.S. Department of Commerce promulgated under that Act
(30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires
the ENGINEER (and any subcontractors) to maintain, for a period of 3 years after
the later of the date of completion of this Contract or the date of final payment under
the Contract, all books and records relating to the performance of the Contract and
necessary to support amounts charged to the City under the Contract. The Contract
and all books and records related to the Contract shall be available for review and
audit by the City and the Illinois Auditor General. If this Contract is funded from
contract/grant funds provided by the U.S. Government, the Contract, books, and
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 4
records shall be available for review and audit by the Comptroller General of the
U.S. and/or the Inspector General of the federal sponsoring agency. The
ENGINEER agrees to cooperate fully with any audit and to provide full access to all
relevant materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The ENGINEER certifies that
he/she is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien
The Internal Revenue Service requires that taxes be withheld on payments made to
non resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the ENGINEER certifies that its
Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
ENGINEER shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on account
of damage to or destruction of property resulting from the performance of work
under this agreement by ENGINEER or its Subcontractors, or due to or arising in
any manner from the wrongful act or negligence of ENGINEER or its Subcontractors
of any employee of any of them. In the event that the either party shall bring any
suit, cause of action or counterclaim against the other party, the non-prevailing party
shall pay to the prevailing party the cost and expenses incurred to answer and/or
defend such action, including reasonable attorney fees and court costs. In no event
shall the either party indemnify any other party for the consequences of that party’s
negligence, including failure to follow the ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of the
types of services rendered hereunder. (Not applicable as having been previously
supplied)
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 5
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided on the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed by
both parties. In the event that any provisions of this agreement shall be held to be
invalid or unenforceable, the remaining provisions shall be valid and binding on the
parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimated Level of Effort and Associated Cost
Attachment D: Anticipated Project Schedule
Attachment E: 2024 Standard Schedule of Charges
Attachment F: IEPA Professional Services Contract Clauses
Attachment G: USEPA / WIFIA Professional Services Contract Clauses
L. Notices:
All notices required to be given under the terms of this agreement shall be given
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time-to-time substitute addresses
or persons in connection with required notices.
Agreed to this ___day of _________, 2024.
United City of Yorkville Engineering Enterprises, Inc.:
_________________________________ _______________________________
John Purcell Bradley P. Sanderson, P.E.
Mayor Chief Operating Officer /President
_________________________________ ______________________________
Jori Behland Angela R. Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 1
ATTACHMENT A – STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing. However, to
the extent that the Scope of Work differs from the Standard Terms and Conditions, the Scope of Work document controls.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furnish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction documents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provision of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinion
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in electronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at the
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations. ENGINEER
agrees to cooperate with the OWNER, as necessary, to remediate a Hazardous Condition, but same may result in additional costs to
the OWNER.
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 2
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have incurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warranty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a) Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b) Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c) Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d) Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against the ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to carry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions being taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting such force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of invoices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of the
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonable fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 1
Northwest Elevated Water Storage Tank (Spheroid) – Design Engineering
United City of Yorkville, IL
Attachment B – Scope of Services
The United City of Yorkville requires Design Engineering services to construct a water spheroid
as part of the connection needs to receive water supply from DuPage Water Commission
(DWC). Items include design of a new elevated water storage tank (spheroidal style) along with
approximately 1,500 feet of water main and valves to the point of connection to the existing
water main. The location of the tank will be confirmed as part of this scope, but it is currently
anticipated to be approximately 1,500 feet north of the intersection of Eldamain Road and
Corneils Road on the east side of the road.
The City has begun implementing a multi-year program to construct required infrastructure to
connect to receive water supply from DWC utilizing funds from the IEPA Public Water Supply
Loan Program (PWSLP). To be eligible for the loan, the City has an approved Drinking Water
Project Plan.
The following list of work items establishes the scope of engineering services for this project:
PROJECT FACILITATION AND ADMINISTRATION:
0.01 Project Management and Administration
• Management of Personnel and the Engineering Contract
• Budget Tracking
• Coordination with the City and Subconsultants
0.02 On-going City Communication/Coordination Updates
0.03 Project Kickoff and Progress Review Meetings (3 Total Meetings with City plus Internal
Meetings)
• Project Kick-Off Meeting Between the City and EEI
o Prepare Discussion Outline and Minutes
o Attend Meeting at City Hall or Virtual
o Site Visit After Meeting
• Two (2) Design Progress Meetings Between the City and EEI prior to Bidding
o Prepare Discussion Outlines and Minutes
o Attend Meetings at City Hall or Virtual
PRELIMINARY DESIGN PHASE:
1.01 Confirm the Size of the EWST (2.0 MG)
1.02 Confirm the location of the EWST
1.03 Prepare Summary of Potential Bidders / Tank Erectors
1.04 Coordinate Soil Borings and Soils Report
1.05 Conduct Site Visits (2) - Pre and Post Design
1.06 Perform a JULIE Design Request
1.07 Prepare Draft Site Plan (Rough grading, Water Main, Storm Sewer/Drainage)
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 2
1.08 Prepare Preliminary Routing of Off-site Water Main (Approximately 1,500 feet)
1.09 Prepare and Obtain the Following Permits/Sign-offs
• IDNR - EcoCAT Sign-off
• SHPO/HARGIS - Historic Sign-off
• Stormwater Permitting (Assumes No Wetlands, No Floodplain)
• IDNR - Notice of Intent (NOI)
• City Building Permit
• Federal Aviation Administration
1.10 Electrical/ComEd Application Preparation and Initial Coordination
1.11 Facilitate Mixing System Discussions with Vendors
1.12 Facilitate Cathodic Protection Discussions with Vendors
1.13 Prepare/Review Coating Systems and Tank Optional Features with City Staff
1.14 Develop Tank Orientation/Tank Cross-Section Plans
1.15 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City
1.16 Telecommunication Facility Location Coordination
1.17 Prepare 30% Complete Drawings and Specifications
1.18 Present Final Layout and Logo to City Council/PW Committee
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications
2.02 Coordination with Landscape Architect
2.02 Prepare 95% Complete Drawings and Specifications
2.03 Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
2.04 Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water Supplies)
2.05 Prepare 95% Engineer's Opinion of Probable Construction Cost
2.06 SCADA Integration and Design
2.07 Complete Plans and Specifications to 100%
2.08 Prepare 100% Engineer's Opinion of Probable Construction Cost
BIDDING AND CONTRACTING PHASE
3.01 Prepare Final Bid Documents and Coordinate Advertise for Bid
3.02 Respond to Bidder Inquiries/Prepare Addenda
3.03 Maintain Bidders List, Coordinate Addenda and Distribution Utilizing Quest
3.04 Prepare IEPA - Notice of Intent
3.05 Prepare for and Attend Bid Opening
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract
3.07 Attend City Council/PW Committee Meeting for Anticipated Contract Award
FUNDING ASSISTANCE
4.01 Preparing and Coordinating Illinois PWSLP Loan Application
• Prepare Loan Application Form
o Loan Program Certifications and Resolutions
Disbarment, Suspension, and Other Responsibility Matters
Intent Regarding National Flood Insurance
Project Site Rights of Way, Easements, and Permits
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 3
Taxpayer ID (FEIN) Certifications
Five Officer Certification Form
Tax Compliance Certificate and Agreement
Authorizing Representative to Sign Loan Documents
Certified Bond Ordinance
o Existing Water Rate Ordinance
o Water System Information
o Project Completion Schedule and Estimates
• Financial Coordination with the City
o Current and Future Debt
o Comprehensive Financial Projections (5 years)
o Audited Financial Statements
o Bond Ratings
4.02 Coordinating WIFIA Loan
• Coordination with USEPA to furnish required documentation necessary for funding
(executed engineering agreements, final bid and contract documents, executed
construction contracts)
• Advertisement for DBE’s consistent with good faith requirements regarding use of
DBE’s
SURVEYING
5.01 Perform and prepare a topological survey for 225’ x 225’ site plus approximately 1500
feet of water main
• Perform Field Topographic and Boundary Work
• Process Topographic Survey
5.02 Prepare an ALTA Survey for the 225’ x 225’ site
5.03 Prepare Plat of Easement or Easement Exhibit for the Temporary Easement associated
with the 1,500 feet of Off-site Water Main
DIRECT EXPENSES
The following scope of services will be provided by EEI’s subconsultants:
• Electrical/SCADA (Consultant To Be Determined)
• Geotechnical and CCDD (Rubino Engineering, Inc.)
o Four (4) Soil Borings at a Maximum Depth of 100’ (or to refusal)
o Three (3) Soil Borings at a Maximum Depth of 25’
o Prepare Geotechnical Report and CCDD Analysis
o Prepare LPC 662/663 Permit
• Archaeological Survey
• Title Commitment
• Landscape Architecture
NOTES AND EXCLUSIONS
• Assumed no stormwater detention will be required.
• The above scope of services does not include the following:
o Construction Engineering
UNITED CITY OF YORKVILLE NORTHWEST ELEVATED WATER STORAGE TANK
PAGE 4
o Site Survey Outside of Scope Identified in Scope Item 5.01
o Land Acquisition and Property Negotiations
o Environmental Surveys
o WIFIA Loan Application or Loan Processing/Coordination other than items noted in
above scope
o New Electrical Service Fees
o Engineering Related to an Altitude Valve
o Engineering related to a Chlorine Analyzer Within the Tank
o Permitting and Sign-off Coordination Other Than Those identified in 1.09 and 2.04
The above scope summarizes the work items that will be completed for this contract. Additional
work items, including additional meetings beyond the meetings defined in the above scope
shall be considered outside the scope of the base contract and will be billed in accordance with
EEI’s Standard Schedule of Charges (Attachment E) in affect at the time the extra work is
performed.
ATTACHMENT C: ESTIMATED LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2418-P
PROJECT TITLE DATE PREPARED BY
Northwest Elevated Water Storage Tank (Spheroid)
ROLE PIC QC/QA SPM PM SPE 2 PE SPT 2 SPT 1 ADMIN
RATE $246 $241 $234 $210 $200 $168 $175 $164 $70
PROJECT FACILITATION & ADMINISTRATION
0.01 Project Management and Administration 2 12 14 3,012$
0.02 On-going City Communication/Coordination/Updates 12 4 16 3,692$
0.03 9 9 12 3 12 45 9,519$
Project Facilitation & Administration Subtotal: 11 21 - 24 7 12 - - - 75 16,223$
PRELIMINARY DESIGN PHASE
1.01 Confirm the Size of the EWST (2.0 MG) 1 4 5 1,210$
1.02 Confirm the location of the EWST 4 2 2 8 1,886$
1.03 Prepare Summary of Potential Bidders / Tank Erectors 1 2 2 4 9 1,733$
1.04 Coordinate Soil Borings and Soils Report 1 1 4 4 10 1,823$
1.05 Conduct Site Visits (2) - Pre and Post Design 6 6 6 18 3,714$
1.06 Perform a JULIE Design Request 2 6 8 1,428$
1.07 Prepare Draft Site Plan (Rough grading, Water Main, Storm Sewer/Drainage) 2 8 1 8 12 31 5,806$
1.08 Prepare Preliminary Routing of Off-site Water Main (Approximately 1,500 feet) 2 8 8 12 30 5,606$
1.09 - -$
1 2 3 546$
1 2 4 7 1,246$
Stormwater Permitting (Assumes No Wetlands, No Floodplain)1 8 2 11 2,146$
1 2 3 546$
City Building Permit 1 1 2 378$
Federal Aviation Administration 1 2 4 7 1,246$
1.10 Electrical/ComEd Application and Initial Coordination 4 16 16 36 7,012$
1.11 Facilitate Mixing System Discussions with Vendors 2 4 4 8 18 3,466$
1.12 Facilitate Cathodic Protection Discussions with Vendors 2 4 4 4 14 2,794$
1.13 Prepare/Review Coating Systems and Tank Optional Features with City Staff 2 4 4 4 14 2,794$
1.14 Develop Tank Orientation/Tank Cross-Section Plans 2 6 12 20 3,650$
1.15 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City 1 4 4 4 24 37 6,658$
1.16 Telecommunication Facility Location Coordination 4 24 28 4,736$
1.17 Prepare 30% Complete Drawings and Specifications 4 8 8 12 32 6,212$
1.18 2 2 492$
Preliminary Design Phase Subtotal: 8 38 - 75 41 83 36 72 - 353 67,128$
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications 16 16 16 48 9,184$
2.02 1 1 4 6 1,034$
2.03 4 40 8 40 40 132 24,244$
2.04 4 4 8 1,804$
2.05 1 4 6 11 2,089$
2.06 1 2 1 12 16 2,877$
2.07 SCADA Integration and Design 2 4 4 8 18 3,466$
2.08 Complete Plans and Specifications to 100% 4 2 4 2 8 12 32 6,018$
2.09 1 1 2 1 2 7 1,443$
Final Design Phase Subtotal: 5 15 - 77 32 77 - 72 - 278 52,159$
BIDDING AND CONTRACTING PHASE
3.01 1 4 2 8 15 2,825$
3.02 Respond to Bidder Inquiries/Prepare Addenda 6 12 6 16 40 7,854$
3.03 4 4 280$
3.04 Prepare IEPA - Notice of Intent 2 2 336$
3.05 Prepare for and Attend Bid Opening 4 4 2 10 1,652$
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract 1 4 2 7 1,053$
3.07 2 2 492$
Bidding and Contracting Phase Subtotal: 2 8 - 20 8 34 - - 8 80 14,492$
FUNDING ASSISTANCE
4.01 Preparing and Coordinating Illinois PWSLP Loan Application 4 16 24 60 104 19,960$
4.02 Coordinating WIFIA Loan 8 16 24 4,368$
Funding Assistance Subtotal: 4 16 - 32 - 76 - - - 128 24,328$
SURVEYING
5.01 Surveying (Topographic Survey, ALTA Survey, and Plat of Easement/Easement Exhibit) 31 18 49 10,404$
Surveying Subtotal: - - 31 - - - 18 - - 49 10,404$
30 98 31 228 88 282 54 144 8 963 184,734
EEI STAFF
PIC Principal In Charge 500$
SPM Senior Project Manager Vehicle Charges/Mileage = 200$
PM Project Manager Electrical/SCADA = 30,000$
SPE 2 Senior Project Engineer II 35,000$
PE Project Engineer 5,000$
SPT 2 Senior Project Technician II Title Commitment = 800$
SPT 1 Senior Project Technician I 2,000$
ST Senior Technician DIRECT EXPENSES = 73,500$
ADMIN Adminstrative Assistant
184,734$
184,734$
258,234$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
7/9/24 MLP
TASK
NO.TASK DESCRIPTION HOURS COST
SHPO/HARGIS - Historic Sign-off
Project Initiation & Progress Meetings (3 Total Meetings with City plus internal review meetings)
Permits/Sign-offs
IDNR - EcoCAT Sign-off
IDNR - Notice of Intent (NOI)
PROJECT TOTAL:
DIRECT EXPENSES
Printing =
Geotechnical and CCDD =
Coordinate with Landscape Architect
Present Final Layout and Logo to City Council/PW Committee
TOTAL COSTS
Maintain Bidders List, Coordinate Addenda and Distribution - Use Quest
Attend City Council/PW Committee Meeting for Anticipated Contract Award
Prepare 95% Complete Drawings and Specifications
Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water Supplies)
Prepare 95% Engineer's Opinion of Probable Construction Cost
Prepare 100% Engineer's Opinion of Probable Construction Cost
Prepare Final Bid Documents and Coordinate Advertise for Bid
LABOR SUMMARY
EEI Labor Expenses =
TOTAL LABOR EXPENSES
Landscape Architect =
Archaeological Survey =
ATTACHMENT D: ESTIMATED SCHEDULE
CLIENT PROJECT NUMBER
United City of Yorkville YO2418-P
PROJECT TITLE DATE PREPARED BY
Northwest Elevated Water Storage Tank (Spheroid)MLP
JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY
PROJECT FACILITATION & ADMINISTRATION
0.01 Project Management and Administration
0.02 On-going City Communication/Coordination/Updates
0.03
PRELIMINARY DESIGN PHASE
1.01 Confirm the Size of the EWST (2.0 MG)
1.02 Confirm the location of the EWST
1.03 Prepare Summary of Potential Bidders / Tank Erectors
1.04 Coordinate Soil Borings and Soils Report
1.05 Conduct Site Visits (2) - Pre and Post Design
1.06 Perform a JULIE Design Request
1.07
1.08 Prepare Preliminary Routing of Off-site Water Main (Approx. 1,500 feet)
1.09
Stormwater Permitting (Assumes No Wetlands, No Floodplain)
City Building Permit
Federal Aviation Administration
1.10 Electrical/ComEd Application and Initial Coordination
1.11 Facilitate Mixing System Discussions with Vendors
1.12 Facilitate Cathodic Protection Discussions with Vendors
1.13
1.14 Develop Tank Orientation/Tank Cross-Section Plans
1.15 Prepare Logo Renderings (3) and Facilitate Logo Discussion with City
1.16 Telecommunication Facility Location Coordination
1.17 Prepare 30% Complete Drawings and Specifications
1.18
FINAL DESIGN PHASE
2.01 Prepare 60% Complete Drawings and Specifications
2.02
2.03
2.04
2.05
2.06
2.07 SCADA Integration and Design
2.08 Complete Plans and Specifications to 100%
2.09
BIDDING AND CONTRACTING PHASE
3.01
3.02 Respond to Bidder Inquiries/Prepare Addenda
3.03
3.04 Prepare IEPA - Notice of Intent
3.05 Prepare for and Attend Bid Opening
3.06 Assist City in Review of Bids and Prepare Bid Tabulation/Contract
3.07
FUNDING ASSISTANCE
4.01 Preparing and Coordinating Illinois PWSLP Loan Application
4.02 Coordinating WIFIA Loan
SURVEYING
5.01
52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
Prepare/Review Coating Systems and Tank Optional Features with City
Staff
7/9/24
TASK
NO.TASK DESCRIPTION 2024 2025
Project Initiation & Progress Meetings (3 Total Meetings with City plus
Prepare Draft Site Plan (Rough grading, Water Main, Storm
Sewer/Drainage)
Present Final Layout and Logo to City Council/PW Committee
Prepare 95% Complete Drawings and Specifications
IDNR - Notice of Intent (NOI)
Permits/Sign-offs
IDNR - EcoCAT Sign-off
SHPO/HARGIS - Historic Sign-off
Surveying (Topographic Survey, ALTA Survey, and Plat of
Easement/Easement Exhibit)
Coordinate with Landscape Architect
IEPA REVIEW
Attend City Council/PW Committee Meeting for Anticipated Contract Award
and Coordinate Contracts
Prepare Final Bid Documents and Coordinate Advertise for Bid
Maintain Bidders List, Coordinate Addenda and Distribution - Use Quest
Prepare Basis of Design for EWST for IEPA Permit (Public Water Supplies)
Prepare, Coordinate, and Submit IEPA Permit Applications (Public Water
Supplies)
Prepare 95% Engineer's Opinion of Probable Construction Cost
Prepare 100% Engineer's Opinion of Probable Construction Cost
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00
Principal E-3 $241.00
Senior Project Manager E-2 $234.00
Project Manager E-1 $210.00
Senior Project Engineer/Surveyor II P-6 $200.00
Senior Project Engineer/Surveyor I P-5 $186.00
Project Engineer/Surveyor P-4 $168.00
Senior Engineer/Surveyor P-3 $155.00
Engineer/Surveyor P-2 $140.00
Associate Engineer/Surveyor P-1 $127.00
Senior Project Technician II T-6 $175.00
Senior Project Technician I T-5 $164.00
Project Technician T-4 $153.00
Senior Technician T-3 $140.00
Technician T-2 $127.00
Associate Technician T-1 $111.00
GIS Technician II G-2 $125.00
GIS Technician I G-1 $114.00
Engineering/Land Surveying Intern I-1 $ 82.00
Executive Administrative Assistant A-4 $ 77.00
Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
ATTACHMENT E - STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024
ATTACHMENT F
IEPA PROFESSIONAL SERVICES CONTRACT CLAUSES
Audit and Access to Records Clause:
A. Books, records, documents and other evidence directly pertinent to performance of PWSLP/WPCLP
loan work under this agreement shall be maintained in accordance with generally accepted
Accounting Principles. The Agency or any of its authorized representatives shall have access to the
books, records, documents and other evidence for the purpose of inspection, audit and copying.
Facilities shall be provided for access and inspection.
B. Audits conducted pursuant to this provision shall be in accordance with auditing standards generally
accepted in the United States of America.
C. All information and reports resulting from access to records pursuant to the above shall be disclosed
to the Agency. The auditing agency shall afford the engineer an opportunity for an audit exit
conference and an opportunity to comment on the pertinent portions of the draft audit report.
D. The final audit report shall include the written comments, if any, of the audited parties.
E. Records shall be maintained and made available during performance of project services under this
agreement and for three years after the final loan closing. In addition, those records that relate to any
dispute pursuant to the Loan Rules Section 365.650 or Section 662.650 (Disputes) or litigation or the
settlement of claims arising out of project performance or costs or items to which an audit exception
has been taken, shall be maintained and made available for three years after the resolution of the
appeal, litigation, claim or exception.
Covenant Against Contingent Fees:
The professional services contractor warrants that no person or selling agency has been employed or
retained to solicit or secure this contract upon an agreement or understanding for a commission,
percentage, brokerage, or contingent fee, excepting bonafide employees. For breach or violation of this
warranty, the loan recipient shall have the right to annul this agreement without liability or in its discretion
to deduct from the contract price or consideration or otherwise recover, the full amount of such
commission, percentage, brokerage, or contingent fee.
Certification Regarding Debarment, Suspension and Other Responsibility Matters:
Form EPA 5700-49 is signed and attached as part of Attachment G.
USEPA Nondiscrimination Clause:
The contractor (engineer) shall not discriminate on the basis of race, color, national origin or sex in the
performance of this contract. The contractor shall carry out applicable requirements of 40 CFR Part 33 in
the award and administration of contracts awarded under EPA financial assistance agreements. Failure
by the contractor to carry out these requirements is a material breach of this contract which may result in
the termination of this contract or other legally available remedies.
USEPA Fair Share Percentage Clause:
The engineer agrees to take affirmative steps to assure that disadvantaged business enterprises are
utilized when possible as sources of supplies, equipment, construction and services in accordance with
the [WPC or PWS] Loan Program rules. As required by the award conditions of USEPA's Assistance
Agreement with Illinois EPA, the engineer acknowledges that the fair share percentages are 5% for MBEs
& 12% for WBEs”.
United States Environmental Protection Agency
Washington, D.C. 20460
Certification Regarding
Debarment, Suspension, and Other Responsibility Matters
The prospective participant certifies to the best of its knowledge and belief that it and its
principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible,
or voluntarily excluded from covered transactions by any Federal department or
agency;
(b) Have not within a three year period preceding this proposal been convicted of or had
a civil judgment rendered against them for commission of fraud or a criminal offense
in connection with obtaining, attempting to obtain, or performing a public: (Federal,
State, or local) transaction or contract under a public transaction; violation of Federal
or State antitrust statutes or commission of embezzlement, theft, forgery, bribery,
falsification or destruction of records, making false statements, or receiving stolen
property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a
government entity (Federal, State, or local) with commission of any of the offenses
enumerated in paragraph (1)(b) of this certification; and
(d) Have not within a three-year period preceding this application/proposal had one or
more public transactions (Federal, State, or local) terminated for cause or default.
I understand that a false statement on this certification may be grounds for rejection of this
proposal or termination of the award. In addition, under 18 USC Sec. 1001, a false statement
may result in a fine of up to $10,000 or imprisonment for up to 5 years, or both.
Typed Name and Title of Authorized Representative
Signature of Authorized Representative Date
I am unable to certify to the above statements. May explanation is attached.
EPA FORM 5700-49 (11-88)
EPA Project Control Number
ATTACHMENT G
SUPPLEMENTARY USEPA / WIFIA PROFESSIONAL SERVICES CONTRACT CLAUSES
ECONOMIC AND MISCELLANEOUS AUTHORITIES
DEBARMENT AND SUSPENSION AND PROHIBITIONS RELATING TO VIOLATIONS OF CWA AND
CAA WITH RESPECT TO FEDERAL CONTRACTS, GRANTS, OR LOANS
Debarment and Suspension. Contractor certifies that it will not knowingly enter into a contract with anyone
who is ineligible under the 2 CFR part 180 and part 1532 (per Executive Order 12549, 51 FR 6370, February
21, 1986) or who is prohibited under Section 306 of the Clean Air Act or Section 508 of the Clean Water
Act to participate in the [Project]. Suspension and debarment information can be accessed at
http://www.sam.gov. Contractor represents and warrants that it has or will include a term or conditions
requiring compliance with this provision in all of its subcontracts under this Agreement.
NEW RESTRICTIONS ON LOBBYING
Federal Lobbying Restrictions (31 U.S.C 1352). Recipients of federal financial assistance may not pay
any person for influencing or attempting to influence any officer or employee of a federal agency, a member
of Congress, an officer or employee of Congress, or an employee of a member of Congress with respect
to the award, continuation, renewal, amendment, or modification of a federal grant, loan, or contract. These
requirements are implemented for USEPA in 40 CFR Part 34, which also describes types of activities, such
as legislative liaison activities and professional and technical services, which are not subject to this
prohibition. Upon award of this contract, Contractor shall complete and submit to the City the certification
and disclosure forms in Appendix A and Appendix B to 40 CFR Part 34. Contractor shall also require all
subcontractors and suppliers of any tier awarded a subcontract over $100,000 to similarly complete and
submit the certification and disclosure forms pursuant to the process set forth in 40 CFR 34.110.
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #12
Tracking Number
PW 2024-64
YBSD Water Main Extension – Recommendation of Award
Public Works Committee – July 16, 2024
Majority
Consideration of Contract Award
Please see the attached memo.
Brad Sanderson Engineering
Name Department
Bids were received, opened and tabulated for work to be done on the YBSD Water Main
Extension at 11:00 a.m., June 6, 2024. Representatives of contractors bidding the project and our
firm were in attendance. A tabulation of the bids and the engineer’s estimate is attached for your
information and record.
The low bidder performed work for the City in 2021 on the Elizabeth Street and Appletree Court.
Their performance on the project was not up to City standards. Issues noted were as follows:
Daily production was significantly less than expected which led to a longer time period
that residents were disrupted. This also led to increased construction engineering fees.
Completion of the punchlist work and final project restoration was challenging and took
much longer than expected. The restoration was not fully accepted until one year after
substantial completion.
Overall project management and scheduling for the completion of the various tasks was
not to City expectations (water main, water services, paving, grading and landscaping).
The YBSD Water Main project involves complex construction as we need to cross Blackberry
Creek and River Road which requires coordination and efficiency. The following clause is
within the bid documents:
The OWNER reserves the right to reject any and all bid proposals, to contract work with
whomever and in whatever manner the OWNER decides, to abandon the work entirely,
or to waive any informality or non-substantive irregularity as the interest of the OWNER
may require. The OWNER reserves the right to award a bid proposal based on any
combination of the Base Bid and/or Alternates at the OWNER’s choosing.
Therefore, we recommend the acceptance of the bid and approval of award be made to the 2nd
lowest bidder, Winninger Excavating, Inc., 1211 Deer Street, Yorkville, IL 60560, in the total
amount of $517,247.46.
If you have any questions or require additional information, please let us know.
Memorandum
To: Bart Olson, City Administrator
From: Brad Sanderson, EEI
CC: Eric Dhuse, Director of Public Works
Jori Behland, City Clerk
Rob Fredrickson, Finance Director
Date: June 10, 2024
Subject: YBSD Water Main Extension
Page 1 of 1
BID TABULATION ENGINEER'S ESTIMATE H. Linden & Sons Sewer and Water, Inc.Conley Excavating, Inc.Performance Const & Eng LLC
BIDS RECEIVED 11:00 A.M. 06/06/2024 52 Wheeler Road 722 E. South St., Unit D 1555 Gramercy Pl 217 W. John Street
Sugar Grove, IL 60554 Plano, IL-60545 Morris, IL-60450 Plano, IL-60545
BASE BID TOTAL $527,182.00 $865,654.00 $608,993.00 $597,880.00
BID BOND X X X
SIGNED BID X X X
ADDENDUM NO. 1 X X X
ADDENDUM NO. 2 X X X
BID TABULATION Stokes Excavating, Inc.Winninger Excavating, Inc.Scanlon Excavating & Concrete, Inc.
BIDS RECEIVED 11:00 A.M. 06/06/2024 903 Daisyfield Rd 1211 Deer St 630 S 7000 W Rd
Rockford, IL-61102 Yorkville, IL-60560 Kankakee, IL-60901
BASE BID TOTAL $500,508.00 $517,247.46 $717,469.46
BID BOND X X X
SIGNED BID X X X
ADDENDUM NO. 1 X X X
ADDENDUM NO. 2 X X X
BID SUMMARY
YBSD WATER MAIN EXTENSION
UNITED CITY OF YORKVILLE
ENGINEERING ENTERPRISES, INC.
52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
BID TABULATION
YBSD WATER MAIN EXTENSION
UNITED CITY OF YORKVILLE
BIDS RECD 6/6/2024
ITEM UNIT UNIT UNIT UNIT UNIT UNIT UNIT
NO.DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 TREE REMOVAL AC 0.3 1,000.00$ 300.00$ 32,000.00$ 9,600.00$ 12,000.00$ 3,600.00$ 40,000.00$ 12,000.00$ 45,000.00$ 13,500.00$ 30,000.00$ 9,000.00$ 7,500.00$ 2,250.00$
2 TREE ROOT PRUNING EACH 1 50.00$ 50.00$ 150.00$ 150.00$ 200.00$ 200.00$ 500.00$ 500.00$ 250.00$ 250.00$ 200.00$ 200.00$ 500.00$ 500.00$
3 CONNECTION TO EXISTING WATER MAIN, 12-INCH EACH 1 7,000.00$ 7,000.00$ 10,000.00$ 10,000.00$ 15,000.00$ 15,000.00$ 3,450.00$ 3,450.00$ 6,000.00$ 6,000.00$ 8,000.00$ 8,000.00$ 7,000.00$ 7,000.00$
4 WATER MAIN, CLASS 52, WITH POLYETHYLENE WRAP, 12-INCH LF 780 185.00$ 144,300.00$ 305.00$ 237,900.00$ 175.00$ 136,500.00$ 184.00$ 143,520.00$ 425.00$ 331,500.00$ 269.00$ 209,820.00$ 225.00$ 175,500.00$
5 GATE VALVE (RESILIENT SEAT) IN 60" VAULT, 12-INCH EACH 3 7,000.00$ 21,000.00$ 12,000.00$ 36,000.00$ 800.00$ 2,400.00$ 9,650.00$ 28,950.00$ 10,000.00$ 30,000.00$ 20,000.00$ 60,000.00$ 9,500.00$ 28,500.00$
6 FIRE HYDRANT ASSEMBLY, WITH AUXILIARY VALVE, 6-INCH MJ EACH 1 9,400.00$ 9,400.00$ 12,000.00$ 12,000.00$ 10,000.00$ 10,000.00$ 9,430.00$ 9,430.00$ 8,500.00$ 8,500.00$ 15,000.00$ 15,000.00$ 10,000.00$ 10,000.00$
7 DUCTILE IRON FITTINGS LB 1,946 6.50$ 12,649.00$ 0.01$ 19.46$ 20.00$ 38,920.00$ 10.00$ 19,460.00$ 0.01$ 19.46$ 20.00$ 38,920.00$ 12.00$ 23,352.00$
8 WATER MAIN PROTECTION, PVC C-900, 18-INCH LF 57 160.00$ 9,120.00$ 150.00$ 8,550.00$ 150.00$ 8,550.00$ 153.00$ 8,721.00$ 150.00$ 8,550.00$ 4,000.00$ 228,000.00$ 130.00$ 7,410.00$
9 NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL - TYPE 1 TON 50 85.00$ 4,250.00$ 40.00$ 2,000.00$ 10.00$ 500.00$ 50.00$ 2,500.00$ 50.00$ 2,500.00$ 50.00$ 2,500.00$ 74.00$ 3,700.00$
10 NON-SPECIAL, NON-HAZARDOUS SOIL WASTE DISPOSAL - TYPE 2 TON 50 20.00$ 1,000.00$ 40.00$ 2,000.00$ 10.00$ 500.00$ 70.00$ 3,500.00$ 50.00$ 2,500.00$ 70.00$ 3,500.00$ 74.00$ 3,700.00$
11 ROCK EXCAVATION CY 30 300.00$ 9,000.00$ 150.00$ 4,500.00$ 15.00$ 450.00$ 300.00$ 9,000.00$ 100.00$ 3,000.00$ 525.00$ 15,750.00$ 300.00$ 9,000.00$
12 FOUNDATION MATERIAL CY 100 10.00$ 1,000.00$ 25.00$ 2,500.00$ 15.00$ 1,500.00$ 50.00$ 5,000.00$ 65.00$ 6,500.00$ 49.00$ 4,900.00$ 50.00$ 5,000.00$
13 EXPLORATORY EXCAVATION EACH 2 1.00$ 2.00$ 500.00$ 1,000.00$ 200.00$ 400.00$ 1,000.00$ 2,000.00$ 2,000.00$ 4,000.00$ 410.00$ 820.00$ 1,500.00$ 3,000.00$
14 STONE RIPRAP, CLASS A3 SY 100 8.00$ 800.00$ 85.00$ 8,500.00$ 25.00$ 2,500.00$ 69.00$ 6,900.00$ 200.00$ 20,000.00$ 214.00$ 21,400.00$ 100.00$ 10,000.00$
15 DISCONNECT AND ABANDON EXISTING WATER MAIN EACH 1 3,000.00$ 3,000.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$ 10,000.00$ 10,000.00$ 2,500.00$ 2,500.00$
16 INLET PROTECTION EACH 2 250.00$ 500.00$ 300.00$ 600.00$ 200.00$ 400.00$ 250.00$ 500.00$ 150.00$ 300.00$ 210.00$ 420.00$ 150.00$ 300.00$
17 WATER MAIN TESTING - PRESSURE AND DISINFECTION LS 1 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$ 4,000.00$ 4,000.00$ 3,000.00$ 3,000.00$ 6,000.00$ 6,000.00$ 5,000.00$ 5,000.00$ 2,500.00$ 2,500.00$
18 HOT-MIX ASPHALT PAVEMENT REMOVAL SY 23 25.00$ 575.00$ 60.00$ 1,380.00$ 15.00$ 345.00$ 50.00$ 1,150.00$ 25.00$ 575.00$ 20.00$ 460.00$ 10.00$ 230.00$
19 HOT-MIX ASPHALT PAVEMENT PATCH, 8"SY 23 160.00$ 3,680.00$ 200.00$ 4,600.00$ 153.00$ 3,519.00$ 317.00$ 7,291.00$ 150.00$ 3,450.00$ 200.00$ 4,600.00$ 70.00$ 1,610.00$
20 AGGREGATE DRIVEWAY REMOVAL AND REPLACEMENT SY 90 15.00$ 1,350.00$ 14.00$ 1,260.00$ 35.00$ 3,150.00$ 50.00$ 4,500.00$ 45.00$ 4,050.00$ 49.00$ 4,410.00$ 50.00$ 4,500.00$
21 FLOW DIVERSION OF BLACKBERRY CREEK LS 1 150,000.00$ 150,000.00$ 48,000.00$ 48,000.00$ 200,000.00$ 200,000.00$ 82,000.00$ 82,000.00$ 100,000.00$ 100,000.00$ 1,000.00$ 1,000.00$ 70,000.00$ 70,000.00$
22 RESTORATION SY 3,711 12.00$ 44,532.00$ 8.00$ 29,688.00$ 15.00$ 55,665.00$ 11.00$ 40,821.00$ 25.00$ 92,775.00$ 14.00$ 51,954.00$ 20.00$ 74,220.00$
23 WETLAND RESTORATION AC 1 25,000.00$ 25,000.00$ 33,000.00$ 33,000.00$ 21,000.00$ 21,000.00$ 170,300.00$ 170,300.00$ 25,000.00$ 25,000.00$ 10,000.00$ 10,000.00$ 2,500.00$ 2,500.00$
24 TRAFFIC CONTROL AND PROTECTION LS 1 20,000.00$ 20,000.00$ 30,000.00$ 30,000.00$ 57,781.00$ 57,781.00$ 12,500.00$ 12,500.00$ 15,000.00$ 15,000.00$ 130,000.00$ 130,000.00$ 50,000.00$ 50,000.00$
25 ALLOWANCE - ITEMS ORDERED BY THE ENGINEER UNIT 30,000 1.00$ 30,000.00$ 1.00$ 30,000.00$ 1.00$ 30,000.00$ 1.00$ 30,000.00$ 1.00$ 30,000.00$ 1.00$ 30,000.00$ 1.00$ 30,000.00$
BASE BID TOTAL 500,508.00$ 517,247.46$ 597,880.00$ 608,993.00$ 717,469.46$ 865,654.00$ 527,272.00$
CORRECTED NUMBERS FROM BID
630 S 7000 W Rd
Kankakee, IL-60901
Sugar Grove, IL 60554
722 E. South St., Unit D
Morris, IL-60450 Plano, IL-60545
ENGINEER'S ESTIMATE
1211 Deer St903 Daisyfield Rd 1555 Gramercy Pl 52 Wheeler Road
H. Linden & Sons Sewer and Water, Inc.Performance Const & Eng LLCBID TABULATION Winninger Excavating, Inc.Stokes Excavating, Inc.Conley Excavating, Inc.Scanlon Excavating & Concrete, Inc.
217 W. John Street
Plano, IL-60545
Yorkville, IL-60560Rockford, IL-61102
ENGINEERING ENTERPRISES, INC.
52 WHEELER ROAD, SUGAR GROVE, ILLINOIS
()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-W River StWest StKing StW Center St
W Main St
Engineering Enterprises, Inc.52 Wheeler RoadSugar Grove, Illinois 60554(630) 466-6700
ATTACHMENT EPROJECT LIMITS
www.eeiweb.com DATE
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
December 2023
YO2104
H:\GIS\PUBLIC\YORKVILLE\2022\
MJT
NO.REVISIONS ³United City of Yorkville800 Game Farm RoadYorkville, IL 60560630-553-4350www.yorkville.il.us
400 0200 Feet
Legend
UNKNOWN WATER MAIN3" WATER MAIN AND SMALLER
4" WATER MAIN
6" WATER MAN
8" WATER MAIN10" WATER MAIN
12" WATER MAIN
16" WATER MAIN
!(VALVE
GF HYDRANT
YO2104_YBSD Center Street W.M Exhibit Attachment E
PROPOSED 12" WATER MAIN(INCLUDED IN CONTRACT A)
PROPOSED 12"WATER MAIN
CENTER STREET WATER MAIN EXHIBIT
YBSD
Have a question or comment about this agenda item?
Call us Monday-Friday, 8:00am to 4:30pm at 630-553-4350, email us at agendas@yorkville.il.us, post at www.facebook.com/CityofYorkville,
tweet us at @CityofYorkville, and/or contact any of your elected officials at http://www.yorkville.il.us/320/City-Council
Agenda Item Summary Memo
Title:
Meeting and Date:
Synopsis:
Council Action Previously Taken:
Date of Action: Action Taken:
Item Number:
Type of Vote Required:
Council Action Requested:
Submitted by:
Agenda Item Notes:
Reviewed By:
Legal
Finance
Engineer
City Administrator
Community Development
Purchasing
Police
Public Works
Parks and Recreation
Agenda Item Number
New Business #13
Tracking Number
PW 2024-65
YBSD Water Main Extension – Construction Engineering Agreement
Public Works Committee – July 16, 2024
Majority
Approval
Please see the attached memo.
Eric Dhuse Public Works
Name Department
Summary
A proposed construction engineering agreement from EEI for the YBSD water main
extension on W. Center St. and Jaycee Pond at an estimated amount of $49,928 with direct costs
estimated at $25,000. This is a budgeted item in the approved FY 25 budget.
Background
YBSD needs a larger water main to service the plant expansion now and into the future.
With the River Rd. bridge as an obstacle, the water main will begin at the intersection of W.
Center and King Street and proceed west to Jaycee pond. From there it will turn south, cross the
Blackberry Creek and River Rd. to get to the YBSD plant expansion. EEI is proposing a
construction engineering agreement to oversee this complex project. The hourly cost is
estimated at $49,928 and an additional $25,000 for direct costs. The direct costs are related to
testing, wetland monitoring and maintenance, and fish sampling.
Per the IGA, YBSD is responsible for 87% of the cost of the project, including
construction engineering. These funds are to be given to the city before the project begins and
the city will be the lead agency for construction. This means that our share of the cost for the
proposed construction engineering agreement will be approximately ~$9,800. The entire project
is in the approved budget in the water fund in the water main replacement line item 51-510-60-
00-6025.
Recommendation
Staff recommends the approval of the construction engineering agreement with EEI in the
amount of $49,928 and an additional $25,000 for direct costs.
Memorandum
To: Public Works Committee
From: Eric Dhuse, Director of Public Works
CC: Bart Olson, City Administrator
Date: July 10, 2024
Subject: YBSD Water Main Construction Engineering Agreement
UNITED CITY OF YORKVILLE YBSD WATER MAIN EXTENSION
PAGE 1
YBSD Water Main Extension
United City of Yorkville
Professional Services Agreement – Construction Engineering
THIS AGREEMENT, by and between the United City of Yorkville, hereinafter
referred to as the "City" or “OWNER” and Engineering Enterprises, Inc. hereinafter
referred to as the "Contractor" or “ENGINEER” agrees as follows:
A. Services:
The ENGINEER shall furnish the necessary personnel, materials, equipment and
expertise to make the necessary investigations, analysis and calculations along with
exhibits, cost estimates and narrative, to complete all necessary engineering
services to the City as indicated on the included Attachment A. Construction
engineering will be provided for approximately 780 linear feet of 12-inch water main
improvements extending from Center Street to the future YBSD expansion location
on River Street, including the crossing of Blackberry Creek. (see Attachment E for
project limits). Engineering will be in accordance with all City, Standard
Specifications for Water and Sewer Construction in Illinois, Illinois Department of
Transportation, and Illinois Environmental Protection Agency requirements.
B. Term:
Services will be provided beginning on the date of execution of this agreement and
continuing, until terminated by either party upon 7 days written notice to the non-
terminating party or upon completion of the Services. Upon termination the
Contractor shall be compensated for all work performed for the City prior to
termination.
C. Compensation and maximum amounts due to Contractor:
ENGINEER shall receive as compensation for all work and services to be performed
herein, an amount based on the Estimate of Level of Effort and Associated Cost
included in Attachment C. Construction Engineering will be paid for Hourly (HR) at
the actual rates for services to be performed, currently estimated at $49,928. Direct
expenses are estimated at $25,000. The hourly rates for this project are shown in
the attached 2024 Standard Schedule of Charges (Attachment F). All payments will
be made according to the Illinois State Prompt Payment Act and not less than once
every thirty days.
D. Changes in Rates of Compensation:
In the event that this contract is designated in Section B hereof as an Ongoing
Contract, ENGINEER, on or before February 1st of any given year, shall provide
UNITED CITY OF YORKVILLE YBSD WATER MAIN EXTENSION
PAGE 2
written notice of any change in the rates specified in Section C hereof (or on any
attachments hereto) and said changes shall only be effective on and after May 1st
of that same year.
E. Ownership of Records and Documents:
Contractor agrees that all books and records and other recorded information
developed specifically in connection with this agreement shall remain the property
of the City. Contractor agrees to keep such information confidential and not to
disclose or disseminate the information to third parties without the consent of the
City. This confidentiality shall not apply to material or information, which would
otherwise be subject to public disclosure through the Freedom of Information Act or
if already previously disclosed by a third party. Upon termination of this agreement,
Contractor agrees to return all such materials to the City. The City agrees not to
modify any original documents produced by Contractor without Contractor’s
consent. Modifications of any signed duplicate original document not authorized by
ENGINEER will be at OWNER’s sole risk and without legal liability to the
ENGINEER. Use of any incomplete, unsigned document will, likewise, be at the
OWNER’s sole risk and without legal liability to the ENGINEER.
F. Governing Law:
This contract shall be governed and construed in accordance with the laws of the
State of Illinois. Venue shall be in Kendall County, Illinois.
G. Independent Contractor:
Contractor shall have sole control over the manner and means of providing the work
and services performed under this agreement. The City’s relationship with the
Contractor under this agreement shall be that of an independent contractor.
Contractor will not be considered an employee of the City for any purpose.
H. Certifications:
Employment Status: The Contractor certifies that if any of its personnel are an
employee of the State of Illinois, they have permission from their employer to perform
the service.
Anti-Bribery: The Contractor certifies it is not barred under 30 Illinois Compiled
Statutes 500/50-5(a) - (d) from contracting as a result of a conviction for or admission
of bribery or attempted bribery of an officer or employee of the State of Illinois or any
other state.
Loan Default: If the Contractor is an individual, the Contractor certifies that he/she is
not in default for a period of six months or more in an amount of $600 or more on
the repayment of any educational loan guaranteed by the Illinois State Scholarship
UNITED CITY OF YORKVILLE YBSD WATER MAIN EXTENSION
PAGE 3
Commission made by an Illinois institution of higher education or any other loan
made from public funds for the purpose of financing higher education (5 ILCS 385/3).
Felony Certification: The Contractor certifies that it is not barred pursuant to 30
Illinois Compiled Statutes 500/50-10 from conducting business with the State of
Illinois or any agency as a result of being convicted of a felony.
Barred from Contracting: The Contractor certifies that it has not been barred from
contracting as a result of a conviction for bid-rigging or bid rotating under 720 Illinois
Compiled Statutes 5/33E or similar law of another state.
Drug Free Workplace: The Contractor certifies that it is in compliance with the Drug
Free Workplace Act (30 Illinois Compiled Statutes 580) as of the effective date of
this contract. The Drug Free Workplace Act requires, in part, that Contractors, with
25 or more employees certify and agree to take steps to ensure a drug free
workplace by informing employees of the dangers of drug abuse, of the availability
of any treatment or assistance program, of prohibited activities and of sanctions that
will be imposed for violations; and that individuals with contracts certify that they will
not engage in the manufacture, distribution, dispensation, possession, or use of a
controlled substance in the performance of the contract.
Non-Discrimination, Certification, and Equal Employment Opportunity: The
Contractor agrees to comply with applicable provisions of the Illinois Human Rights
Act (775 Illinois Compiled Statutes 5), the U.S. Civil Rights Act, the Americans with
Disabilities Act, Section 504 of the U.S. Rehabilitation Act and the rules applicable
to each. The equal opportunity clause of Section 750.10 of the Illinois Department
of Human Rights Rules is specifically incorporated herein. The Contractor shall
comply with Executive Order 11246, entitled Equal Employment Opportunity, as
amended by Executive Order 11375, and as supplemented by U.S. Department of
Labor regulations (41 C.F.R. Chapter 60). The Contractor agrees to incorporate this
clause into all subcontracts under this Contract.
International Boycott: The Contractor certifies that neither it nor any substantially
owned affiliated company is participating or shall participate in an international
boycott in violation of the provisions of the U.S. Export Administration Act of 1979 or
the regulations of the U.S. Department of Commerce promulgated under that Act
(30 ILCS 582).
Record Retention and Audits: If 30 Illinois Compiled Statutes 500/20-65 requires
the Contractor (and any subcontractors) to maintain, for a period of 3 years after the
later of the date of completion of this Contract or the date of final payment under the
Contract, all books and records relating to the performance of the Contract and
necessary to support amounts charged to the City under the Contract. The Contract
and all books and records related to the Contract shall be available for review and
audit by the City and the Illinois Auditor General. If this Contract is funded from
contract/grant funds provided by the U.S. Government, the Contract, books, and
UNITED CITY OF YORKVILLE YBSD WATER MAIN EXTENSION
PAGE 4
records shall be available for review and audit by the Comptroller General of the
U.S. and/or the Inspector General of the federal sponsoring agency. The Contractor
agrees to cooperate fully with any audit and to provide full access to all relevant
materials.
United States Resident Certification: (This certification must be included in all
contracts involving personal services by non-resident aliens and foreign entities in
accordance with requirements imposed by the Internal Revenue Services for
withholding and reporting federal income taxes.) The Contractor certifies that he/she
is a: x United States Citizen ___ Resident Alien ___ Non-Resident Alien The
Internal Revenue Service requires that taxes be withheld on payments made to non-
resident aliens for the performance of personal services at the rate of 30%.
Tax Payer Certification : Under penalties of perjury, the Contractor certifies that its
Federal Tax Payer Identification Number or Social Security Number is (provided
separately) and is doing business as a (check one): ___ Individual ___ Real
Estate Agent ___ Sole Proprietorship ___ Government Entity ___ Partnership
___ Tax Exempt Organization (IRC 501(a) only) x Corporation ___ Not for Profit
Corporation ___ Trust or Estate ___ Medical and Health Care Services Provider
Corp.
I. Indemnification:
Contractor shall indemnify and hold harmless the City and City’s agents, servants,
and employees against all loss, damage, and expense which it may sustain or for
which it will become liable on account of injury to or death of persons, or on account
of damage to or destruction of property resulting from the performance of work under
this agreement by Contractor or its Subcontractors, or due to or arising in any
manner from the wrongful act or negligence of Contractor or its Subcontractors of
any employee of any of them. In the event that the either party shall bring any suit,
cause of action or counterclaim against the other party, the non-prevailing party shall
pay to the prevailing party the cost and expenses incurred to answer and/or defend
such action, including reasonable attorney fees and court costs. In no event shall
either party indemnify any other party for the consequences of that party’s
negligence, including failure to follow the ENGINEER’s recommendations.
J. Insurance:
The ENGINEER agrees that it has either attached a copy of all required insurance
certificates or that said insurance is not required due to the nature and extent of the
types of services rendered hereunder. (Not applicable as having been previously
supplied)
UNITED CITY OF YORKVILLE YBSD WATER MAIN EXTENSION
PAGE 5
K. Additional Terms or Modification:
The terms of this agreement shall be further modified as provided in the attached
Exhibits. Except for those terms included on the Exhibits, no additional terms are
included as a part of this agreement. All prior understandings and agreements
between the parties are merged into this agreement, and this agreement may not
be modified orally or in any manner other than by an agreement in writing signed by
both parties. In the event that any provisions of this agreement shall be held to be
invalid or unenforceable, the remaining provisions shall be valid and binding on the
parties. The list of Attachments are as follows:
Attachment A: Standard Terms and Conditions
Attachment B: Scope of Services
Attachment C: Estimate of Level of Effort and Associated Cost
Attachment D: Anticipated Project Schedule
Attachment E: Location Map
Attachment F: 2024 Standard Schedule of Charges
L. Notices:
All notices required to be given under the terms of this agreement shall be given by
mail, addressed to the parties as follows:
For the City: For the ENGINEER:
City Administrator and City Clerk Engineering Enterprises, Inc.
United City of Yorkville 52 Wheeler Road
651 Prairie Pointe Drive Sugar Grove Illinois 60554
Yorkville, IL 60560
Either of the parties may designate in writing from time to time substitute addresses
or persons in connection with required notices.
Agreed to this ___day of _________, 2024.
United City of Yorkville: Engineering Enterprises, Inc.:
_________________________________ ______________________________
John Purcell Brad Sanderson, P.E.
Mayor Chief Operating Officer / President
_________________________________ ______________________________
Jori Behland Angie Smith
City Clerk Executive Assistant
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 1
STANDARD TERMS AND CONDITIONS
Agreement: These Standard Terms and Conditions, together with the Professional Services Agreement, constitute the entire
integrated agreement between the OWNER and Engineering Enterprises, Inc. (EEI) (hereinafter “Agreement”), and take precedence
over any other provisions between the Parties. These terms may be amended, but only if both parties consent in writing.
Standard of Care: In providing services under this Agreement, the ENGINEER will endeavor to perform in a matter consistent with
that degree of care and skill ordinarily exercised by members of the same profession currently practicing under same circumstances
in the same locality. ENGINEER makes no other warranties, express or implied, written or oral under this Agreement or otherwise, in
connection with ENGINEER’S service.
Construction Engineering and Inspection: The ENGINEER shall not supervise, direct, control, or have authority over any
contractor work, nor have authority over or be responsible for the means, methods, techniques sequences, or procedures of
construction selected or used by any contractor, or the safety precautions and programs incident thereto, for security or safety of the
site, nor for any failure of a contractor to comply with laws and regulations applicable to such contractor’s furnishing and performing
of its work.
The ENGINEER neither guarantees the performance of any contractor nor assumes responsibility for contractor’s failure to furn ish
and perform the work in accordance with the contract documents.
The ENGINEER is not responsible for the acts or omissions of any contractor, subcontractor, or supplies, or any of their agents or
employees or any other person at the site or otherwise furnishing or performing any work.
Shop drawing and submittal review by the ENGINEER shall apply to only the items in the submissions and only for the purpose of
assessing if upon installation or incorporation in the project work they are generally consistent with the construction docum ents.
OWNER agrees that the contractor is solely responsible for the submissions and for compliance with the construction documents.
OWNER further agrees that the ENGINEER’S review and action in relation to these submissions shall not constitute the provisio n of
means, methods, techniques, sequencing or procedures of construction or extend or safety programs or precautions. The
ENGINEER’S consideration of a component does not constitute acceptance of the assembled items.
The ENGINEER’S site observation during construction shall be at the times agreed upon in the Project Scope. Through standard,
reasonable means the ENGINEER will become generally familiar with observable completed work. If the ENGINEER observes
completed work that is inconsistent with the construction documents, that information shall be communicated to the contractor
and OWNER for them to address.
Opinion of Probable Construction Costs: ENGINEER’S opinion of probable construction costs represents ENGINEER’S best and
reasonable judgment as a professional engineer. OWNER acknowledges that ENGINEER has no control over construction costs of
contractor’s methods of determining pricing, or over competitive bidding by contractors, or of market conditions or changes thereto.
ENGINEER cannot and does not guarantee that proposals, bids or actual construction costs will not vary from ENGINEER’S opinio n
of probable construction costs.
Copies of Documents & Electronic Compatibility: Copies of Documents that may be relied upon by OWNER are limited to the
printed copies (also known as hard copies) that are signed or sealed by the ENGINEER. Files in electronic media format of text, data,
graphics, or of other types that are furnished by ENGINEER to OWNER are only for convenience of OWNER. Any conclusion or
information obtained or derived from such electronic files will be at the user's sole risk. When transferring documents in el ectronic
media format, ENGINEER makes no representations as to long term compatibility, usability, or readability of documents resulting from
the use of software application packages, operating systems, or computer hardware differing from those used by ENGINEER at th e
beginning of the project.
Changed Conditions: If, during the term of this Agreement, circumstances or conditions that were not originally contemplated by or
known to the ENGINEER are revealed, to the extent that they affect the scope of services, compensation, schedule, allocation of
risks, or other material terms of this Agreement, the ENGINEER may call for renegotiation of appropriate portions of this Agreement.
The ENGINEER shall notify the OWNER of the changed conditions necessitating renegotiation, and the ENGINEER and the OWNER
shall promptly and in good faith enter into renegotiation of this Agreement to address the changed conditions. If terms cannot be
agreed to, the parties agree that either party has the absolute right to terminate this Agreement, in accordance with the termination
provision hereof.
Hazardous Conditions: OWNER represents to ENGINEER that to the best of its knowledge no Hazardous Conditions
(environmental or otherwise) exist on the project site. If a Hazardous Condition is encountered or alleged, ENGINEER shall have the
obligation to notify OWNER and, to the extent of applicable Laws and Regulations, appropriate governmental officials. It is
acknowledged by both parties that ENGINEER's scope of services does not include any services related to a Hazardous Condition.
In the event ENGINEER or any other party encounters a Hazardous Condition, ENGINEER may, at its option and without liability for
consequential or any other damages, suspend performance of services on the portion of the project affected thereby until OWNER:
(i) retains appropriate specialist consultant(s) or contractor(s) to identify and, as appropriate, abate, remediate, or remove the
Hazardous Condition; and (ii) warrants that the project site is in full compliance with applicable Laws and Regulations.
Consequential Damages: Notwithstanding any other provision of this Agreement, and to the fullest extent permitted by law, neither
the OWNER nor the ENGINEER, their respective officers, directors, partners, employees, contractors, or subcontractors shall be liable
to the other or shall make any claim for any incidental, indirect, or consequential damages arising out of or connected in any way to
the Project or to this Agreement. This mutual waiver of consequential damages shall include, but is not limited to, loss of use, loss of
ENGINEERING ENTERPRISES, INC. JUNE 2024
PAGE 2
profit, loss of business, loss of income, loss of reputation, or any other consequential damages that either party may have i ncurred
from any cause of action including negligence, strict liability, breach of contract, and breach of strict or implied warran ty. Both the
OWNER and the ENGINEER shall require similar waivers of consequential damages protecting all the entities or persons named
herein in all contracts and subcontracts with others involved in this project.
Termination: This Agreement may be terminated for convenience, without cause, upon fourteen (14) days written notice of either
party. In the event of termination, the ENGINEER shall prepare a final invoice and be due compensation as set forth in the Professional
Services Agreement for all costs incurred through the date of termination.
Either party may terminate this Agreement for cause upon giving the other party not less than seven (7) calendar days’ written notice
for the following reasons:
(a) Substantial failure by the other party to comply with or perform in accordance with the terms of the Agreement
and through no fault of the terminating party;
(b) Assignment of the Agreement or transfer of the project without the prior written consent of the other party;
(c) Suspension of the project or the ENGINEER’S services by the OWNER for a period of greater than ninety (90)
calendar days, consecutive or in the aggregate.
(d) Material changes in the conditions under which this Agreement was entered into, the scope of services or the
nature of the project, and the failure of the parties to reach agreement on the compensation and schedule
adjustments necessitated by such changes.
Payment of Invoices: Invoices are due and payable within 30 days of receipt unless otherwise agreed to in writing.
Third Party Beneficiaries: Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in
favor of a third party against either the OWNER or the ENGINEER. The ENGINEER’S services under this Agreement are being
performed solely and exclusively for the OWNER’S benefit, and no other party or entity shall have any claim against the ENGINEER
because of this Agreement or the performance or nonperformance of services hereunder. The OWNER and ENGINEER agree to
require a similar provision in all contracts with contractors, subcontractors, vendors and other entities involved in this Project to car ry
out the intent of this provision.
Force Majeure: Each Party shall be excused from the performance of its obligations under this Agreement to the extent that such
performance is prevented by force majeure (defined below) and the nonperforming party promptly provides notice of such prevention
to the other party. Such excuse shall be continued so long as the condition constituting force majeure continues. The party affected
by such force majeure also shall notify the other party of the anticipated duration of such force majeure, any actions b eing taken to
avoid or minimize its effect after such occurrence, and shall take reasonable efforts to remove the condition constituting su ch force
majeure. For purposes of this Agreement, “force majeure” shall include conditions beyond the control of the parties, including an act
of God, acts of terrorism, voluntary or involuntary compliance with any regulation, law or order of any government, war, acts of war
(whether war be declared or not), labor strike or lock-out, civil commotion, epidemic, failure or default of public utilities or common
carriers, destruction of production facilities or materials by fire, earthquake, storm or like catastrophe. The payment of in voices due
and owing hereunder shall in no event be delayed by the payer because of a force majeure affecting the payer.
Additional Terms or Modification: All prior understandings and agreements between the parties are merged into this Agreement,
and this Agreement may not be modified orally or in any manner other than by an Agreement in writing signed by both parties. In the
event that any provisions of this Agreement shall be held to be invalid or unenforceable, the remaining provisions shall be valid and
binding on the parties.
Assignment: Neither party to this Agreement shall transfer or assign any rights or duties under or interest in this Agreement without
the prior written consent of the other party. Subcontracting normally contemplated by the ENGINEER shall not be considered an
assignment for purposes of this Agreement.
Waiver: A party’s waiver of, or the failure or delay in enforcing any provision of this Agreement shall not constitute a waiver of th e
provision, nor shall it affect the enforceability of that provision or of the remainder of this Agreement.
Attorney’s Fees: In the event of any action or proceeding brought by either party against the other under this Agreement, the
prevailing party shall be entitled to recover from the other all costs and expenses including without limitation the reasonab le fees of
its attorneys in such action or proceeding, including costs of appeal, if any, in such amount as the Court may adjudge reasonable.
Fiduciary Duty: Nothing in this Agreement is intended to create, nor shall it be construed to create, a fiduciary duty owed to either
party to the other party. EEI makes no warranty, express or implied, as to its professional services rendered.
Headings: The headings used in this Agreement are inserted only as a matter of convenience only, and in no way define, limit,
enlarge, modify, explain or define the text thereof nor affect the construction or interpretation of this Agreement.
Attachment B – Scope of Services
YBSD Water Main Extension
United City of Yorkville
The United City of Yorkville intends to install approximately 780 linear feet of 12-inch water main
improvements extending from Center Street to the future YBSD expansion location on River Street, including
the crossing of Blackberry Creek.
Our proposed scope of services for Construction Engineering will include the following:
3.1 Construction Administration
• Prepare for, Attend, and Facilitate the Preconstruction Meeting with the Contractor Including
Preparation of Meeting Minutes
• Shop Drawing Review
• Review Engineering Plans, Specifications and Prepare Field Book
• Prepare Pay Estimates and Change Orders
• Gather Invoices and Waivers of Lien
• Provide Weekly Updates to City or as Required Based on Onsite Activities
3.2 Construction Layout and Record Drawings
• Stake Proposed Water Main
• Perform Post Construction Field Survey for Record Drawings
• Prepare and Review Record Drawings
3.3 Construction Observation and Documentation
• Review Staked Water Main
• Take Pre-Construction Videos and Photos of Pre-Existing Conditions
• Provide Resident Engineering Services for Construction
• Coordinate Any Required Testing on Behalf of the City and Review Test Reports
• Provide Quantity Tracking, Documentation, and Daily Field Reports
• Perform Punch Walks, Prepare Punch List Letters, and Provide Follow Up Inspections and
Recommend Acceptance When Appropriate (2 Each)
• Prepare Project Closeout Paperwork
The following scope of services will be provided by EEI’s Subconsultant:
• Rubino Engineering – Material Testing for Quality Assurance
• Hey & Associates – Wetland Monitoring & Maintenance (5 year duration)
• Hey & Associates – ITA Fish Sampling (2025 only)
Exclusions:
• Water Quality Certification (if required by USACE)
• ITA Fish Sampling beyond 2025
The above scope for “YBSD Water Main Extension” summarizes the work items that will be
completed for this contract. Additional work items, including additional meetings beyond the
meetings defined in the above scope, shall be considered outside the scope of the base contract
and will be billed in accordance with the Standard Schedule of Charges.
ATTACHMENT C: ESTIMATE OF LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
CLIENT PROJECT NUMBER
United City of Yorkville YO2327-P
PROJECT TITLE DATE PREPARED BY
YBSD Water Main Extension 6/11/24
ROLE PIC PM PE PT PM SPT2 INTERN ADMIN
RATE $246 $210 $168 $153 $210 $175 $82 $72
CONSTRUCTION ENGINEERING
3.1 Contract Administration - 17 - 16 - - - - 33 6,018$
3.2 Construction Layout and Record Drawings - 2 - 2 2 15 5 - 26 4,181$
3.3 Observation and Documentation 2 20 - 229 - - - - 251 39,729$
Construction Engineering Subtotal:2 39 - 247 2 15 5 - 310 49,928$
2 39 - 247 2 15 5 - 310 49,928
DIRECT EXPENSES
Vehicle =-$
Material Testing = 1,000$
Monitoring & Maintenance = 15,000$
ITA Fish Sampling =9,000$
DIRECT EXPENSES =25,000$
LABOR SUMMARY
EEI Labor Expenses = 46,473$
Surveying Expenses = 3,455$
Drafting Expenses = -$
TOTAL LABOR EXPENSES 49,928$
TOTAL COSTS 74,928$
52 Wheeler Road, Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
PROJECT TOTAL:
KDW
COSTTASK
NO.TASK DESCRIPTION HOURS
ATTACHMENT D: ESTIMATED SCHEDULE
CLIENT
United City of Yorkville
PROJECT TITLE
YBSD Water Main Extension
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
CONSTRUCTION ENGINEERING
3.1 Contract Administration
3.2 Construction Layout and Record Drawings
3.3 Observation and Documentation - Water Main
52 Wheeler Road Sugar Grove, IL 60554 Tel: 630.466.6700 Fax: 630.466.6701 www.eeiweb.com
TASK
NO.TASK DESCRIPTION July August September
PROJECT NUMBER
DATE
YO2327-P
November
6/11/2024
PREPARED BY
KDW
2024
DecemberOctober
()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-
()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-()-W River StWest StKing StW Center St
W Main St
Engineering Enterprises, Inc.52 Wheeler RoadSugar Grove, Illinois 60554(630) 466-6700
ATTACHMENT EPROJECT LIMITSwww.eeiweb.com DATE
DATE:
PROJECT NO.:
FILE:
PATH:
BY:
JUNE 2024
YO2104
H:\GIS\PUBLIC\YORKVILLE\2022\
KJD
NO.REVISIONS ³United City of Yorkville
651 Prairie Pointe DrYorkville, IL 60560
www.yorkville.il.us
400 0200 Feet
Legend
UNKNOWN WATER MAIN3" WATER MAIN AND SMALLER
4" WATER MAIN
6" WATER MAN
8" WATER MAIN
10" WATER MAIN
12" WATER MAIN
16" WATER MAIN
!(VALVE
GF HYDRANT
YO2104_YBSD_Water_Main_Extrention E
PROPOSED 12"WATER MAIN
YBSD WATER MAIN EXTENTION
YBSD
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE Senior Principal E-4 $246.00 Principal E-3 $241.00 Senior Project Manager E-2 $234.00 Project Manager E-1 $210.00 Senior Project Engineer/Surveyor II P-6 $200.00 Senior Project Engineer/Surveyor I P-5 $186.00 Project Engineer/Surveyor P-4 $168.00 Senior Engineer/Surveyor P-3 $155.00 Engineer/Surveyor P-2 $140.00 Associate Engineer/Surveyor P-1 $127.00 Senior Project Technician II T-6 $175.00 Senior Project Technician I T-5 $164.00 Project Technician T-4 $153.00 Senior Technician T-3 $140.00 Technician T-2 $127.00 Associate Technician T-1 $111.00 GIS Technician II G-2 $125.00 GIS Technician I G-1 $114.00 Engineering/Land Surveying Intern I-1 $ 82.00 Executive Administrative Assistant A-4 $ 77.00 Administrative Assistant A-3 $ 72.00
VEHICLES. REPROGRAPHICS, DIRECT COSTS, DRONE AND EXPERT TESTIMONY
Vehicle for Construction Observation $ 20.00
In-House Scanning and Reproduction $0.25/Sq. Ft. (Black & White)
$1.00/Sq. Ft. (Color)
Reimbursable Expenses (Direct Costs) Cost
Services by Others (Direct Costs) Cost + 10%
Unmanned Aircraft System / Unmanned Aerial Vehicle / Drone $ 225.00
Expert Testimony $ 275.00
STANDARD SCHEDULE OF CHARGES ~ JANUARY 1, 2024