HomeMy WebLinkAboutPublic Works Committee Minutes 2025 10-21-25APPROVED 11/18/25
Page 1 of 3
UNITED CITY OF YORKVILLE
PUBLIC WORKS COMMITTEE
Tuesday, October 21, 2025, 6:00pm
Yorkville City Hall, East Conference Room #337
651 Prairie Pointe Drive, Yorkville, IL
IN ATTENDANCE:
Committee Members
Chairman Craig Soling Alderman Dan Transier
Alderman Rusty Corneils Alderman Joe Plocher (arr. 6:08pm)
Other City Officials
City Administrator Bart Olson Assistant City Administrator Erin Willrett via Zoom
Engineer Brad Sanderson, EEI Assistant Public Works Director John Sleezer
Public Works Director Eric Dhuse
Other Guests:
Dave Hubert, Fox Highlands Janice Triptow (via Zoom)
The meeting was called to order at 6:00pm by Chairman Craig Soling.
Citizen Comments:
Mr. Dave Hubert of Kingsmill St. in Ward 1 commented on the water audit and efforts regarding unaccounted
water use. He referred to reports from the August and September meetings and explained that he interprets the
data differently. From 2012 through 2021, he said there is a consistent pattern of pumped water and
unaccounted water ranging from 10-12%. It was 600 million gallons pumped in 2020 and 12% unaccounted
which equals 72 million gallons. He said any incremental growth comes from new residents and other usage
would remain approximately the same. In 2023-2024 the loss grew to 14% with 700 millions gallons pumped.
Using past calculations, that resulted in a 28% increase in the losses and with no additional water main breaks.
He believes this calculation needs to be evaluated. He said the figures were consistent for 10 years before it rose
dramatically. He does not believe it is a software problem. He believes the city is actually losing much more
water than in previous years. Mr. Olson will consult with staff and respond to these questions.
Previous Meeting Minutes: September 16, 2025
The minutes were approved as presented.
New Business:
1. PW 2025-94 Quarterly Bond and Letter of Credit Reduction Summary
This is the standard report with no new activity and is informational.
2. PW 2025-95 Capital Improvement Projects Update
Mr. Sanderson said the memo highlights the projects being done. He said 3 of the utility projects related to
Cyrus 1 are almost complete. The 2025 water main replacement project on the south side of the river is moving
along and it is expected all replacements will be done before the end of the year. He said some of the paving
work will be pushed to next year. Also, the east alley water main replacement should be done a couple weeks. I
addition, the NW tank and south standpipe, both relating to the Lake Michigan water project, will be started in
the next couple weeks. The Road to Better Roads program paving is finished.
Page 2 of 3
3. PW 2025-96 Water Reports for January 2025 – September 2025
Director Dhuse said these are the monthly summaries and by IEPA rules, must be adopted by the City Council.
The October report reflects the 1.5 million gallon water loss from the large water main break on Crooked Creek.
He said there were many new accounts. Chairman Soling asked for more details about the Crooked Creek water
main break and Mr. Dhuse replied that there were small holes in the pipe, but the pipe broke very suddenly.
There were 2 breaks back-to-back which were repaired. He said 105 feet of new pipe will be installed to
replace the 1989 pipe. This item moves to the consent agenda.
4. PW 2025-97 BNSF Agreement (Quiet Zone)
Engineer Sanderson said this item was first discussed in September and he recalled the steps that need to be
taken for quiet zones. He said BNSF now charges $28,000 for their work to establish quiet zones. This item
will move forward to the regular agenda.
5. PW 2025-98 South Receiving Station – Contract Award
Bids were received on October 7th for the south receiving station. A similar number of bids was received as was
for the north station. Whittaker Construction was the low bidder at $6,875,000 and they were also the low
bidder for the north station. Mr. Sanderson recommended awarding them the bid and the item moves to the
regular agenda.
(Discussion on items #6 & #7 was reversed)
6. PW 2025-99 Resolution Approving an Engineering Agreement with Engineering Enterprises, Inc.
(South Receiving Station – Construction Engineering)
Mr. Dhuse said this is the accompanying agreement for item #5 and will authorize Engineering Enterprises to
oversee this project. The budgeted cost is $362,000 and will be spread over 3 fiscal years. This moves to the
consent agenda with committee approval.
7. PW 2025-100 Resolution Approving An Agreement By and Between the United City of Yorkville and the
State of Illinois Acting By and Through the Department of Transportation (IL Route 47/US Route 30
– Waterpark Way to Jericho Road)
This item is related to a previously passed inter-governmental agreement, said Mr. Sanderson. With the
expansion of Rt. 47 from Jericho to Waterpark Way, some of the improvements conflict with city water main in
an existing easement. The agreement says that the state will pay for the construction. The design cost was
inadvertently omitted from the agreement and this agreement will cover that cost. The committee was OK with
this and it will move to the consent agenda.
8. PW 2025-101 2025 Water Main Replacement – Change Order No. 2
Engineer Sanderson said this is about 70% complete and funded by IEPA. The IEPA was slower getting the
loans out and the project did not start as early as hoped. November was the original finish date, however, he
recommends the new completion date of June 2026 to allow for the paving to occur in the next construction
season. He recommends acceptance and there is no difference in price. This will move to the consent agenda
with committee approval.
9. PW 2025-102 Water Meter Replacement - Phase II
Mr. Dhuse gave this update. He said approximately 900 of the 1,200 meters in the first phase have been
replaced. The infrastructure on top of the water tower was also changed in the first phase. Almost 4,000 meters
will be changed out in Phase II. Some of these meters are now 25 years old. This should help get under the 10%
water loss needed. When finished, all will be able to be radio-read remotely and anytime with accuracy. The
same company will do the changeout. He said it is important to have this done now to have a full year of water
data by October 2027. He said the complete changeout of meters should be done by October 1, 2026. City staff
will do the replacement if residents are having issues with their meters, but the company will do the bulk of the
replacements. This will move to the regular agenda.
Page 3 of 3
10. PW 2025-103 Caledonia Phase 3 – Acceptance
The punchlist items and infrastructure are complete and Mr. Sanderson recommends acceptance. There is a one-
year guarantee and a re-inspection will be done at 8 months. This moves to the consent agenda.
11. PW 2025-104 Grande Reserve – Unit 12 Bond Release
12. PW 2025-105 Grande Reserve – Unit 15 Bond Release
13. PW 2025-106 Grande Reserve – Unit 22 Bond Release
These 3 items were discussed simultaneously. Mr. Sanderson said all are on the 1-year maintenance phase and
some items were corrected, but all work is now complete and he recommended bond release for all 3. These
items move to the consent agenda.
14. PW 2025-107 Grande Reserve – Unit 28 Plat of Easement Grant
This apartment complex is located north of railroad tracks. There are water mains and sanitary sewer installed
and will be public. Easements are needed and Mr. Sanderson recommends approval of the agreements for the
easements. This also moves to the consent agenda.
15. PW 2025-108 2024 Water Main Replacement - Contracts A and B – WIFIA Change Orders
Finance Director Rob Fredrickson compiled a memo for the packet which gave the reason for the Change Order.
These 2 projects were not included in the original WIFIA package and 24 projects are now desired to be included
in the WIFIA package. Adjustments are needed to the 2 contracts, language needs to be added to the
construction contract and language needs to be added to the design construction and engineering agreements.
When the Change Orders are approved, they can be rolled into the original WIFIA package with no dollar
change. Mr. Sanderson recommended acceptance and this moves to the consent agenda.
16. PW 2025-109 Water Audit and Non-Revenue Water Reduction Consultation – Agreement for
Professional Services
Mr. Olson said this is an agreement with Engineering Enterprises to conduct the water audit as a requirement of
the Lake Michigan allocation permit and also includes a cleanup of the 2024 report. It is an estimated cost of
$49,800 which is budgeted and he recommends approval. This moves to the regular agenda.
17. PW 2025-110 Meeting Schedule for 2026
The committee approved the schedule at committee level.
18. PW 2025-111 Windett Ridge Road and Fairfax Way Traffic Control Study
Mr. Olson said the Mayor had received a citizen complaint about speeding at this location. The Mayor felt there
should be a 4-way stop and after an analysis was done, it was determined the stop is warranted. Staff
recommends the 4-way stop and a nearby branch will be trimmed by the city. This will move to the consent
agenda with committee approval.
Old Business:
1. PW 2025-62 Resolution Approving an Engineering Agreement with Engineering Enterprises, Inc.
(2025 Stormwater Basin Inspections)
Mr. Olson said there is no update on this yet. He said the city has been doing these inspections on a base
contract and approving hourly increases where needed. The inspections are using the hours of the basic contract
and it was decided to make this a separate contract. The Mayor has concerns about the trees in the basin and
does not want them removed unless necessary. This will be placed on the consent agenda.
Additional Business: None
There was no further business and the meeting adjourned at 6:33pm.
Minutes respectfully transcribed by
Marlys Young, Minute Taker