Resolution 2025-063Resolution No. 2025-63 A RESOLUTION OF THE UNITED CITY OF YORKVILLE, KENDALL COUNTY, ILLINOIS APPROVING A SECOND CHANGE ORDER RELATING TO THE SOUTHERN SANITARY SEWER CONNECTION WHEREAS, the United City of Yorkville (the "City") is a duly organized and validly existing non home -rule municipality created in accordance with the Constitution of the State of Illinois of 1970 and the laws of the State; and WHEREAS, the City had approved a contract in the amount of $826,384.00 with Fischer Excavating, Inc. ("Fischer"), for a project commonly known as the Southern Sanitary Sewer Connection (the "Project"); and WHEREAS, an earlier change order, approved by Resolution No. 2025-46, adopted March 25, 2025, increased the total price of the Project to $915,066.00; and WHEREAS, C1 Yorkville, LLC, a Delaware limited liability company ("C1 Yorkville") has agreed to pay the costs of the Proj ect, as it is necessary to a data center project that C 1 Yorkville plans to develop; and WHEREAS, the price of the Project has since increased in the amount of $85,000.00 (the "Change Order") as, due to the size and number of boulders encountered while Fischer was constructing the Project, the casing used in the Project must be increased from 20" to 30" and additional work will result from increasing the size of the casing; and WHEREAS, all change orders increasing or decreasing the cost of a public contract by at least $25,000 must meet the required findings that circumstances necessitating the change were not reasonably foreseeable at the time the contract was signed; or the change is germane to the original contract as signed; or the Change Order is in the best interest of the City as required by Section 33E-9 of the Illinois Criminal Code (720 ILCS 5133E-9); and Resolution No. 2025-63 Page I WHEREAS, it has been recommended to the Mayor and City Council (the "Corporate Authorities") that a Change Order increasing the total contract price to the amount of $1,000,066.00 was not reasonably foreseeable at the time the contract was signed, as set forth in the proposal from Fischer. NOW, THEREFORE, BE IT RESOLVED by the Mayor and City Council of the United City of Yorkville, Kendall County, Illinois: Section 1. The foregoing recitals are hereby incorporated in this Resolution as the findings of the Corporate Authorities. Section 2. The Corporate Authorities hereby find and declare that Change Order No. 2 to the Southern Sanitary Sewer Connection contract with Fischer Excavating, Inc., which results in a total increase in the amount of $85,000.00, is required and that such increase is in the best interests of the City. Section 3. The Change Order is hereby approved, and the City Administrator is authorized to execute the Change Order as hereinabove identified. Section 4. That this resolution shall be in full force and effect from and after its passage and approval according to law. [Remainder of Page Intentionally Blank; Roll Call Vote to Follow] Resolution No. 2025-63 Page 2 Passed by the City Council of the United City of Yorkville, Kendall County, Illinois this 27`� day of May, A.D. 2025. QN - 1k, 6wav(- L�y CLERK KEN KOCH AYE DAN TRANSIER ABSENT ARDEN JOE PLOCHER ABSENT CRAIG SOLING AYE CHRIS FUNKHOUSER AYE MATT MAREK AYE RUSTY CORNEILS AYE RUSTY HYETT AYE APPROVED` ,by me, as Mayor of the United City of Yorkville, Kendall County, Illinois this day of ��Qll� , A.D. 2025. MAYOR Attest: JUMOK Y CLERK Resolution No. 2025-63 Page 3 CHANGE ORDER Order No. 2 Date: May 20, 2025 Agreement Date: January 17 2025 NAME OF PROJECT: Southern Sanitary Sewer Connection OWNER: United City of Yorkville CONTRACTOR: Fischer Excavating, Inc. The following changes are hereby made to the CONTRACT DOCUMENTS: 1) Upsize steel casing to 30-inches in diameter $85,000.00 Change of CONTRACT PRICE. - Original CONTRACT PRICE: $ 826,384.00 Current CONTRACT PRICE adjusted by previous CHANGE ORDER(S) $ 915,066.00 The CONTRACT PRICE due to this CHANGE ORDER will be (increased)(�'^�ed) by: $ 85, 000.00 The new CONTRACT PRICE including this CHANGE ORDER will be $ 1,000,066.00 Justification: 1) During the casing installation under Rob Roy Creek, several small boulders were encountered. These boulders drastically slowed the progress of the work and resulted in the Contractor spending one whole day advancing the 20-inch casing only 10-feet. Thus, it is recommended that the casing be upsized to 30-inch diameter so these obstructions can be more easily removed. Otherwise, there will be a significant cost increase to shut down the progress of the work while they are removed via other means. Change to CONTRACT TIME: The contract time is increased/decreased by 0 days. Requested by: Recommended by: Accepted by: 5-13c)(25 rises. Inc. LaAgendas - Packets\Packets\2025 Packet$\Public VVorks105-20-251Southern Sanitary Sewer Change Order 213. Change Order 2.doc CHANGE ORDER Order No. 2 Date: May 20 2025 Agreement Date: JgnWary 17 2025 NAME OF PROJECT: Southern Sanitary Sewer Connection OWNER: United CiN of Yorkville CONTRACTOR: Fischer Excavatin , Joe. The following changes are hereby made to the CONTRACT DOCUMENTS: 1) Upsize steel casing to 30-inches in diameter $85,000.00 Chanae of CONTRACT PRIG; Original CONTRACT PRICE: $ 826 384.00 Current CONTRACT PRICE adjusted by previous CHANGE ORDER(S) $ 915 066.00 The CONTRACT PRICE due to this CHANGE ORDER will be (increased)(desr$ased) by: $ 85.000.00 The new CONTRACT PRICE including this CHANGE ORDER will be $ 1.000 066.00 Justificatiorl: 1) During the casing installation under Rob Roy Creek, several small boulders were encountered. These boulders drastically slowed the progress of the work and resulted in the Contractor spending one whole day advancing the 20-inch casing only 10-feet. Thus, it is recommended that the casing be upsized to 30-inch diameter so these obstructions can be more easily removed. Otherwise, there will be a significant cost increase to shut down the progress of the work while they are removed via other means. Change t9 CONTRACT TIM : The contract t Requested by Recommende Accepted by: United it of orkville \\MILKYWAY\EEI_Storage\Docs\Public\Yorkville\2023\YO2321-P Southern Sanitary Sewer Connection\Construction\Pay Estimates and Quantities\Change Orders\Change Order No. 2 Increase Casing Size\3. Change Order 2.doc